15.6 Overhead Variances Flashcards

1
Q

Variable overhead is applied on the basis of standard direct labor hours. If, for a given period, the direct labor efficiency variance is unfavorable, the variable overhead efficiency variance will be

A. Favorable
B. Unfavorable
C. Zero
D. The same amount as the direct labor efficiency variance

A

B. Unfavorable

If variable overhead is applied to production on the basis of direct labor hours, both the variable overhead efficiency variance and the direct labor efficiency variance will be calculated on the basis of the same number of hours. If the direct labor efficiency variance is unfavorable, the overhead efficiency variance will also be unfavorable because both variances are based on the difference between standard and actual direct labor hours worked.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A children’s dress manufacturer’s variable overhead costs are allocated on the basis of budgeted direct labor hours. According to the December budget, each dress takes 4 direct labor hours to produce. Budgeted variable manufacturing overhead cost per labor hour is $12, and the budgeted number of dresses to be made is 1,040. Actual variable manufacturing costs in December were $52,164 for 1,080 dresses produced. Actual direct labor hours were 4,536 hours. The variable overhead spending variance is

A. $2,592 favorable
B. $2,592 unfavorable
C. $2,268 favorable
D. $2,268 unfavorable

A

C. $2,268 favorable

1) Actual variable overhead: $52,164
2) Flexible budget: AQ x SP = 4536 x 12 = 54,432
3) Static Budget: SQ x SP = 4,320 x 12 = 51,840

Spending variance: 1) - 2) = 2268 favorable
Difference efficiency variance: 2) - 3) = 2,592 unfavorable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which one of the following is not normally measured in a standard cost system?

A. Fixed overhead efficiency
B. Variable overhead spending
C. Variable overhead efficiency
D. Fixed overhead spending

A

A. Fixed overhead efficiency

In a standard cost system, the static budget lump-sum of fixed overhead is also the flexible budget amount over the relevant range of output. The efficiency of production does not affect the fixed overhead variances. Thus, a fixed overhead efficiency variance is normally not measured.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A manufacturing company uses a standard cost system that applies overhead based upon direct labor hours. The manufacturing budget for the production of 7,500 units for the month is shown below:

Direct labor (15,000 hours at $20 per hour): $300,000
Variable overhead: 50,000
Fixed overhead: 105,000

During the month, 8,000 units were produced, and the fixed overhead budget variance was $1,000 unfavorable. Fixed overhead during the month was

A. Underapplied by $6,000
B. Underapplied by $7,000
C. Overapplied by $7,000
D. Overapplied by $6,000

A

D. Overapplied by $6,000

The fixed overhead budget variance was $1,000 unfavorable, indicating that actual fixed overhead is $1,000 greater than budgeted fixed overhead. That is, actual fixed overhead is $106,000.

With budgeted fixed overhead of $105,000 and budgeted direct labor hours of 15,000, the budgeted application rate is $7 per direct labor hour. Each unit requires 2 direct labor hours to produce (15,000 / 7,500). Fixed overhead applied is thus $112,000 (8,000 x 2 x $7). With actual fixed overhead of $106,000 and applied fixed overhead of $112,000, fixed overhead during the month was overapplied by $6,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A company planned to produce 50,000 units with $500,000 of manufacturing overhead. The budgeted machine hours per unit is 2 hours. The company’s actual results indicated it spent $505,000 for manufacturing overhead, produced 49,000 units, and used 99,000 machine hours. Under a standard cost system that allocates overhead based upon machine hours, the manufacturing overhead traced to the products would total

A. $500,000
B. $490,000
C. $505,000
D. $495,000

A

B. $490,000

The standard cost of manufacturing overhead applied to each machine hour is $5 [500,000 / (50,000 units x 2 machine hours per unit]. The company actually created 49,000 units. The standard cost of manufacturing overhead applied to each unit is based on the standard cost per machine hour and the standard number of machine hours per unit. Thus, the manufacturing overhead traced to the products is $490,000 (49,000 units x $5 per machine hour x 2 machine hours per unit)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which of these variances is least significant for cost control?

