2° Full-Length Test Flashcards

1
Q

Which of the following is a primary output of ‘Develop Project Charter’?
- A) Project scope statement
- B) Project management plan
- C) Project charter
- D) Stakeholder register

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The ‘Buyer-Conducted Performance Review’ is an activity within which process?
- A) Control Procurements
- B) Plan Procurement Management
- C) Conduct Procurements
- D) Close Procurements

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

‘Project Scope Management’ includes:
- A) Defining and controlling what is included and what is not included in the project.
- B) Identifying the project outcomes beneficial to stakeholders.
- C) Managing the project team.
- D) Ensuring the project is completed within the approved budget.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

‘Earned Value Analysis’ (EVA) is utilized to:
- A) Estimate the required budget at completion of the project.
- B) Measure the project performance against the scope, schedule, and cost baselines.
- C) Define the total scope of the project.
- D) Allocate the project resources efficiently.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The main purpose of ‘Control Schedule’ is to:
- A) Develop the project schedule.
- B) Ensure that project activities are completed on time.
- C) Monitor the status of project activities to update project progress and manage changes to the schedule baseline.
- D) Allocate sufficient time for project tasks.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which process involves reviewing all change requests, approving changes, and updating the project management plan and project documents?
- A) Direct and Manage Project Work
- B) Monitor and Control Project Work
- C) Perform Integrated Change Control
- D) Control Scope

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

‘Stakeholder Analysis’ is a technique used in:
- A) Develop Project Charter
- B) Identify Stakeholders
- C) Plan Stakeholder Engagement
- D) Manage Stakeholder Engagement

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The ‘To-Complete Performance Index’ (TCPI) is calculated to:
- A) Determine the cost performance required to complete the project within the original budget.
- B) Measure the cost efficiency of work performed to date.
- C) Forecast the project’s schedule performance.
- D) Assess the project team’s effectiveness.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

‘Qualitative Risk Analysis’ should:
- A) Assign a numerical value to both the probability of occurrence and the impact of project risks.
- B) Prioritize risks based on their probability of occurrence and potential impact on project objectives.
- C) Quantify the possible outcomes for the project and their probabilities.
- D) Develop responses for the highest priority risks.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In the ‘Manage Communications’ process, what is a key activity?
- A) Creating a detailed project budget.
- B) Ensuring that project information is generated, collected, distributed, and understood.
- C) Performing a stakeholder analysis.
- D) Updating the project risk register.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following best describes ‘Resource Leveling’?
- A) Enhancing project team members’ skills through additional training.
- B) Adjusting the project schedule to address resource over-allocation.
- C) Allocating the most skilled resources to high-priority tasks.
- D) Reducing the project scope to meet resource availability.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The ‘Cost Management Plan’ is developed in which process?
- A) Plan Cost Management
- B) Estimate Costs
- C) Determine Budget
- D) Control Costs

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

‘Procurement Statements of Work’ (SOW) are developed to:
- A) Describe the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results.
- B) Outline the project’s scope in detail.
- C) Provide vendors with a clear understanding of project timelines.
- D) Establish the project’s quality requirements.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the ‘Project Schedule Network Diagram’ provide?
- A) An estimation of the project’s costs.
- B) A visual representation of the project’s activities and their interdependencies.
- C) The critical path of the project.
- D) Both B and C.

A

Correct Answer: D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

During which process group is the ‘Project Charter’ developed?
- A) Initiating
- B) Planning
- C) Executing
- D) Monitoring and Controlling

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

‘Risk Urgency Assessment’ is a tool used to:
- A) Measure the severity of potential project risks.
- B) Prioritize risks based on their urgency and potential impact on project objectives.
- C) Identify the risks that require immediate response.
- D) Determine the probability of risk occurrence.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The main goal of ‘Plan Communications Management’ is to:
- A) Ensure that all project stakeholders are kept informed about the project status.
- B) Determine the information and communications needs of the project stakeholders.
- C) Develop an appropriate approach for project communications based on stakeholder needs and requirements.
- D) Implement the tools and techniques necessary to enhance project communication.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The ‘Control Quality’ process is crucial because it:
- A) Defines the quality standards for the project.
- B) Identifies quality metrics for the project.
- C) Ensures that the project’s deliverables meet the defined quality standards.
- D) Develops the project management plan.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

‘Bottom-Up Estimating’ is a technique that:
- A) Estimates the project cost by aggregating the individual costs from the bottom up.
- B) Provides a quick and easy way to estimate project duration.
- C) Is used exclusively during the closing phase of the project.
- D) Relies solely on the expertise of top management for estimation.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which process involves establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule?
- A) Plan Schedule Management
- B) Develop Schedule
- C) Control Schedule
- D) Sequence Activities

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

‘Configuration Management’ is primarily concerned with:
- A) Managing the project team’s configuration.
- B) Tracking changes to the product configuration and documenting them.
- C) Ensuring the compatibility of project hardware and software.
- D) Managing the project schedule configuration.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

‘Stakeholder Management Plan’ is developed to:
- A) Identify project stakeholders.
- B) Analyze the potential impact of project decisions on stakeholders.
- C) Outline strategies to engage stakeholders effectively.
- D) Track stakeholder satisfaction.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The purpose of ‘Perform Integrated Change Control’ is to:
- A) Review all change requests, approve changes, and manage changes to the deliverables, organizational process assets, and project documents.
- B) Ensure that all changes are communicated to all stakeholders.
- C) Implement approved changes to the project scope, plans, and environment.
- D) Both A and C.

