Identify Process Groups
Which Process Group?
Develop Project Charter
Initiating
Which Process Group?
Develop Project Management Plan
Planning
Which Process Group?
Direct and Manage Project Work
Executing
Which Process Group?
Monitor and Control Project Work
Monitoring and Controlling
Which Process Group?
Perform Integrated Change Control
Monitoring and Controlling
Which Process Group?
Close Project or Phase
Closing
Which Process Group?
Plan Scope Management
Planning
Which Process Group?
Collect Requirements
Planning
Which Process Group?
Define Scope
Planning
Which Process Group?
Create WBS
Planning
Which Process Group?
Validate Scope
Monitoring and Controlling
Which Process Group?
Control Scope
Monitoring and Controlling
Which Process Group?
Plan Schedule Management
Planning
Which Process Group?
Define Activities
Planning
Which Process Group?
Sequence Activities
Planning
Which Process Group?
Estimate Activity Resources
Planning
Which Process Group?
Estimate Activity Durations
Planning
Which Process Group?
Develop Schedule
Planning
Which Process Group?
Control Schedule
Monitoring and Controlling
Which Process Group?
Plan Cost Management
Planning
Which Process Group?
Estimate Costs
Planning
Which Process Group?
Determine Budget
Planning
Which Process Group?
Control Costs
Monitoring and Controlling
Which Process Group?
Plan Quality Management
Planning
Which Process Group?
Perform Quality Assurance
Executing
Which Process Group?
Control Quality
Monitoring and Controlling
Which Process Group?
Plan Human Resource Management
Planning
Which Process Group?
Acquire Project Team
Executing
Which Process Group?
Develop Project Team
Executing
Which Process Group?
Manage Project Team
Executing
Which Process Group?
Plan Communications Management
Planning
Which Process Group?
Manage Communications
Executing
Which Process Group?
Control Communications
Monitoring and Controlling
Which Process Group?
Plan Risk Management
Planning
Which Process Group?
Identify Risks
Planning
Which Process Group?
Perform Qualitative Risk Analysis
Planning
Which Process Group?
Perform Quantitative Risk Analysis
Planning
Which Process Group?
Plan Risk Responses
Planning
Which Process Group?
Control Risks
Monitoring and Controlling
Which Process Group?
Plan Procurement Management
Planning
Which Process Group?
Conduct Procurements
Executing
Which Process Group?
Control Procurements
Monitoring and Controlling
Which Process Group?
Close Procurements
Closing
Which Process Group?
Identify Stakeholders
Initiating
Which Process Group?
Plan Stakeholder Management
Planning
Which Process Group?
Manage Stakeholder Engagement
Executing
Which Process Group?
Control Stakeholder Engagement
Monitoring and Controlling