3.5 Contract Change Flashcards
Supplemental Agreement
Contract mod based on prior agreement of parties regarding the
change
Incorporates equitable adjustment to contract cost and/or
schedule as a result of the change
Three types of contract modifications
Supplemental Agreement
Change Order
Constructive Change
Change Order
Written order issued by CO directing contractor to make a change without prior agreement
Creates “undefinitized” Government liability
Contractor may be entitled to equitable adjustment
Authorized by the “Changes Clause”
Limited to:
- Drawings, designs, or specifications
- Method of shipping or packing
- Increase or decrease in Govt Furnished Property
- Place of delivery
FAR 52.243- 1&2
Constructive Change
Oral or written act (or failure to act) by an authorized Government official in position of authority construed by contractor as having same effect as a written change order (existing contract)
Must involve:
‐ Order: improper word or deed by Government (could be “inaction”)
‐ Acted upon: required contractor effort that was not part of the contract (did not “volunteer”)
Must Result in:
‐ Increased cost: change in performance beyond original contract
requirement
Unauthorized Commitment
an agreement that is not binding solely because the government representative who made it lacked the authority to enter into that agreement on behalf of the government (both existing or no contract)
An unauthorized commitment resulting from a constructive change requires ratification