What can LG do in 30 days?
How soon can file suit?
30 days aft condemnation notice delivered or undeliverable.
———–
Ʃ: Offer was already made at or before notice.
What has a deadline 30 days after service?
OFFER OF JMT ----------- Timeline of accepting Offer of Jmt. ------------ 30 days after service. UNLESS Trial is less than 30 days, then just accept b/4 trial.
Weirdness about timeline in accepting Offer of Jmt.
Can be made 20 days b/4 trial.
So can’t hold Def to 30 day acceptance rule.
If made less than 30 days b/4 trial, Def can accept b/4 trial.
When can LG petition for E.D.?
31 days aft condemnation notice delivered or undeliverable to Fee O. ----------- NOBO ----------- 1. Notice O. 2. w/ or aft O's Notice: Offer O 3. w/ or aft. O's Offer: Notice BO.
What does O have to respond to in 30 days, or get sued?
NOBO ----------- O has 30 days from NOTICE to respond to OFFER. ----------- 1. Notice O. 2. w/ or aft O's Notice: Offer O 3. w/ or aft. O's Offer: Notice BO.
For which type of revenue bond is 30 years significant?
- Can’t exceed 30 yrs to mature.
- ## If term is longer than 5 yrs, cannot pay from AV.~~~confirmed. LG can pay for COPS out of ANY revenues of LG, including AVs.~~~
What are 2 types of agreements that cannot exceed 30 years?
30
1) Developer Agreements.
2) COPS leases. [if over 5 yrs, can’t use A-V.]
How does 30 days play into bond issuance?
When there is a referendum, requires 30 days notice, to wit:
A) 30 days prior to the referendum,
B) 2x.
C) (1 x 5th wk) + (1 x 3rd wk) before vote.
How is 30% significant in MBE preferences?
May set up to 10% aside
+
Encourage 20% bond writing
Equal protection suit @ 30%
State 4 ways 336 & 255.20 differ.
336 [County roads] / 255.20 [public roads] ----------- 336: Bid only, no award. County qualifies Ktor. 10% behind on job for County. No timeline for Circuit review. ----------- 255.20: Award FDOT (if already preq) & County prequalify. 10% on any govt job. 30 day review by Circuit.
What does 30 have to do with punch lists?
30 days for up to $10M
60 days for over $10M
How does 30 days impact FLUEDRA?
30 days for:
A. O to request
B. LG to resp to Spec Mag recommendation.
———–
30 - request, 10 - get mag, 15 - answer, 45 [40] - hrg
14 - rec
15 - notify DLA, 30 - resp, issue ltr, 45 - rejection