A. Variable O/H spending variance
B. Fixed O/H volume variance
C. Labor price variance
D. Materials quantity variance

A

B. Fixed O/H volume variance

The fixed O/H volume variance occurs when actual activity levels differ from anticipated levels. It is an excellent example of cost allocation as opposed to cost control. Unlike other variances, the volume variance does not directly reflect a difference between actual and budgeted expenditures. The economic substance of this variance lies in the costs or benefits of capacity usage or nonusage. For example, idle capacity results in the loss of the contribution margin from units not produced and sold.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A company has gathered the following information from a recent production run:

Standard variable overhead rate: $10
Actual variable overhead rate: 8
Standard process hours: 20
Actual process hours: 25

What is the company’s variable overhead spending variance?

A. $40 unfavorable
B. $50 favorable
C. $40 favorable
D. $50 unfavorable

A

B. $50 favorable

The variable overhead spending variance is equivalent to the materials price, or labor rate variance. It equals the actual quantity times the difference between the standard and actual rates.

The variable overhead spending variance is therefore $50 [25 hours x (10-8)]. The variance is favorable because the actual rate is less than the standard rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A company uses a standard cost system. On January 1 of the current year, the company budgeted fixed manufacturing overhead cost of $600,000 and production at 200,000 units. During the year, the firm produced 190,000 units and incurred fixed manufacturing overhead of $595,000. The production volume variance for the year was

A. $10,000 unfavorable
B. $25,000 unfavorable
C. $5,000 unfavorable
D. $30,000 unfavorable

A

D. $30,000 unfavorable

The application rate for fixed overhead is $3.00 per unit ($600,000 budgeted cost / 200,000 budgeted units). The actual amount applied was $570,000 (190,000 actual units x $3.00 application rate). The production volume variance was thus $30,000 unfavorable ($570,000 - $600,000).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A company produces and sells replacement parts for cotton processing equipment. Which one of the following cost variances are least likely to be controllable by the production manager?

A. Variable overhead spending variance
B. Labor efficiency variance
C. Materials quantity variance
D. Fixed overhead production volume variance

A

D. Fixed overhead production volume variance

The fixed overhead production volume variance is the difference between the static/flexible budget for fixed overhead and the amount allocated based on the budgeted collection rate and the driver level allowable for the actual production level achieved. None of these factors are under the control of the production manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following overhead variances would be helpful in bringing attention to a potential short-term problem in the control of overhead costs?

  • Spending variance: yes/no
  • Volume variance: yes/no
A
  • Spending variance: yes
  • Volume variance: no

The variable overhead spending variance is favorable or unfavorable if production spending is less or more, respectively, than the standard. The fixed overhead spending variance is attributable to more or less spending by the production. The spending variances can alert the production team that this is a problem with overhead costs. The production volume variance is only for fixed overhead, and it results from the difference between production capacity and capacity usage. It only uses standard cost as a base and would not be a good indicator of a short-term spending problem. In the long-term, both types of variances would be necessary to resolve an overhead costs problems.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A firm uses a standard cost system and applies factory overhead to products on the basis of direct labor hours. If the firm recently reported a favorable direct labor efficiency variance, then the

A. Direct labor rate variance must be unfavorable
B. Variable overhead spending variance must be favorable
C. Fixed overhead volume variance must be unfavorable
D. Variable overhead efficiency variance must be favorable

A

D. Variable overhead efficiency variance must be favorable

Highlight uses direct labor hours as the driver for variable overhead application. Thus, if the direct labor efficiency variance was favorable, the variable overhead efficiency variance must be favorable as well since the two variances are based on the same standard and actual hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which one of the following variances is of least significance from a behavioral control perspective?

A. Unfavorable direct materials quantity variance amounting to 20% of the quantity allowed for the output attained
B. Fixed overhead volume variance resulting from management’s decision midway through the fiscal year to reduce its budgeted output by 20%
C. Unfavorable direct labor efficiency variance amounting to 10% more than the budgeted hours for the output attained
D. Favorable direct labor rate variance resulting from an inability to hire experienced workers to replace retiring workers

A

B. Fixed overhead volume variance resulting from management’s decision midway through the fiscal year to reduce its budgeted output by 20%.