A

Correct Answer: D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the purpose of the ‘Monitor Stakeholder Engagement’ process?
- A) To identify all stakeholders at the beginning of the project.
- B) To plan how to engage stakeholders effectively.
- C) To track project performance and make necessary adjustments to the engagement strategies.
- D) To ensure all stakeholders are fully satisfied with the project outcomes.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

‘Critical Path Method’ (CPM) is primarily used for:
- A) Identifying the longest sequence of activities in a project plan which must be completed on time for the project to complete on due date.
- B) Estimating the shortest possible project duration.
- C) Determining the most cost-effective way to complete the project.
- D) Assessing the risk impact on project schedules.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

In ‘Perform Qualitative Risk Analysis’, what is a primary factor to consider?
- A) The numerical impact of each risk on project objectives.
- B) The probability and impact of risks occurring.
- C) The total cost of risk mitigation activities.
- D) The exact duration impact of each risk on the project.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

‘Resource Optimization Techniques’ are used to address:
- A) The alignment of project budget allocations.
- B) The improvement of team performance and skills.
- C) The balancing of resource allocation to ensure project milestones are met.
- D) The enhancement of communication methods within the project team.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which output from the ‘Direct and Manage Project Work’ process is used to influence and inform stakeholders of project progress?
- A) Change requests
- B) Project documents updates
- C) Deliverables
- D) Work performance data

A

Correct Answer: D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

The ‘Schedule Performance Index’ (SPI) is a measure of:
- A) Cost efficiency on a project.
- B) Schedule efficiency on a project.
- C) The accuracy of the project scope.
- D) The effectiveness of risk management.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is a key activity in the ‘Manage Communications’ process?
- A) Updating the risk register with new communications risks.
- B) Ensuring that the communications meet stakeholders’ needs and are understood.
- C) Creating a new project management plan.
- D) Conducting performance reviews with the project team.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

‘Earned Value Management’ (EVM) integrates information from which areas?
- A) Scope, schedule, and quality
- B) Scope, quality, and risk
- C) Scope, schedule, and cost
- D) Cost, quality, and risk

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

The primary purpose of ‘Stakeholder Engagement Assessment Matrix’ is to:
- A) List all potential project stakeholders and their information.
- B) Document how stakeholders prefer to receive project communications.
- C) Assess the current engagement level of stakeholders and plan future engagement strategies.
- D) Evaluate the power and influence of stakeholders over the project.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

‘Plan Procurement Management’ involves:
- A) Deciding which project needs can be best met by procuring products or services outside the project organization.
- B) Selecting sellers and awarding contracts.
- C) Managing contract and vendor performance.
- D) Closing out contracts upon project completion.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

‘Analogous Estimating’ is characterized by:
- A) High accuracy and is based on detailed project data.
- B) Using historical data from similar projects as the basis for estimating.
- C) Being the most time-consuming estimating technique.
- D) Providing an estimate for the total project rather than individual tasks.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

In project management, ‘Procurement Audits’ are conducted to:
- A) Review the procurement process from planning through closure.
- B) Ensure that all procurements comply with legal requirements.
- C) Audit the project team’s performance.
- D) Assess the seller’s financial stability.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

‘Decision Tree Analysis’ is a tool used in which process?
- A) Perform Quantitative Risk Analysis
- B) Plan Risk Responses
- C) Perform Qualitative Risk Analysis
- D) Identify Risks

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

‘Work Performance Reports’ provide information on:
- A) The physical work accomplished.
- B) Project forecasts and potential issues.
- C) Detailed financial expenditures.
- D) Compliance with project governance.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Which of the following is true about the ‘Close Project or Phase’ process?
- A) It focuses exclusively on financial closure of the project.
- B) It involves handing off completed deliverables to the next phase or project closure.
- C) It is conducted during the execution phase to close out parts of the project work.
- D) It includes activities to transfer the completed project to operations or maintenance.

A

Correct Answer: D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

The ‘Cost of Quality’ includes costs associated with:
- A) Procuring high-quality materials only.
- B) Prevention, appraisal, and failure (both internal and external).
- C) Training project team members on quality management processes.
- D) Meeting legal requirements for product quality.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

‘Scope Creep’ refers to:
- A) The total work included in the project scope.
- B) The uncontrolled expansion to project scope without adjustments to time, cost, and resources.
- C) The reduction of project scope during the project execution phase.
- D) Detailed documentation of the project scope.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Which process ensures that project work is performed according to the project management plan and authorizes the transition between project phases?
- A) Monitor and Control Project Work
- B) Direct and Manage Project Work
- C) Perform Integrated Change Control
- D) Close Project or Phase

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

‘Resource Smoothing’ is a technique where:
- A) Project resources are extended to lower overall costs.
- B) Resources are adjusted so that requirements on all days of the project are not to exceed certain predefined levels.
- C) Additional resources are allocated to critical tasks.
- D) Tasks are delayed to manage resource utilization.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

The ‘Project Schedule Network Diagram’ provides a graphical representation of:
- A) The project’s cost baseline.
- B) The project’s resources and their allocations.
- C) The logical relationships among all the project activities.
- D) The project’s time and cost performance data.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

In which process would you develop a ‘Stakeholder Engagement Plan’?
- A) Identify Stakeholders
- B) Plan Stakeholder Engagement
- C) Manage Stakeholder Engagement
- D) Monitor Stakeholder Engagement

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

‘Plan Quality Management’ is crucial for determining:
- A) The project’s quality policy, objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken.
- B) The metrics to be used for monitoring and controlling quality.
- C) The specific quality standards that the project will aim to meet.
- D) Both A and C.

A

Correct Answer: D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

‘Earned Value Management’ (EVM) helps project managers to:
- A) Track the ethical conduct of the project team.
- B) Measure project performance against the project scope baseline.
- C) Assess project performance and progress against established scope, schedule, and cost baselines.
- D) Ensure the project team’s compliance with legal requirements.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

‘Change Management Plan’ is a component of:
- A) The project management plan that describes how changes will be managed throughout the project.
- B) The project scope statement that outlines how scope changes will be handled.
- C) The communications management plan that details how changes are communicated to stakeholders.
- D) The stakeholder engagement plan that outlines how stakeholders are informed about changes.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

‘Bottom-Up Estimating’:
- A) Is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the Work Breakdown Structure (WBS).
- B) Provides an estimate for the project as a whole without going into detailed estimates for activities.
- C) Is used primarily in the early phases of project planning when detailed information is not available.
- D) Is less accurate than analogous and parametric estimating.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What is the primary focus of the ‘Develop Schedule’ process in project management?
- A) Allocating project resources effectively.
- B) Analyzing project risks and their impact on the project schedule.
- C) Establishing the order and timing of project activities to complete the project.
- D) Documenting the roles and responsibilities of project team members.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

‘Parametric Estimating’ involves:
- A) Estimating the duration or cost of an activity by applying an average of similar activities from past projects.
- B) Using project-specific variables in a mathematical model to forecast project costs or durations.
- C) Summing the costs of individual work packages or activities to come up with a project total.
- D) Relying on the expertise of seasoned project managers to estimate costs and durations.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

