2. Site and Environment Flashcards
4 types of soils
sand - granular; low plasticity; good bases for building foundations
gravel - granular; low plasticity; good bases for building foundations
Silts - smaller than sands and grave; bigger than clay; granular but slightly plastic
clays - smaller particles than silts; has cohesion or tensile strength; swells when absorbs water; shrinks when it dries
hardpan
unbroken mixture of clay, sand, and gravel
standard penetration test (SPT)
measure of the density of granular soils and the consistency of some clays
- a 2 in samplers is driven into the bottom of the borehole by a 140 lbm hammer falling 30 in.
- the number of blowsrequried to drive the cylinder 12 in is recorded
- minimum of 4 borings are taken
test pits
- trenches dug on site to inspect soil
- limited to 10 ft.
auger borings
auger bit drilled into site
usually used for sand or clay
cannot penetrate hardpan or bedrock
wash borings
2 in to 4 in diameter pipe is used though which a water jet is maintained to force up soil
analysis is difficult because material mixes together
useful for soils too hard for auger tests
good up to 100 ft.
soils are classified according to
Unified Soil Classification System
TO increase bearing capacity, decrease settlement, or do both, the following soil treatments are used:
- drainage: reduces moisture content of soil, thus increasing load carrying capacity; reduces hydrostatic pressure
- fill: is existing soil is unsuitable for building, it is removed and engineered soil is brough in; compacted before construction begins; proctor test used to determine a standard for compatction (there is an optimum relationship with a fill’s density and moisture content)
- compaction: existing soil can simply be compacted to provide adequate base; tool used to compact is a sheepsfoot roller
densification: may involve vibration, dropping of heavy weights; pounding piles into ground and filling voids with sand; technique used depends on the grain size of soil - surcharging: surchargins is the preloading of the ground with fill materials to cause consolidation and settlements before building; after settlement, fill is removed and construction begins
- mixing: instead of replacement of soil a layer of gravel or sand may be placed and mixed in
earthwork
excavating soil for construction of a building foundation, water and sewer lines, and other buried items; includes modifying sites countours
unshored sides of soil shold be no steeper than…
their natural angle of repose or not greater than a slope of 1.5 horizontal to the vertial
grading
the modification of the contours of the site according to the grading plan
-finish grading is the final removal of soil prior to landscaping to paving
common method used for shoring and bracing during excavation
- soldier beams and lagging
- braced excavation
underpinning
method used to temporarily support existing foundations while they are being repaired or strengthened or when they are being extended to a lower level
-needle bemas supported by the adjacent grade and hydraulic jacks are used to temporarily support building while new foundation is constructed
subsurface drainage
minimum slope of 1/4 in per foot is recommended
-perforated drain tile should be laid around the footings at least 6 in below the floor slab to collect water and carry it away to storm drain
Surcharging
battered wall
simply a type of retaining wall using a material, such as stones or brick slightly angled to support the adjacent earth.
bentonite
an expansive type of clay than can push foundations and floor slabs upward when it gets wet.
when buildings are build on benotnite what foundation would they have?
drilled piers with grade beams
to prevent the upward movement cause by bentonite when it gets wet, drillled piers are used to support the building weight on bedrock or stable soil below the bentonite, grade beams span continuously between the piers and transmit buildin loads from the superstructure to the piers