All feedback reports requesting change in maintenance responsibilities must be signed by who?
XO
What instruction dictates the requirements for HAZMAT container labeling?
OPNAVINST 5100.19
When can a MIP not applicable to a work center be deleted?
When a Feed Back Report is approved for deletion of MIP
What PQS requires the 301 Craftsman as a pre-requisite?
303 DCPO
What are five exapmles of PPE?
Gloves, face shield, goggles, hearing protection, boots
What is the definition of Status I Inactive Equipment Maintenance (IEM)?
Equipment that will remain on board and will be inactive for 30 days of longer and is not scheduled for corrective maintenance or overhaul
What is the objective of the ship’s #M Preventive Maintenance System (PMS)?
Maintain equipment within specifications through preventive maintenance
How much time does the 3MC have prior to sending out FBR?
4 days
When a FBR is received, safety related PMS updates are required to be implemented?
Within 2 to 5 working days of receipt
What is an ACN?
Advance Change Notice
The ship should _____ when IEM requirements are not justified.
Consider all factors that affect equipment deterioration and take precautionary measures
What must HAZMAT container contain?
As much information as applicable (name, manufacture, stock number, precautions, handling procedures, storage procedures)
What does a circles maintenance requirement on the Quarterly Board signify?
Not Fully Accomplished
Who is overall responsible for the 3M program?
XO
A flip page entry must be made for on the Accountability Sheet for the following PMS checks:
Out of periodicity, rescheduled, deleted, accomplished by a higher authority
When conducting an Equipment Validation and the Manufacture Serial Number is blank, what is used to identify the equipment?
PRID - Positional Reference Identification
When does the Maintenance Person performing PMS sign for accomplishment?
After completion of the maintenance
Who ensures that the ship’s 3M program id functional and meets the required standard to meet the mission?
CO
A maintenance man will be given no more than ___ hours to gather required PMS materials to demonstrate the PMS spot check.
2 hours
At the end of a PMS week, who is required to review Sked accountability log for completeness and accuracy?
WCS, LCPO, DIVO
What is the intent of a spot check?
Ensure the maintenance was completed and correctly performed.
When preparing Equipment Guide Lists (EGL) what must be taken into account?
Have no more than a single days worth of work
When is an Equipment Guide List required?
When a controlling MRC applies to a number of identical items
How many days can a work candidate be in the OMMS Review and Approval queue?
7 days
What is the time line goal of equipment validations on board in regards to equipment and PMS assignments?
5 years
The 3M System Coordinator serves as which of the following?
Serve as the principal 3M assistant to the XO