3.2.1.1 Parts of the matrix Flashcards

1
Q

Intervention logic

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Intervention logic

A

This corresponds to the first column of the matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

it displays

A

what the project intends to achieve?
how?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

by clarifying the

A

causal relations between
different levels of Obj
or
project strategy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

General objective/Goal

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

describes the

A

large-scale goal to which the project will contribute
together with other projects or actions,

but which cannot be achieved by the project alone.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The Specific objective/Project purpose
(SO/PP)

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

(SO/PP) is

A

normally the first piece in the LFM

key reference point of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The SO/PP is defined in terms of

A

the benefits
or
the immediate impact
upon project Ben

as result of the project services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The SO/PP must clearly state

A

the desired change

where the change will take place

and

the magnitude of the change to be achieved

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The achievement of the SO/PP should depend on

A

the team responsible for the project
and also on
the Ben involved
in order to ensure SOS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The following advice is given regarding the project purpose:

A

– It is recommended to develop only one specific objective per logical framework matrix.

More than one matrix may be needed for a more complex project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The following advice is given regarding the project purpose:

A

– Objectives should be set such that they are achievable within the proj

Time
Resource
Constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The following advice is given regarding the project purpose:

A

The matrix inputs should describe the desired outcome and not the process or activity for achieving the result.

Terms such as “guaranteed” or “assured” can be difficult to achieve
in some programmes and should be used carefully.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Results/Outputs

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The Results/Outputs describe the

A

undertaken.services to be delivered to project Ben
to achieve SO/PP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

they are the

A

product of the activities undertaken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

It is important to distinguish between results, activities and indicator

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Results statements should describe the change in the service provided and they will be the effect produced by the proposed activities: For example

A

‘Better access to sanitation services’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Activity example

A

‘100 latrines constructed’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Indicators of the results should be chosen for measurement of the result. In this example,

A

the result will be ‘1 500 people have access to
latrines, and use them’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Activities

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Activities are

A

how the services of the project will be delivered,

things that must be done to achieve the results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Some recommendations on presenting the activities are:

A

Activities should be presented with the corresponding result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Some recommendations on presenting the activities are:

A

Activities should be expressed in a tangible way, and should be achievable within the project timeframe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Some recommendations on presenting the activities are:

A

While activities are tangible, flexibility is also important

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

For example
‘Construct 10 water points’

A

allows the type of water point to be chosen during project implementation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

whereas
‘Construct 10 wells’

A

precisely defines the type of water point and may not be appropriate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

It is easier to justify
changes in the activities in the implementation phase than changes of results or specific objective

A

it is necessary to understand how changes can affect the project in terms of timing, budget,
human resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Vertical logic

A

specify indicators
(to measure progress)

ID SOV/MOV
(which indicators are to be measured)

Present ROA
(concerning the project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Objectively verifiable indicators

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Indicators are

A

parameters
used to
measure, state and check
how the
SO,results and activities have been achieved

33
Q

They are important for

A

monitoring the project.

34
Q

Indicators can be

A

qualitative or quantitative

35
Q

Note. – It is important to distinguish between the 1-indicators discussed earlier that serve to characterise a situation and

2-the indicators that measure actions undertaken

A

Indicators of the situation are parameters used to define a specific quality or state and they are used mainly in the ID, Ass
phase
(i.e. WQ parameters).

However, objective and results indicators precisely express
changes brought about by interventions
(e.g. ‘water supplied will have between 0.4 and 0.6 mg/l of FRC’).

36
Q

Before defining an indicator, it is necessary to

A

verify the feasibility of measuring it.
For example, diarrhoea morbidity can be difficult to measure by a water and sanitation project if the health care system does not include proper monitoring

37
Q

Some activities, results and specific objectives may require more than

A

one indicator, as one
may not provide enough information to assess progress

38
Q

Indicators must be

A

“SMART”

39
Q

Specific: with regard to

A

Q&Q
TGs
Time
Place

40
Q

Measurable:

A

(direct or indirect) and unambiguous

41
Q

Attainable and sensitive:
they should be

A

achievable by the project and
sensitive to changes
the project aims to make.

42
Q

Relevant and easy to collect:

A

the indicators chosen should be relevant to the project in question,

and

it must be feasible to collect information on them at reasonable cost.

