4 Flashcards

1
Q

Wat zijn incremental cash flows

A

Additional cash flows that occur only as a result of taking on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Welke 4 incremental cashflows zijn er
Erosion
Spillover effects
Salvage
Opportunity costs

A

Erosion – demand for a new product cuts into sales of existing products (e.g., new gaming console);
Spillover effects – the project may help the firm’s existing business;
Salvage – when a project comes to an end, assets can be sold or redeployed elsewhere in the business;
Opportunity costs – undertaking the project may require giving up benefits (e.g., piece of land)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Wat is free cash flow

A

Cash that the firm is free to distribute to creditors and stockholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Wat zijn non incremental cash flows
Sunk costs
Overhead costs
Financing costs

A

Sunk cost – past and irreversible outflows (i.e., costs that have been already paid) that cannotbe affected by the decision to accept or reject the project (e.g., already conducted R&D, consulting services);
Overhead cost – expenses associated with running a business that cannot be affected by the decision to accept or reject the project (e.g., rent, utilities, supervisory salaries) → include only the ‘extra’ expenses that would result from the project;
Financing cost – always view the project as if all-equity-financed (e.g., exclude interest paid)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Wat is project free cash flow

A

The incremental effect of a project on the firm’s available cash independent from any financing decision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate project free cash flow

A

Project Free Cash Flow =
Operating Cash Flow (OCF) – Capital Investment – Investment in Working Capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Hoe bereken je operating cash flow

A

The Top-Down Approach (most direct):
Operating Cash Flow = Revenues – Expenses – Taxes
 The Bottom-Up Approach (indirect):
Operating Cash Flow = Net Income + Depreciation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Wat is capital expenditure (Capex)

A

Funds used by a company to acquire, upgrade, and maintain physical assets such as property, plants, buildings, technology, or equipment
Negative cashflow because it is paid upfront

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Hoe bereken je Capex

A

CapEx = ∆PP&E + Current Depreciation
∆PP&E= change in PPE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Wat betekent salavge value

A

When an asset is completely depriciated but it still hass some value
Positive cash flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Hoe gaan investments in working capital aan het begin midden en eind van een project

A

At the beginning of the project’s life:
Investment in inventories (of raw materials or finished products) – negative CF.
Working capital changes during the life of the project!
Increase in accounts receivable – negative CF;
Increase in accounts payable – positive CF.
Investments in net working capital are recovered at the end of the project:
Inventories are sold and accounts receivable collected – positive CF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Hoe evaluate je NPV estimates

A

Scenario analysis – consider a number of (typically five) possible alternative scenarios (in terms of input variables);
Sensitivity analysis – a variation of scenario analysis that probes the sensitivity of the NPV estimate with respect to a single input variable (e.g., sales volume), while all other variables are kept constant;
Simulation analysis – considers a very large number of scenarios by leveraging technology;
Break-even analysis – determines what level of sales are necessary to cover the company’s total fixed costs (the margin of safety)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Wat zijn challenges bij investment decisions

A

Challenge I: The investment timing decision (Should we invest now or later?)
Challenge II: The choice between long- and short-lived equipment
Challenge III: The replacement problem (Should an existing machine be replaced?)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Hoe werkt de investment timing decision

A

A positive NPV project may be more valuable if undertaken in the future:
1. Examine alternative start dates for the investment;
2. Calculate the net future value at each of these dates;
3. Discount these net future values back to present.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Hoe werkt de choice between long- and short-lived equipment

A

EAC= PV of all cashflows/ annuity factor
The lowest cost is better

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Hoe werkt de replacement problem

A

Calculate NPV for both options