In project risk management, ‘Secondary Risks’ are best described as:
- A) Risks that have been identified but are considered low priority.
- B) New risks that arise as a direct result of implementing a risk response.
- C) Risks that are identified by stakeholders external to the project team.
- D) The risks remaining after the primary risks have been mitigated.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

The ‘Manage Team’ process is crucial for:
- A) Identifying the skills and expertise required for project tasks.
- B) Developing individual team members to enhance project performance.
- C) Tracking team member performance, providing feedback, resolving issues, and managing changes to enhance project performance.
- D) Ensuring that the project team adheres to the project schedule.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

‘Work Performance Data’ includes:
- A) The analysis of project progress and performance.
- B) Raw observations and measurements identified during activities performed to carry out the project work.
- C) Recommendations for future actions to improve performance.
- D) High-level information regarding project progress.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What is the main outcome of the ‘Plan Stakeholder Engagement’ process?
- A) A detailed list of project stakeholders.
- B) A plan describing how to effectively engage stakeholders and manage their expectations.
- C) A report on stakeholder satisfaction with the project.
- D) Documentation of resolved stakeholder issues.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

‘Cost-Benefit Analysis’ in project management is used to:
- A) Track and report actual costs incurred during the project.
- B) Evaluate the financial viability of the project.
- C) Estimate the costs associated with project risks.
- D) Determine the project’s internal rate of return (IRR).

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

In ‘Perform Integrated Change Control,’ a major role of the Change Control Board (CCB) is to:
- A) Implement changes as soon as they are requested by any stakeholder.
- B) Review, evaluate, and approve or reject change requests.
- C) Ensure that all changes are reflected in the project schedule.
- D) Communicate changes to external stakeholders.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

The ‘Collect Requirements’ process is essential for:
- A) Defining and documenting stakeholders’ needs to meet the project objectives.
- B) Gathering the project team’s input on the project scope.
- C) Collecting the project deliverables at the end of each phase.
- D) Understanding the budgetary requirements of the project stakeholders.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

‘Resource Calendars’ are important in project management because they:
- A) Outline the financial resources available over the life of the project.
- B) Detail when specific project resources are available to perform project activities.
- C) Provide a timeline of project milestones and deliverables.
- D) Indicate the availability of equipment and materials required for the project.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

The main goal of ‘Control Costs’ is to:
- A) Develop an approximation of the monetary resources needed to complete project work.
- B) Monitor the status of the project to update project costs and manage changes to the cost baseline.
- C) Ensure that all project expenditures are recorded and reported.
- D) Provide a comprehensive breakdown of all costs associated with the project.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

‘Project Charter’ includes information about:
- A) Detailed project requirements and the project management plan.
- B) High-level project description, key stakeholders, and the project’s objectives.
- C) The project’s cost baseline and budget allocations.
- D) Specific tasks assigned to project team members.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

‘Quality Metrics’ might include measurements such as:
- A) The number of change requests approved.
- B) The percentage of tasks completed on schedule.
- C) The number of defects per thousand lines of code.
- D) The total cost of the project at completion.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

‘Stakeholder Engagement’ levels throughout a project are typically:
- A) Static and unchanging.
- B) Decreasing as the project progresses.
- C) Increasing in a linear fashion as the project moves forward.
- D) Dynamic and may change based on project phase and stakeholder influence.

A

Correct Answer: D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

The ‘Perform Qualitative Risk Analysis’ process primarily:
- A) Assigns numerical values to the probability and impacts of identified risks.
- B) Prioritizes risks for further analysis or action by assessing and combining their probability of occurrence and impact.
- C) Involves developing options and actions to enhance opportunities and reduce threats.
- D) Quantifies the possible outcomes for the project and their probabilities.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

‘Decision Tree Analysis’ in project management is useful for:
- A) Organizing and presenting the schedule activities in a graphical sequential order.
- B) Making informed decisions when multiple options are available with different outcomes.
- C) Tracking the project progress against its objectives.
- D) Analyzing the project team’s performance.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

‘Variance Analysis’ in the context of project management is used to:
- A) Determine the cause of differences between the planned and actual performance.
- B) Analyze the variance between different project estimates.
- C) Compare the cost variances of different projects within the same program.
- D) Establish new baselines for project performance.

A

Correct Answer: A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

Which of the following is NOT a direct benefit of ‘Project Scope Management’?
- A) Ensuring the project includes all and only the work required.
- B) Preventing scope creep.
- C) Increasing the project’s budget to accommodate changes.
- D) Defining and controlling what is and is not included in the project.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

The ‘Manage Communications’ process is important because it:
- A) Defines the project’s communications channels.
- B) Ensures that project information is generated, collected, distributed, stored, retrieved, and disposed of according to the communications management plan.
- C) Establishes new communication technologies for project management.
- D) Documents the project’s communication requirements in the project charter.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

‘Lessons Learned’ documentation is compiled:
- A) Only at the beginning of the project during the initiating process.
- B) Exclusively at the end of the project during the closing process.
- C) Throughout the project lifecycle and finalized during the closing process.
- D) During project planning and never revisited.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

What is the primary purpose of ‘Project Integration Management’?
- A) To ensure that all project phases are completed on time.
- B) To oversee the performance of the project team.
- C) To coordinate all aspects of the project plan.
- D) To manage the integration of project budget and resource allocations.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

‘Monte Carlo Analysis’ is a tool used in:
- A) Developing the project schedule.
- B) Performing quantitative risk analysis.
- C) Estimating project costs.
- D) Planning resource allocations.

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

In which process would ‘Expert Judgment’ be utilized to estimate the duration of project activities?
- A) Develop Schedule
- B) Estimate Activity Durations
- C) Plan Resource Management
- D) Define Activities

A

Correct Answer: B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

‘Plan Cost Management’ involves:
- A) Approving project budgets and funding.
- B) Estimating costs of individual activities.
- C) Defining how the project costs will be planned, structured, and controlled.
- D) Allocating additional funds to cover project risks.

