2015 IRC Exam 2 of 4 (25-48) Flashcards

1
Q
25.  Termite protection shall not be provided by what means?
(p72 - R318.1)
a.  plastic sheeting 
b.  te1mite baiting systems 
c.  6 inch air gap 
d.  use Eastern Red Cedar wood
A

c. 6 inch air gap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
26.  What is the minimum distance between foam plastics installed above grade and exposed earth in areas of heavy termite infestation?
(p72 - R318.4)
a.  4 inches 
b.  6 inches 
c.  8 inches 
d.  12 inches
A

b. 6 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
27.  What is the minimum thickness requirement for a footing carrying 2 stories of a slab on grade light-framed structure?
(p81 - Table R403.1)
a.  16 inches 
b.  12 inches 
c.  10 inches 
d.  6 inches
A

d. 6 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
28.  What is the size of rebar required in the middle third of a footing that is part of a monolithic slab on grade with tum down footings?
(p84 - 403.1.3.3)
a.  #4 
b.  #5 
c.  #8 
d.  #10
A

b. #5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
29.  What is the minimum clearance of rebar to earth used in a footing?
(p84 - 403.1.3.5.3)
a.  3 inches 
b.  6 inches 
c.  8 inches 
d.  placed in the middle ofthe footing
A

a. 3 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
30.  An exterior footing for a structure must be at least \_\_\_\_\_\_ inches below the undisturbed ground surface. 
(p89 - 403.1.3.4)
a.  24 
b.  18 
c.  12 
d.  6
A

c. 12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
31.  An accessory storage building that is 350 square feet is required to be \_\_\_\_\_\_ 
(p89 - 403.1.4.1)
a.  on piers 
b.  on a slab 
c.  does not require a permit 
d.  does not require an inspection
A

b. on a slab

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
32.  What is the minimum depth a footing must be below undisturbed ground in Jackson, Mississippi? 
(p31)
a.  6 
b.  12 
c.  18 
d.  no requirement
A

b. 12

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
33.  What is the maximum distance between anchor bolts used in wood wall framing?
(p89 - 403.1.6)
a.  3 feet 
b.  4 feet 
c.  6 feet 
d.  8 feet
A

c. 6 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
34.  What is the maximum distance anchor bolts shall be from ends of sill plates in wood wall framing? 
(p89 - 403.1.6)
a.  2 inches 
b.  4 inches 
c.  8 inches 
d.  12 inches
A

d. 12 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
35.  What is the minimum size block that may be used in a foundation wall if the wall is 8 feet tall and has backfill of 4 feet made of type SW soil? 
(p102 - 404.1.1.1)
a.  12 inch 
b.  10 inch 
c.  8 inch 
d.  4 inch
A

c. 8 inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
36.  Given: 8 inch thick masonry foundation wall that is 8 feet tall, has 8 feet of unbalanced backfill of ML-CL soil.  How often are #6 vertical bars required for this wall? 
(p103 - Table R404.1.1.2)
a.  48 inches on center 
b.  36 inches on center 
c.  32 inches on center 
d.  24 inches on center
A

c. 32 inches on center

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
37.  What is the maximum height of a foundation wall supporting light frame construction if a 4" inch unreinforced hollow masonry unit is used in the foundation?
(p116 - R404.1.5.3) 
a.  2 feet 
b.  3 feet 
c.  4 feet 
d.  6 feet
A

c. 4 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
38.  A masonry foundation wall must extend \_\_\_\_\_ inches above the finished grade when masonry veneer is used.
(p116 - R404.1.6)
a.  12 
b.  8 
c.  6 
d.  4
A

d. 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
39.  A crawlspace of an office building must have \_\_\_\_\_\_\_ sq. ft. of ventilation for 1500 sq. ft. of crawlspace area.
(p121 - R408.1)
a.  1 
b.  5 
c.  10 
d.  12
A

c. 10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
40.  The door for the crawlspace access point must be?
(p122 - R408.4)
a.  22" X 30" 
b.  18" x 24" 
C.  12"x 12" 
d.  no requirement
A

b. 18” x 24”

17
Q
41.  Wood forms used for the placing of concrete shall be \_\_\_\_\_\_ the crawlspace before the structure is occupied.
(p122 - R408.5)
a.  removed from 
b.  buried in 
c.  stacked in 
d.  no requirement
A

a. removed from

18
Q
42.  Wood used for load supporting structures shall be identified by the grade mark of a lumber grading or \_\_\_\_ 
(p123 - R502.1.1)
a.  ASTM 84 
b.  DOC 29 
c.  inspection agency 
d.  mill
A

c. inspection agency

19
Q
43.  What is the maximum span of a 2 x 10 floor joist if the species is Southern Pine #2, spaced 16 inches on center, and must support a 40 lbs. live load and 10 lbs. dead load?
(p127 - R502.3.1.2)
a.  12 feet 6 inches 
b.  14 feet 
c.  15 feet 6 inches 
d.  18 feet
A

b. 14 feet

20
Q
44.  You wish to notch the top of a 2x12 in the middle.  The maximum size of the notch can be \_\_\_\_\_\_?
(p130 - R502.8.1)
a.  3 in. 
b.  4 in. 
c.  6 in. 
d.  not allowed
A

d. not allowed

21
Q
45.  What is the maximum percentage you can notch the end of a floor joist? 
(p130 - R502.8.1)
a.  50 
b.  30 
c.  25 
d.  10
A

c. 25

22
Q
46.  End joints in end-matched lumber used as subflooring shall \_\_\_\_\_\_ 
(p132 - R503.1.1)
a.  not be over 24 inches long. 
b.  not be less than 16 inches long 
c.  bear on at least 2 joists 
d.  no requirements
A

c. bear on at least 2 joists

23
Q
47.  The base for preservative treated wood floors placed on the ground shall be at least \_\_\_\_\_ inches of gravel over compacted earth. 
(p134 - R504.2.1)
a.  4 
b.  6 
c.  8 
d.  not allowed
A

a. 4

24
Q
48.  What is the maximum distance a cantilevered metal floor joist may extend if supporting the first floor of a one story building?
(p145 - R505.3.6)
a.  48 inches 
b.  36 inches 
c.  24 inches 
d.  12 inches
A

c. 24 inches