Most variances are of significance to someone who is responsible for that variance. However, a fixed overhead volume variance is often not the responsibility of anyone other than top management. The fixed overhead volume variance equals the difference between budgeted fixed overhead and the amount applied (Standard input allowed for the actual output x Standard rate). It can be caused by economic downturns, labor strife, bad weather, or a change in planned output. Thus, a fixed overhead volume variance resulting from a top management decision to reduce output has fewer behavioral implications than other variances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which type of variance will reflect overtime premiums when the overall volume of work is greater than expected?

A. Labor efficiency
B. Yield
C. Overhead
D. Materials quantity

A

C. Overhead

Overtime premiums arising from a heavy overall volume of work rather than from the requirements of a specific job are deemed to apply to all production. Hence, they are treated as indirect costs and assigned to overhead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The performance report indicated the following information for the past month.

  • Actual total overhead: $1,600,000
  • Budgeted fixed overhead: 1,500,000
  • Applied fixed overhead at $3 per labor hour: 1,200,000
  • Applied variable overhead at $.50 per labor hour: 200,000
  • Actual labor hours: 430,000

Total overhead spending variance for the month was

A. $185,000 unfavorable
B. $100,000 favorable
C. $200,000 unfavorable
D. $115,000 favorable

A

D. $115,000 favorable

The total overhead applied was $1,400,000
($1,200,000 fixed + $200,000 variable)

Since the actual overhead was $1,600,000, the total overhead variance was $200,000 unfavorable. The $200,000 total variance would be explained by three elements: the fixed overhead volume variance, the variable overhead efficiency variance, and the total spending variance.

At $3 per hour, fixed overhead was applied on the basis of 400,000 hours ($1,200,000 applied fixed overhead / $3 per labor hour). But since the budget called for 500,000 hours (1,500,000 budgeted overhead / $3 per labor hour), there was an unfavorable volume variance of 100,000 hours at $3, or $300,000.

The variable overhead efficiency variance is calculated by multiplying the excess hours of 30,000 (430,000 - 400,000) time the variable application rate of $.50, or $15,000 unfavorable.

Therefore, when you combine the $300,000 unfavorable volume variance and the $15,000 unfavorable efficiency variance, you get $315,000 unfavorable. Since the total variance was only $200,000 unfavorable, the spending variance must be favorable in the amount of $115,000. Algebraically, this is solved as $300,000 U + 15,000 U - SV = 200,000 U

Thus SV = 115,000 F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A supervisor controls her department’s costs. The following data relate to her department for the month of June:

Variable factory overhead
* Budgeted based on actual input: 100,000
* Actual: 106,250

Fixed factory overhead
* Budgeted: $31,250
* Actual: 33,750

What was the department’s total spending variance for June?

A. $2,500 U
B. $6,250 U
C. $8,750 U
D. $3,750 F

A

C. $8,750 U

Spending variance = actual total overhead - (budgeted fixed overhead + variable overhead budgeted for the actual input).

The total actual overhead is $140,000 (106,250+33,750). The sum of budgeted fixed overhead and variable overhead budgeted for the actual input is $131,250 (100,000 + 31,250).

Thus, the total spending variance is $8,750 (140,000 - 131,250). The variance is unfavorable because the actual overhead exceeds the budgeted overhead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following is used to compute the total overhead spending variance?

  • Actual factory overhead: yes/no
  • Budgeted allowance based on actual input: yes/no
  • Budget allowance based on standard input: yes/no
A
  • Actual factory overhead: yes
  • Budgeted allowance based on actual input: yes
  • Budget allowance based on standard input: no

The total overhead spending variance is the difference between actual total overhead and the sum of the budgeted (lump-sum) fixed overhead and the variable overhead budgeted for the actual input at the standard rate. It combines the variable overhead spending and the fixed overhead budget (spending) variances.

17
Q

A company ends the month with a volume variance of $6,360 unfavorable. If budgeted fixed O/H was $480,000, O/H was applied on the basis of 32,000 budgeted machine hours, and budgeted variable O/H was $170,000, what were the actual number of machine hours (AH) for the month?