A

Correct Answer: C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

The process of ‘Close Procurements’ is primarily concerned with:
- A) Documenting project procurement decisions.
- B) Completing and settling each contract, including the resolution of any open items.
- C) Developing the procurement management plan.
- D) Selecting sellers and awarding contracts.

A

Correct Answer: B

70
Q

The ‘Define Scope’ process primarily aims to:
- A) Establish the project’s boundaries and acceptance criteria.
- B) Identify the high-level objectives and deliverables of the project.
- C) Detail the project’s specific goals, deliverables, tasks, and deadlines.
- D) Create a detailed description of the project and product

A

Correct Answer: D

71
Q

‘Schedule Compression’ techniques include:
- A) Fast tracking and resource leveling.
- B) Crashing and fast tracking.
- C) Monte Carlo simulations and crashing.
- D) Resource smoothing and Monte Carlo simulations.

A

Correct Answer: B

72
Q

In project management, ‘Scope Creep’ can be best managed by:
- A) Increasing the project budget to accommodate additional work.
- B) Implementing a rigorous change control process.
- C) Reducing the project scope to offset additional tasks.
- D) Allowing stakeholders to make changes without formal approval.

A

Correct Answer: B

73
Q

‘Earned Value Management’ (EVM) helps in determining:
- A) The project’s communication needs.
- B) The project’s strategic alignment with organizational goals.
- C) The project’s physical progress compared to its planned progress.
- D) The effectiveness of the project team’s collaboration.

A

Correct Answer: C

74
Q

A ‘Stakeholder Engagement Plan’ is developed to:
- A) List all potential and current project stakeholders.
- B) Detail strategies for engaging stakeholders throughout the project lifecycle.
- C) Document the roles and responsibilities of stakeholders.
- D) Ensure all stakeholders approve the project management plan.

A

Correct Answer: B

75
Q

‘Cost Performance Index’ (CPI) and ‘Schedule Performance Index’ (SPI) are components of:
- A) Scope management.
- B) Quality management.
- C) Risk management.
- D) Performance measurement.

A

Correct Answer: D

76
Q

The ‘Monitor and Control Project Work’ process is vital for:
- A) Approving project changes and updating the project management plan.
- B) Tracking, reviewing, and regulating the progress and performance of the project.
- C) Ensuring that project objectives are met through stakeholder engagement.
- D) Developing and managing the project team and organizational interfaces.

A

Correct Answer: B

77
Q

Which process involves the formal authorization to begin a new project or project phase?
- A) Develop Project Charter
- B) Develop Project Management Plan
- C) Define Scope
- D) Plan Stakeholder Engagement

A

Correct Answer: A

78
Q

‘Qualitative Risk Analysis’ includes evaluating risks based on their:
- A) Probability and impact.
- B) Cost implications.
- C) Duration effects.
- D) Response costs.

A

Correct Answer: A

79
Q

In the ‘Control Quality’ process, the main focus is on:
- A) Identifying quality requirements.
- B) Inspecting the quality of deliverables and ensuring they meet the project and product requirements.
- C) Developing the project team’s quality management skills.
- D) Planning how quality will be managed throughout the project

A

Correct Answer: B

80
Q

‘Resource Leveling’ is a technique used to:
- A) Enhance team performance by providing training and development.
- B) Address resource over-allocation within the project schedule.
- C) Allocate additional resources to activities to compress the schedule.
- D) Level out project risks by applying adequate resources.

A

Correct Answer: B

81
Q

‘Procurement Management Plan’ details:
- A) How the project will acquire goods and services from outside the performing organization.
- B) The project’s budget for external purchases.
- C) A list of preferred vendors.
- D) The contract closure process.

A

Correct Answer: A

82
Q

Which of the following best describes ‘Project Integration Management’?
- A) It involves making choices about resource allocation.
- B) It focuses exclusively on integrating the project schedule.
- C) It ensures that project components are properly coordinated.
- D) It deals only with the integration of project costs and budgets.

A

Correct Answer: C

83
Q

The purpose of the ‘Perform Integrated Change Control’ process is to:
- A) Ensure that all changes are beneficial to the project’s objectives.
- B) Review all change requests, approve changes, and manage changes to deliverables, organizational process assets, project documents, and the project management plan.
- C) Prevent any changes to the project scope.
- D) Document all changes made to the project.

A

Correct Answer: B

84
Q

‘Bottom-Up Estimating’ is most useful when:
- A) There is a high level of uncertainty in project activities.
- B) Detailed information about the project is available.
- C) The project is small and not complex.
- D) Quick project estimates are required.

A

Correct Answer: B

85
Q

‘Stakeholder Analysis’ in the ‘Identify Stakeholders’ process is used to:
- A) Determine the project scope.
- B) Analyze stakeholders’ potential impact on the project.
- C) Estimate the resources required by stakeholders.
- D) Create a communications plan.

A

Correct Answer: B

86
Q

The ‘Control Scope’ process involves:
- A) Developing a detailed project scope statement.
- B) Monitoring the status of the project and managing changes to the scope baseline.
- C) Ensuring all requested changes and recommended corrective actions are processed.
- D) Defining and documenting project and product functionality.

A

Correct Answer: B

87
Q

What is a primary concern of ‘Cost Management’?
- A) Determining how costs will be planned, structured, and controlled.
- B) Ensuring that project purchases stay within the budget.
- C) Allocating additional funds to cover unforeseen expenses.
- D) Reducing project costs to increase profitability.

A

Correct Answer: A

88
Q

‘Work Performance Information’ is:
- A) Data collected from performance measurements to analyze project progress.
- B) The raw observations and data identified during project execution.
- C) An output of the Direct and Manage Project Work process.
- D) Detailed information on which project aspects are performing as planned.

A

Correct Answer: D

89
Q

The main objective of ‘Plan Stakeholder Engagement’ is to:
- A) Identify all people or organizations impacted by the project.
- B) Develop approaches to involve stakeholders based on their needs and potential impact.
- C) Communicate project information to stakeholders to ensure their continued support.
- D) Monitor overall project stakeholder relationships.

A

Correct Answer: B

90
Q

‘Monte Carlo Simulation’ is utilized in project management to:
- A) Define the project scope.
- B) Estimate the probability of completing the project by a certain date or within a certain cost.
- C) Develop the project schedule.
- D) Allocate project resources.

