5 PMP - Process Definitions Flashcards
Which process is this?
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Develop Project Charter
Which process is this?
The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project’s integrated baselines and subsidiary plans may be included within the project management plan.
Develop Project Management Plan
Which process is this?
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project’s objectives.
Direct and Manage Project Work
Which process is this?
The process of tracking, reviewing, and reporting project progress against the performance objectives defined in the project management plan.
Monitor and Control Project Work
Which process is this?
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Perform Integrated Change Control
Which process is this?
The process of finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project.
Close Project or Phase
Which process is this?
The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.
Plan Scope Management
Which process is this?
The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
Collect Requirements
Which process is this?
The process of developing a detailed description of the project and product.
Define Scope
Which process is this?
The process of subdividing project deliverables and project work into smaller, more manageable components.
Create WBS
Which process is this?
The process of formalizing acceptance of the completed project deliverables.
Validate Scope
Which process is this?
The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Control Scope
Which process is this?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Plan Schedule Management
Which process is this?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Define Activities
Which process is this?
The process of identifying and documenting relationships among the project activities.
Sequence Activities
Which process is this?
The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Estimate Activity Resources
Which process is this?
The process of estimating the number of work periods needed to complete individual activities with estimated resources.
Estimate Activity Durations
Which process is this?
The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
Develop Schedule