204.09 Trench Rescue Operations Flashcards

1
Q

True of False:
It shall be the policy of the Phoenix Fire Department that any equippted personnel shall be allowed into an unsafe trench or excavation if done so safely.

A

False
It shall be the policy of the Phoenix Fire Department that NO personnel shall be allowed into an unsafe trench or excavation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

OSHA Regulations ________________ regulates excavations for general industry
and the rescue service and shall be considered the basis for emergency trench rescue
operations.

A

Standard 29 CFR 1926 Subpart P

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

For the purpose of emergency response, an excavation shall be defined by any depression, hole, trench, or earth wall, man made or natural, of _______feet or greater..

A

four feet or greater.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Trench collapses generally occur due to?

A

unstable soil conditions combined with improper or inadequate shoring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The primary hazard to personnel in a trench rescue operation is?

A

the potential for additional collapse

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The phased approach for trench rescue

operations includes;

A

Arrival, Pre-entry operations, Entry operations, and Termination,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

First arriving company officer at a trench rescue shall?

A

assume Command and begin an immediate
size-up of the situation while ensuring that apparatus remains at least 50 feet from the
location of the trench failure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Command shall announce that Level 1 staging should take place?

A

at least 150 feet from the trench failure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should the first arriving TRT unit that is staffed with a TRT Company Officer should be assigned?

A

Rescue Sector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Rescue Sector responsibilities include:

A

• Assuming technical rescue operations control.
• Identifying hazards and critical factors.
• Developing a rescue plan and back-up plan.
• Communicating with and directing TRT resources assigned to Rescue Sector.
• Informing Command of conditions, actions, and needs during all phases of the
rescue operation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

a proper Size-Up for a trench rescue includes:

A

A. Secure a witness or responsible party to assist in gathering information to determine
exactly what happened. If no witnesses are present, Command may have to look for
clues on the scene to determine what happened.
B. Assess the immediate and potential hazards to the rescuers.
C. Isolate immediate hazard area, secure the scene, and deny entry for all non-rescue
personnel.
D. Assess on-scene capabilities and determine the need for additional resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

It must be determined if this will be a _____ operation or a ______ operation
based on the survivability profile of the victim(s) which include factors such as the
location and condition of the victim(s), and elapsed time since the accident occurred.

A

RESCUE, RECOVERY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Establish a hazard zone perimeter of ___ feet from the collapse area.

A

50 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Remove all non-essential civilian personnel at least ___ feet away from the collapse area.

A

150 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Stage apparatus at least ___ feet from the collapse area

A

150 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

All heavy equipment operating within ___ feet of the collapse area should be shut down.

A

300 feet

17
Q

An open trench should be approached from?

A

the ends if possible.

18
Q

In order to make a trench safe ingress and egress ladders should be placed into the trench. There should be at least __ ladders placed into the trench no more than ___ feet apart.

A

2, 50 feet

19
Q

There are three types of shoring system used in trench rescue. What are they?

A

hydraulic shore, pneumatic shore,

timber shore

20
Q

M.P 204.09 breaks victim removal into two catagories. What are they?

A

INCIDENTS WITHOUT COLLAPSE, INCIDENTS WITH COLLAPSE

21
Q

Prior to termination of command the incident commander should ?

A

A. Ensure personnel accountability.
B. Remove tools, equipment, and the trench shoring system (last-in / first-out) from the
trench. In cases of a fatality, consider leaving everything in place until the
investigative process has been completed.
C. Consider a Post Incident Critique (may be more appropriate at a later date).
D. Return to service after turning the scene over to the responsible party and ensuring
the scene is secure.

22
Q

Rescue teams, Lobby, Ventilation, Air Monitoring, Shoring, Cut teams,
and any other such functional team operating in the hazard zone shall be under the
direction of _________.

A

Rescue Sector

23
Q

Command should maintain awareness of the time of day. Why?

A

To ensure sufficient lighting is available on

the scene if operations extend into the night.