A

Correct Answer: B

91
Q

‘Project Governance’ includes:
- A) Managing project deliverables and tasks.
- B) The framework within which project decisions are made.
- C) The daily management of the project team.
- D) Documenting project changes.

A

Correct Answer: B

92
Q

Which process aims to document project procurement decisions, specify the approach, and identify potential sellers?
- A) Plan Procurement Management
- B) Conduct Procurements
- C) Control Procurements
- D) Close Procurements

A

Correct Answer: A

93
Q

‘Project Scope Statement’ is developed in which process?
- A) Plan Scope Management
- B) Collect Requirements
- C) Define Scope
- D) Create WBS

A

Correct Answer: C

94
Q

The primary purpose of ‘Perform Qualitative Risk Analysis’ is to:
- A) Numerically analyze the effect of identified risks on project objectives.
- B) Prioritize risks for further analysis or action by assessing their probability of occurrence and impact.
- C) Implement risk responses for the most significant project risks.
- D) Monitor identified risks throughout the project lifecycle.

A

Correct Answer: B

95
Q

Which process involves determining the project stakeholders’ information needs and defining a communication approach?
- A) Identify Stakeholders
- B) Plan Communications Management
- C) Manage Communications
- D) Monitor Communications

A

Correct Answer: B

96
Q

‘Resource Histogram’ is a tool used in which of the following processes?
- A) Estimate Activity Resources
- B) Acquire Resources
- C) Develop Schedule
- D) Control Resources

A

Correct Answer: A

97
Q

What is the main goal of the ‘Identify Risks’ process?
- A) To implement risk response actions for identified risks.
- B) To determine the probability and impact of identified risks on project objectives.
- C) To document the overall risk management approach for the project.
- D) To determine which risks might affect the project and document their characteristics.

A

Correct Answer: D

98
Q

The ‘Cost Performance Index’ (CPI) is an indicator of:
- A) The efficiency of time management on the project.
- B) The efficiency of cost management on the project.
- C) The status of the project schedule.
- D) The project’s progress toward completion.

A

Correct Answer: B

99
Q

In the context of project scope management, ‘Control Scope’ is important because it:
- A) Identifies the work required for the project.
- B) Ensures that the project includes all the work required, and only the work required, to complete the project successfully.
- C) Monitors the status of the project and product scope and manages changes to the scope baseline.
- D) Defines and approves all project and product deliverables.

A

Correct Answer: C

100
Q

Which process ensures that the project’s deliverables are complete and satisfactory?
- A) Validate Scope
- B) Control Quality
- C) Define Scope
- D) Plan Quality Management

A

Correct Answer: A

101
Q

‘Procurement Documents’ should be used during which process to solicit proposals from prospective sellers?
- A) Plan Procurement Management
- B) Conduct Procurements
- C) Control Procurements
- D) Close Procurements

A

Correct Answer: B

101
Q

‘Work Breakdown Structure’ (WBS) is primarily used to:
- A) Allocate project budgets.
- B) Organize and define the total scope of the project.
- C) Schedule project tasks.
- D) Identify project risks.

A

Correct Answer: B

102
Q

The purpose of ‘Monitor Risks’ process is to:
- A) Identify new risks and reassess existing risks.
- B) Prioritize risks based on their impact and probability.
- C) Implement risk response plans.
- D) Track identified risks, monitor residual risks, and identify new risks, ensuring the execution of risk response plans.

A

Correct Answer: D

103
Q

In ‘Perform Integrated Change Control’, the main role of the Change Control Board (CCB) is to:
- A) Implement all approved changes.
- B) Review and approve, postpone, or reject changes to the project.
- C) Update the project management plan to reflect changes.
- D) Ensure that all change requests are documented.

A

Correct Answer: B

104
Q

Which of the following best describes ‘Fast Tracking’?
- A) Increasing project resources to speed up the project completion.
- B) Performing more project activities in parallel.
- C) Reducing the project scope to meet deadlines.
- D) Extending the project schedule to accommodate all tasks.

A

Correct Answer: B

105
Q

‘Qualitative Risk Analysis’ typically involves assessing risks based on their:
- A) Quantitative impact on the project’s objectives.
- B) Severity and the cost to mitigate them.
- C) Probability of occurrence and potential impact on project objectives.
- D) Relationship to other project risks.

A

Correct Answer: C

106
Q

‘Stakeholder Engagement Plan’ includes strategies for:
- A) Identifying stakeholders.
- B) Engaging stakeholders based on their needs, interests, and potential impact on project success.
- C) Communicating project information to stakeholders.
- D) Assigning tasks to stakeholders.

A

Correct Answer: B

107
Q

The ‘To-Complete Performance Index’ (TCPI) is used to:
- A) Calculate the performance needed to complete the project within the original budget.
- B) Measure the cost performance to date.
- C) Estimate the project’s final cost at completion.
- D) Assess the schedule performance of the project.

A

Correct Answer: A

108
Q

Which of the following is NOT typically a reason for project initiation?
- A) A market demand.
- B) An organizational need.
- C) A legal requirement.
- D) A competitor’s performance.

A

Correct Answer: D

109
Q

‘Earned Value Management’ (EVM) integrates information from:
- A) Scope, schedule, and cost for measuring project performance.
- B) Quality, risk, and procurement to control project costs.
- C) Human resources, communications, and stakeholder engagement for project planning.
- D) Scope, quality, and human resources for performance measurement.

A

Correct Answer: A

110
Q

The primary purpose of ‘Plan Cost Management’ is to:
- A) Estimate the costs of project activities.
- B) Establish policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
- C) Allocate the project budget across project work packages.
- D) Develop a schedule for project cost reporting.

A

Correct Answer: B

110
Q

A ‘Responsibility Assignment Matrix’ (RAM) such as a RACI chart is developed to:
- A) Track project expenses and budget allocations.
- B) Clarify roles and responsibilities in project tasks and processes.
- C) Manage project risks and develop mitigation strategies.
- D) Schedule project activities and milestones.

A

Correct Answer: B

111
Q

‘Analogous Estimating’ is a technique used in:
- A) Determining the project schedule based on the project team’s availability.
- B) Calculating the project budget based on historical data from similar projects.
- C) Assessing project risks using past project experiences.
- D) Allocating project resources based on past allocation trends.

