17. Decision Making and Project Appraisal Flashcards

1
Q

What do capital investment decisions consider?

A

Future cash flows

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main cash based measures of investment decisions?

A
  • Payback period
  • Discounted payback period
  • Net present value (NPV)
  • Internal rate of return (IRR)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does payback period calculate?

A

How long it takes for the net cash flows from an investment to repay the initial investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the discounted payback period?

A

The payback period, with time value of money taken into consideration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 5 main benefits of payback as an investment appraisal method?

A
  1. Simple to calculate
  2. Easy to understand
  3. Uses relevant cash flows
  4. Good initial screening tool
  5. Allows for risk in timing of cash flows
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 4 main drawbacks of payback as an investment appraisal method?

A
  1. Ignores time value of money (unless DPP)
  2. Only considers flows up to payback date
  3. May lead to short term decision making
  4. No clear decision rule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the NPV of an investment?

A

The discounted present value of all cash inflows and outflows of an investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Considering NPV, when should a project be undertaken?

A

If NPV is positive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What discount rate do we use when calculating NPV?

A

Cost of capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 4 main benefits of NPV as an investment appraisal method?

A
  1. Allows for time value of money
  2. Shows change in shareholders wealth
  3. Can allow for risk
  4. Looks at entire project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 2 main drawbacks of NPV as an investment appraisal method?

A
  1. Requires cost of capital to be estimated

2. Calculations can be time consuming and not easily understood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the internal rate of return?

A

The discount factor that would give an NPV of zero - the actual % return that the project generates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the relationship between discount factor and NPV?

A

As discount factor increases, NPV decreases - project becomes less attractive as cost of financing increases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do we estimate the IRR?

A

Calculate NPV at discount rate given, and a second discount rate (higher if NPV negative). Estimate the IRR by L + (NPVl)/(NPVl - NPVh) *(H-L)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When do we accept a project using IRR?

A

If IRR> cost of capital

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the 4 main benefits of IRR as an investment appraisal method?

A
  1. It allows for time value of money
  2. Does not require an exact cost of funds to be known
  3. As a % measure it is familiar to non accountants
  4. Looks at the entire project
17
Q

What are the 2 main drawbacks of IRR as an investment appraisal method?

A
  1. It does not tell you whether to accept or reject

2. Possible to have more than one IRR