43
Q

Timebound:

A

indicators should describe by when a certain change is expected

44
Q

Indicators may be

A

direct or indirect

45
Q

Direct indicators are related to

A

a directly observable change

For the result ‘Water access improved’
direct indicator can be :

‘100 families have access to improved water points’

46
Q

indirect indicators are

A

indirect consequences of this change

For the result ‘Water access improved’
indirect indicator could be ‘More children attend school’

(because they spend less than 15 minutes
collecting water and this leaves them time to go to school

47
Q

Indicators for
Specific objectives/results
can focus on

A

CB or BC.
In these cases,
indicators are mainly qualitative.

However, they must still be rigorous

48
Q

For the result
‘Water department capacities’,

A

‘Number of people attended training’ is not enough as the only indicator because it
does not demonstrate change.

‘10 technical staff have improved their knowledge on water-point maintenance’ should complement the first indicator.

Although ‘improved knowledge’ is qualitative it is a measure of progress.

49
Q

Indicators of SOV/MOV
indicate

A

How, where & in what
forms the required information on the achievement of
SO/PP and results can be found.

50
Q

SOV must be

A

Trustworthy
Accessible
Provide the information required to verify the chosen indicators

51
Q

SOV/MOV include

A

official/private
reports /EV
internal surveys /reports, technical surveys
CCI from
different sources is recommended for certain indicators

52
Q

SOV/MOV must indicate

A

1-The source
(project records, official statistics etc.)
which provides the information and how regularly it should be provided.

2-The work + cost of collecting +analysing information must be assessed and covered by the project

53
Q

Examples of SOV/MOV

A

KAP surveys can be the SOV for indicators of hygiene-BC

WQA can be used to verify improvement in the quality of the water

HCC records
Health,sanitary assessment

Internal,Proj,Prog, report
External EV

54
Q

Means

55
Q

Means are

A

human, material and service resources (inputs)
needed to carry out the activities

56
Q

Activities must be

A

detailed with the required means and costs

57
Q

Costs are the

A

FIN.Resources needed to carry out these activities

58
Q

Some logical frameworks have ‘ Inputs’

A

the means and the costs separated from the
activities

59
Q

Risks or Assumptions “AOR “

60
Q

Risks are

A

key events, actions or decisions

upon which project success depends

which may be subject to delay or which may not materialise.

61
Q

Risks are not supposed to occur

A

but there is a probability that they might

62
Q

Assumptions are

A

external factors

outside the immediate control of the project,

crucial for
the achievement of activities, results and objectives

63
Q

The aim of specifying assumptions and preconditions is to

A

ID and assess
potential risks to, dependencies of, the project right from initial stages of the project design,

to support the M of risks during the Imp of the
project

to provide a basis for necessary adjustments.

64
Q

It is important to identify the assumptions at

A

each level of the logical framework analysis

65
Q

Some assumptions can be identified during the

A

analysis phase as objectives included in the
objective tree

66
Q

Those objectives are not achieved by the project but

A

they can be important for achieving the purpose of the project

67
Q

For example

A

a nutrition project may have ‘improved nutritional status of the population’ as its purpose, in a context where this may only be achieved on the condition
that a complementary water project achieves its specific objectives.

One of the assumptions behind the nutritional project therefore may be that this condition is met

68
Q

Other examples are:

A

‘access to water will be guaranteed, assuming that there is no sabotage of the transmission line of the water system’,

69
Q

other example

A

‘capacity in the region will be improved,

assuming that

the authorities continue to participate in training’,

70
Q

other example

A

‘a system can be built in a specific area, assuming that access to the area is guaranteed’.

71
Q

There are different levels of assumption depending on

A

Their relevance to the project.

72
Q

If an assumption for success is unlikely

A

Then the project should be redesigned

73
Q

If it is sure, or almost sure,that it will occur,

A

Then it is not necessary to include it in the logical framework

74
Q

Preconditions

75
Q

Preconditions
A precondition is a

A

condition that must be satisfied before the project starts

76
Q

Examples OF Preconditions

A

‘an end to the conflict allows access to the area’

77
Q

Examples of Preconditions

A

‘communities agree to participate
in activity implementation’

78
Q

Examples of Preconditions

A

‘local authorities respect signed agreements and agree to collaborate’