A

Correct Answer: B

112
Q

The ‘Manage Quality’ process aims to:
- A) Determine how quality will be managed and controlled throughout the project.
- B) Ensure that the project’s deliverables meet the required quality standards.
- C) Incorporate the organization’s quality policies into project activities.
- D) Audit the quality requirements and results from quality control measurements.

A

Correct Answer: D

112
Q

In project management, ‘Scope Verification’ is primarily concerned with:
- A) Developing a detailed project scope statement.
- B) Ensuring that all project work has been completed satisfactorily.
- C) Obtaining formal acceptance of the completed project deliverables from the customer or sponsor.
- D) Controlling changes to the project scope.

A

Correct Answer: C

113
Q

‘Resource Optimization’ in project scheduling is used to:
- A) Ensure that resources are used efficiently across the project.
- B) Increase the project’s duration to utilize resources fully.
- C) Reduce the amount of resources required for the project.
- D) Assign the best resources to the most critical tasks.

A

Correct Answer: A

114
Q

Which process involves documenting the procedures to manage changes to the project scope?
- A) Define Scope
- B) Control Scope
- C) Plan Scope Management
- D) Validate Scope

A

Correct Answer: C

115
Q

‘Lessons Learned’ documentation is used to:
- A) Record the experiences and insights gained during the project for use in future projects.
- B) Provide feedback to project team members on their performance.
- C) Satisfy the project’s compliance requirements with organizational policies.
- D) Document the project team’s disagreements and conflicts.

A

Correct Answer: A

116
Q

What does ‘rolling wave planning’ imply in project management?
- A) Planning the project in detail from start to finish at the beginning.
- B) Planning for high-risk activities to occur as late as possible in the schedule.
- C) Detailed planning for near-term activities and high-level planning for future work.
- D) Adjusting the project plan daily based on team performance.

A

Correct Answer: C

116
Q

‘Project Integration Management’ is crucial because it:
- A) Deals exclusively with the integration of schedules and resources within the project.
- B) Ensures that project components are properly coordinated.
- C) Focuses on the project’s alignment with business goals.
- D) Manages the project’s budget and financial resources.

A

Correct Answer: B

117
Q

The main objective of the ‘Identify Stakeholders’ process is to:
- A) Determine the project scope based on stakeholder needs.
- B) Document relevant information regarding interested parties in the project.
- C) Ensure all stakeholders agree with the project plan before proceeding.
- D) Assign roles and responsibilities to stakeholders.

A

Correct Answer: B

118
Q

‘Control Schedule’ is a process that aims to:
- A) Develop the schedule management plan.
- B) Shorten the project duration without changing the project scope.
- C) Monitor the status of project activities to update project progress and manage changes to the schedule baseline.
- D) Allocate adequate time for project tasks.

A

Correct Answer: C

119
Q

In project risk management, ‘Avoidance’ is a strategy that involves:
- A) Changing the project plan to eliminate the threat posed by an adverse risk.
- B) Accepting the risk and actively responding to its impacts.
- C) Sharing the risk with another party to mitigate its impact.
- D) Ignoring the risk since its impact is deemed insignificant.

A

Correct Answer: A

120
Q

‘Procurement Statements of Work’ (SOW) are created to:
- A) Outline the project’s scope in detail for the procurement team.
- B) Describe the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results.
- C) Define the specific tasks that the project team will perform.
- D) Establish the project’s budget for external purchases.

A

Correct Answer: B

120
Q

Which of the following best describes the ‘Manage Stakeholder Engagement’ process?
- A) Identifying people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project.
- B) Communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.
- C) Monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
- D) Assigning project roles and responsibilities to stakeholders.

A

Correct Answer: B

121
Q

The ‘Cost Performance Index’ (CPI) is a measure of:
- A) The amount of budgeted resources allocated to work.
- B) The financial effectiveness of project activities.
- C) The schedule efficiency of the project.
- D) The projected cost at completion.

A

Correct Answer: B

122
Q

‘Project Charter’ is an output of which process?
- A) Develop Project Management Plan
- B) Identify Stakeholders
- C) Develop Project Charter
- D) Plan Scope Management

A

Correct Answer: C

123
Q

The purpose of ‘Plan Risk Management’ is to:
- A) Identify all potential project risks.
- B) Determine how to approach, plan, and execute risk management activities for a project.
- C) Assign risk owners and develop risk response strategies.
- D) Quantify the possible outcomes for the project and their probabilities.

A

Correct Answer: B

124
Q

‘Work Performance Data’ consists of:
- A) Analyses of project progress and performance.
- B) Raw observations and measurements identified during project activities.
- C) Recommendations for corrective actions based on performance.
- D) Aggregated project performance information.

A

Correct Answer: B

125
Q

Which process aims to review all change requests, approve changes, and manage changes to deliverables, organizational process assets, project documents, and the project management plan?
- A) Direct and Manage Project Work
- B) Perform Integrated Change Control
- C) Monitor and Control Project Work
- D) Control Scope

A

Correct Answer: B

126
Q

‘Qualitative Risk Analysis’ is best used for:
- A) Providing a numerical probability and impact rating of risks.
- B) Prioritizing risks based on their impact and likelihood of occurrence.
- C) Calculating the overall risk score for the project.
- D) Developing detailed risk response plans.

A

Correct Answer: B

127
Q

The ‘Manage Communications’ process involves:
- A) Developing a strategy for managing project communications.
- B) Creating, collecting, distributing, storing, retrieving, and the ultimate disposition of project information in accordance with the communications management plan.
- C) Updating the project management plan and project documents to include new communication strategies.
- D) Monitoring and controlling communications throughout the entire project lifecycle.

A

Correct Answer: B

128
Q

‘Resource Leveling’ can be used to address:
- A) Scope creep by reallocating resources to critical path activities.
- B) Overallocation of resources by adjusting the project schedule.
- C) Budget constraints by reducing the resources assigned to project activities.
- D) Quality issues by assigning more skilled resources to tasks.

A

Correct Answer: B

129
Q

In the ‘Monitor and Control Project Work’ process, a primary activity is to:
- A) Implement approved changes to the project scope, schedule, and cost baselines.
- B) Track, review, and report the progress to meet the performance objectives defined in the project management plan.
- C) Ensure that all project deliverables are completed on time and within budget.
- D) Redefine the project scope based on stakeholder feedback.

