4. Project Integration Management Terms Flashcards
Change control system (CCS)
communicates the process for controlling changes to the project deliverables. This system works with the configuration management system and seeks to control and document proposals to change the project’s product
Configuration management system
ТОЛЬКО ЕСЛИ АППРУВЯТСЯ НОВЫЕ FEATURES/FUNCTIONS
- defines how stakeholders are allowed to submit CRs, the conditions for approving a change request, and how approved change requests are validated in the project scope.
- Configuration management also:
documents the characteristics and functions of the products and any changes to a product’s characteristics.
(?) Configuration status accounting
The organization of the product materials, details, and prior product documentation
Configuration verification and auditing
The scope verification and completeness auditing of project or phase deliverables to ensure that they are in alignment with the project plan.
Integrated Change Control Workflow
A process to consider and control the impact of a proposed change on the project’s knowledge areas.
Открытые вопросы:
* После Integrated Change Control также переходит на Approved и пр. (не хватает стрелки?)
* CCB само анализирует анализирует влияние на Scope, Schedule, Cost etc.?