1
Q

Which Process Group?

Develop Project Charter

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which Process Group?

Develop Project Management Plan

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which Process Group?

Direct and Manage Project Work

A

Executing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which Process Group?

Monitor and Control Project Work

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which Process Group?

Perform Integrated Change Control

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which Process Group?

Close Project or Phase

A

Closing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which Process Group?

Plan Scope Management

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which Process Group?

Collect Requirements

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which Process Group?

Define Scope

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which Process Group?

Create WBS

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which Process Group?

Validate Scope

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which Process Group?

Control Scope

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which Process Group?

Plan Schedule Management

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which Process Group?

Define Activities

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which Process Group?

Sequence Activities

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which Process Group?

Estimate Activity Resources

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which Process Group?

Estimate Activity Durations

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which Process Group?

Develop Schedule

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which Process Group?

Control Schedule

A

Monitoring and Controlling

20
Q

Which Process Group?

Plan Cost Management

A

Planning

21
Q

Which Process Group?

Estimate Costs

A

Planning

22
Q

Which Process Group?

Determine Budget

A

Planning

23
Q

Which Process Group?

Control Costs

A

Monitoring and Controlling

24
Q

Which Process Group?

Plan Quality Management

A

Planning

25
Q

Which Process Group?

Perform Quality Assurance

A

Executing

26
Q

Which Process Group?

Control Quality

A

Monitoring and Controlling

27
Q

Which Process Group?

Plan Human Resource Management

A

Planning

28
Q

Which Process Group?

Acquire Project Team

A

Executing

29
Q

Which Process Group?

Develop Project Team

A

Executing

30
Q

Which Process Group?

Manage Project Team

A

Executing

31
Q

Which Process Group?

Plan Communications Management

A

Planning

32
Q

Which Process Group?

Manage Communications

A

Executing

33
Q

Which Process Group?

Control Communications

A

Monitoring and Controlling

34
Q

Which Process Group?

Plan Risk Management

A

Planning

35
Q

Which Process Group?

Identify Risks

A

Planning

36
Q

Which Process Group?

Perform Qualitative Risk Analysis

A

Planning

37
Q

Which Process Group?

Perform Quantitative Risk Analysis

A

Planning

38
Q

Which Process Group?

Plan Risk Responses

A

Planning

39
Q

Which Process Group?

Control Risks

A

Monitoring and Controlling

40
Q

Which Process Group?

Plan Procurement Management

A

Planning

41
Q

Which Process Group?

Conduct Procurements

A

Executing

42
Q

Which Process Group?

Control Procurements

A

Monitoring and Controlling

43
Q

Which Process Group?

Close Procurements

A

Closing

44
Q

Which Process Group?

Identify Stakeholders

A

Initiating

45
Q

Which Process Group?

Plan Stakeholder Management

A

Planning

46
Q

Which Process Group?

Manage Stakeholder Engagement

A

Executing

47
Q

Which Process Group?

Control Stakeholder Engagement

A

Monitoring and Controlling