A

Correct Answer: B

130
Q

The ‘Perform Qualitative Risk Analysis’ process is essential for:
- A) Identifying new risks throughout the project lifecycle.
- B) Assessing the priority of identified risks for further analysis or action.
- C) Implementing risk response actions for high-priority risks.
- D) Quantitatively analyzing the impact of risks on project objectives.

A

Correct Answer: B

131
Q

‘Stakeholder Engagement’ levels are described by all the following EXCEPT:
- A) Unaware
- B) Resistant
- C) Supportive
- D) Controlled

A

Correct Answer: D

132
Q

Which of the following best describes ‘Earned Value Management’ (EVM)?
- A) A method for measuring project performance and progress in terms of scope, time, and cost.
- B) A technique for forecasting future project performance based on historical data.
- C) A process for managing the project team’s performance and effectiveness.
- D) A system for developing and controlling the project’s budget.

A

Correct Answer: A

133
Q

The main purpose of ‘Develop Project Management Plan’ is to:
- A) Document the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans.
- B) Establish the total scope of the project.
- C) Define and refine objectives and select the best courses of action to achieve project goals.
- D) Ensure that the project will be executed in a controlled manner

A

Correct Answer: A

134
Q

‘Analogous Estimating’ is most reliable when:
- A) The previous projects are substantially similar in fact and not just in appearance.
- B) The project team members have the requisite skills and experience.
- C) The project is unique with no comparable past projects.
- D) Detailed information about the current project is available.

A

Correct Answer: A

135
Q

The ‘Plan Scope Management’ process is crucial for ensuring that:
- A) The project includes all the work required, and only the work required, to complete the project successfully.
- B) The project scope is accurately defined and mapped.
- C) The scope baseline is monitored, verified, and controlled throughout the project lifecycle.
- D) Detailed descriptions of the project and product are documented and protected from scope creep.

A

Correct Answer: A

136
Q

In ‘Manage Team’, the project manager’s role includes:
- A) Assigning tasks and activities to project team members.
- B) Tracking team member performance, providing feedback, resolving issues, and implementing development plans.
- C) Developing the project budget based on team needs.
- D) Communicating project information to external stakeholders.

A

Correct Answer: B

136
Q

‘Monte Carlo Simulation’ in project management is used primarily for:
- A) Determining the project’s critical path.
- B) Estimating the probability of completing the project within the budget and on time.
- C) Identifying potential project risks and their impacts.
- D) Allocating resources across project activities.

A

Correct Answer: B

137
Q

‘Procurement Documents’ are important for:
- A) Establishing communication protocols between the project team and vendors.
- B) Soliciting bids and proposals from prospective sellers.
- C) Describing the project management processes and procedures.
- D) Documenting the project scope for internal stakeholders.

A

Correct Answer: B

138
Q

The ‘Direct and Manage Project Work’ process is responsible for:
- A) Leading and performing the work defined in the project management plan and implementing approved changes.
- B) Tracking, reviewing, and regulating the progress and performance of the project.
- C) Identifying changes to the project scope, schedule, and costs.
- D) Approving or rejecting changes to the project.

A

Correct Answer: A

139
Q

In which process would you determine the project stakeholders’ information needs?
- A) Identify Stakeholders
- B) Plan Stakeholder Engagement
- C) Manage Communications
- D) Plan Communications Management

A

Correct Answer: D

140
Q

What is the primary goal of ‘Control Quality’ in project management?
- A) To ensure that the project adheres to the quality standards set forth in the quality management plan.
- B) To inspect the final product to determine compliance with quality requirements.
- C) To monitor and record the results of executing the quality activities to assess performance and recommend necessary changes.
- D) To identify quality requirements and/or standards for the project and its deliverables.

A

Correct Answer: C

141
Q

The ‘Plan Risk Responses’ process is designed to:
- A) Identify new risks throughout the project.
- B) Develop options and actions to enhance opportunities and reduce threats to project objectives.
- C) Prioritize risks based on their probability and impact.
- D) Monitor and control risks on an ongoing basis.

A

Correct Answer: B

142
Q

‘Earned Value Management’ (EVM) integrates information from which project management knowledge areas?
- A) Scope, Schedule, and Cost
- B) Quality, Human Resources, and Communications
- C) Risk, Procurement, and Stakeholder Management
- D) Scope, Quality, and Procurement

A

Correct Answer: A

143
Q

Which of the following is NOT a typical output of the ‘Develop Project Charter’ process?
- A) Project Charter
- B) Stakeholder Register
- C) Assumption Log
- D) Preliminary Scope Statement

A

Correct Answer: B

144
Q

The ‘To-Complete Performance Index’ (TCPI) provides a measure of:
- A) The cost performance that must be achieved with the remaining resources to meet a specified management goal.
- B) The current cost performance trends of the project.
- C) The performance of the project team against the baseline.
- D) The schedule performance index required to complete on time.

A

Correct Answer: A

145
Q

‘Resource Smoothing’ is a technique that:
- A) Increases the project duration to make better use of resources.
- B) Adjusts the activities of a project such that the requirements on resources do not exceed certain predefined limits.
- C) Allocates extra resources to activities to decrease project duration.
- D) Redistributes work among resources to address a resource bottleneck.

A

Correct Answer: B

146
Q

‘Fast Tracking’ a project involves:
- A) Increasing the project budget to expedite project activities.
- B) Executing more activities in parallel.
- C) Extending the project timeline to accommodate more tasks.
- D) Reducing the project scope to meet time constraints.

A

Correct Answer: B

147
Q

The purpose of ‘Perform Integrated Change Control’ is to:
- A) Ensure that all changes to the project are recorded.
- B) Review all change requests, approve changes, and manage changes to deliverables, organizational process assets, project documents, and the project management plan.
- C) Implement all changes as soon as they are requested.
- D) Update the project management plan with the approved changes.

A

Correct Answer: B

148
Q

‘Quantitative Risk Analysis’:
- A) Assesses the impact of identified risks on project objectives using numerical data.
- B) Determines the probability of achieving project objectives.
- C) Prioritizes risks for further action based on their impact and likelihood.
- D) Is performed immediately after ‘Identify Risks’ process.

