17. Decision Making and Project Appraisal Flashcards
What do capital investment decisions consider?
Future cash flows
What are the main cash based measures of investment decisions?
- Payback period
- Discounted payback period
- Net present value (NPV)
- Internal rate of return (IRR)
What does payback period calculate?
How long it takes for the net cash flows from an investment to repay the initial investment
What is the discounted payback period?
The payback period, with time value of money taken into consideration
What are the 5 main benefits of payback as an investment appraisal method?
- Simple to calculate
- Easy to understand
- Uses relevant cash flows
- Good initial screening tool
- Allows for risk in timing of cash flows
What are the 4 main drawbacks of payback as an investment appraisal method?
- Ignores time value of money (unless DPP)
- Only considers flows up to payback date
- May lead to short term decision making
- No clear decision rule
What is the NPV of an investment?
The discounted present value of all cash inflows and outflows of an investment
Considering NPV, when should a project be undertaken?
If NPV is positive
What discount rate do we use when calculating NPV?
Cost of capital
What are the 4 main benefits of NPV as an investment appraisal method?
- Allows for time value of money
- Shows change in shareholders wealth
- Can allow for risk
- Looks at entire project
What are the 2 main drawbacks of NPV as an investment appraisal method?
- Requires cost of capital to be estimated
2. Calculations can be time consuming and not easily understood
What is the internal rate of return?
The discount factor that would give an NPV of zero - the actual % return that the project generates
What is the relationship between discount factor and NPV?
As discount factor increases, NPV decreases - project becomes less attractive as cost of financing increases
How do we estimate the IRR?
Calculate NPV at discount rate given, and a second discount rate (higher if NPV negative). Estimate the IRR by L + (NPVl)/(NPVl - NPVh) *(H-L)
When do we accept a project using IRR?
If IRR> cost of capital