A

Correct Answer: A

149
Q

The ‘Manage Stakeholder Engagement’ process is key to:
- A) Identifying all people or organizations affected by the project.
- B) Communicating project information to stakeholders to meet their needs and expectations.
- C) Engaging stakeholders in project decisions and activities based on their needs, interests, and potential impact.
- D) Monitoring overall project stakeholder relationships.

A

Correct Answer: C

150
Q

‘Cost Performance Index’ (CPI) and ‘Schedule Performance Index’ (SPI) are important because they:
- A) Help in identifying the project’s best practices.
- B) Indicate the project’s health in terms of cost and schedule.
- C) Determine the quality of the project’s deliverables.
- D) Measure the effectiveness of stakeholder engagement.

A

Correct Answer: B

151
Q

A ‘Project Scope Statement’ includes:
- A) A detailed list of the project’s deliverables, exclusions, constraints, and assumptions.
- B) The project’s cost baseline.
- C) The schedule for stakeholder engagement activities.
- D) The criteria for project success.

A

Correct Answer: A

152
Q

‘Procurement Documents’ are used primarily for:
- A) Documenting the project’s purchasing decisions.
- B) Soliciting bids and proposals from potential vendors.
- C) Outlining the project’s scope to the team.
- D) Managing project team assignments.

A

Correct Answer: B

153
Q

In ‘Plan Human Resource Management’, the key output is:
- A) A project team directory.
- B) Resource calendars.
- C) The human resource management plan.
- D) Team performance assessments.

A

Correct Answer: C

154
Q

The main objective of ‘Plan Communications Management’ is to:
- A) Develop an appropriate approach for the timely and efficient communication of project information.
- B) Ensure all project information is archived.
- C) Implement communication technologies for the project.
- D) Provide performance reports to stakeholders.

A

Correct Answer: A

155
Q

‘Work Breakdown Structure’ (WBS) is crucial because it:
- A) Defines the project scope by breaking down all project work into smaller, more manageable components.
- B) Provides a schedule for project completion.
- C) Allocates the project budget across tasks.
- D) Identifies the project team required for the project.

A

Correct Answer: A

156
Q

‘Plan Scope Management’ process results in the creation of:
- A) Work Breakdown Structure (WBS).
- B) Scope Management Plan and Requirements Management Plan.
- C) Project Scope Statement.
- D) Change Management Plan.

A

Correct Answer: B

157
Q

The ‘Direct and Manage Project Work’ process involves:
- A) Leading and performing the work defined in the project management plan and implementing approved changes.
- B) Monitoring the project team’s performance.
- C) Managing communications with stakeholders.
- D) Controlling the project schedule.

A

Correct Answer: A

158
Q

What is the purpose of ‘Monitor Stakeholder Engagement’?
- A) To ensure that all stakeholders are satisfied with the project’s deliverables.
- B) To track project progress and performance.
- C) To monitor stakeholder relationships and tailor strategies for engaging stakeholders.
- D) To identify new stakeholders throughout the project lifecycle.

A

Correct Answer: C

158
Q

‘Change Control Tools’ are used in which process?
- A) Perform Integrated Change Control
- B) Direct and Manage Project Work
- C) Monitor and Control Project Work
- D) Plan Risk Management

A

Correct Answer: A

159
Q

The ‘Identify Risks’ process is critical for:
- A) Implementing risk responses.
- B) Developing the risk management plan.
- C) Determining which risks might affect the project and documenting their characteristics.
- D) Prioritizing risks for further analysis.

A

Correct Answer: C

160
Q

‘Risk Urgency Assessment’ is part of which process?
- A) Perform Qualitative Risk Analysis
- B) Identify Risks
- C) Plan Risk Responses
- D) Perform Quantitative Risk Analysis

A

Correct Answer: A

161
Q

‘Cost Aggregation’ refers to:
- A) The summing of individual activity costs to establish a total cost baseline for the project.
- B) The distribution of the overall project budget to individual work items.
- C) The process of determining the project’s cost efficiency.
- D) Aggregating the estimated costs of project phases to determine the project’s ROI.

A

Correct Answer: A

162
Q

Which process involves confirming human resource availability and obtaining the team necessary to complete project assignments?
- A) Develop Project Team
- B) Plan Human Resource Management
- C) Acquire Resources
- D) Manage Team

A

Correct Answer: C

162
Q

‘Stakeholder Engagement Assessment Matrix’ is used to:
- A) Identify all project stakeholders.
- B) Analyze stakeholders’ communication preferences.
- C) Evaluate the current level of stakeholder engagement and compare it to the desired level.
- D) Develop the project charter.

A

Correct Answer: C

163
Q

During which process is the ‘Risk Register’ initially created?
- A) Plan Risk Management
- B) Identify Risks
- C) Perform Qualitative Risk Analysis
- D) Plan Risk Responses

A

Correct Answer: B

164
Q

The ‘Control Costs’ process involves:
- A) Approving project budgets.
- B) Estimating costs of individual project activities.
- C) Monitoring the status of the project to update the project costs and managing changes to the cost baseline.
- D) Determining the budget.

A

Correct Answer: C

165
Q

What is the main outcome of the ‘Develop Project Team’ process?
- A) A list of project team members and their assigned roles.
- B) Improved competencies, team member interaction, and overall team environment to enhance project performance.
- C) The project management plan.
- D) Resource calendars.

A

Correct Answer: B

166
Q

‘Procurement Management Plan’ specifies:
- A) The types of contracts to be used.
- B) The project schedule.
- C) How team members will be acquired.
- D) The stakeholder engagement strategies.

A

Correct Answer: A

167
Q

Which statement best describes the ‘Manage Quality’ process?
- A) It focuses on the adherence to quality standards and the correctness of the deliverables.
- B) It is solely concerned with the quality of the final product.
- C) It ensures that the project employs all processes necessary to meet quality requirements.
- D) It is responsible for quality inspections and audits.

A

Correct Answer: C

168
Q

‘Perform Integrated Change Control’ process is critical because it:
- A) Ensures that all changes are reflected in the project budget.
- B) Requires that all project changes go through a formal review process.
- C) Allows project managers to make changes without stakeholder approval.
- D) Focuses solely on schedule changes.

A

Correct Answer: B