A. 32,000
B. 32,318
C. 31,576
D. 32,425

A

C. 31,576

The volume variance (VV) arises from the difference between budgeted fixed O/H and the fixed O/H applied at the standard rate based on the standard input allowed for actual output. The O/H rate is $15 per machine hour ($480,000 / 32,000)

VV = budgeted fixed O/H - Applied Fixed O/H
$6,360 = $480,000 - (15 x AH)
$15 x AH = $480,000 - 6,360
AH = 473,640 / 15
AH = 31,576

18
Q

A fixed overhead volume variance based on standard direct labor hours measures

A. Deviation from standard direct labor hour capacity.
B. Fixed overhead use.
C. Fixed overhead efficiency.
D. Deviation from the normal, or denominator, level of direct labor hours.

A

D. Deviation from the normal, or denominator, level of direct labor hours.

The fixed overhead volume variance measures the effect of not operating at the budgeted (denominator) activity level. It is the difference between budgeted fixed costs and the product of the standard fixed overhead application rate and the standard activity level for the actual output. A favorable variance means that activity was greater than expected and that fixed overhead was overapplied. It might be caused by, for example, hiring more workers to provide an extra shift. An unfavorable volume variance means that activity was less than budgeted (overhead was underapplied), for example, because of insufficient sales or a labor strike. Accordingly, the volume variance is usually outside the control of production management. Moreover, unlike other variances, it does not directly reflect a difference between actual and budgeted expenditure of resources.

19
Q

A manufacturer uses a standard cost system with overhead applied based upon direct labor hours. The manufacturing budget for the production of 5,000 units for the month of May included the following information:

Direct labor
10,000 hours at $15 per hour: $150,000
Variable overhead: 30,000
Fixed overhead: 80,000

During May, 6,000 units were produced and the fixed overhead budget variance was $2,000 favorable. Fixed overhead during May was

A. Underapplied by $2,000.
B. Underapplied by $16,000.
C. Overapplied by $16,000.
D. Overapplied by $18,000.

A

D. Overapplied by $18,000.

First, the actual production level for the month was 6,000 units of output. Second, the standard number of labor hours consumed per unit of output is 2 (10,000 budgeted direct labor hours ÷ 5,000 budgeted units output). Third, since fixed overhead for the month was budgeted at $80,000 and it is to be applied in proportion to 10,000 budgeted direct labor hours, the application rate is $8 per direct labor hour ($80,000 ÷ 10,000). Thus, the amount of fixed overhead applied for the month was $96,000 = (6,000 × $8 × 2). The fixed overhead budget variance was $2,000 favorable, which means the actual fixed overhead incurred for the month was $78,000 ($80,000 – $2,000). Thus, fixed overhead was overapplied by $18,000 ($96,000 – $78,000).

20
Q

Nanjones Company manufactures a line of products distributed nationally through wholesalers. Presented below are planned manufacturing data for the year and actual data for November of the current year. The company applies overhead based on planned machine hours using a predetermined annual rate.

Planning Data
Fixed overhead
- Annual: $1,200,000
- November: $100,000
Variable overhead
- Annual: $2,400,000
- November: $220,000
Direct labor hours
- Annual: 48,000
- November: 4,000
Machine hours
- Annual: 240,000
- November: 22,000

Data for November
Direct labor hours (actual): 4,200
Direct labor hours (plan based on output): 4,000
Machine hours (actual): 21,600
Machine hours (plan based on output): 21,000
Fixed overhead: $101,200
Variable overhead: $214,000

Nanjones’ fixed overhead volume variance for November was

A. $10,000 favorable.
B. $5,000 favorable.
C. $5,000 unfavorable.
D. $1,200 unfavorable.

A

B. $5,000 favorable.

The fixed overhead volume (production volume or idle capacity) variance is the difference between budgeted fixed costs and the product of the standard fixed overhead cost per unit of input and the standard units of input allowed for the actual output. Budgeted fixed costs for the month were $100,000. The standard cost of actual output was $105,000 [21,000 machine hours planned for actual output × ($1,200,000 planned annual FOH ÷ 240,000 planned annual machine hours) FOH application rate]. Hence, the fixed overhead volume variance was $5,000 favorable. It was favorable because the budget for fixed overhead was less than the amount applied to jobs. An overapplication of fixed overhead suggests that output exceeded expectations.

21
Q

Franklin Glass Works’ production budget for the year ended November 30 was based on 200,000 units. Each unit requires 2 standard hours of labor for completion. Total overhead was budgeted at $900,000 for the year, and the fixed overhead rate was estimated to be $3.00 per unit. Both fixed and variable overhead are assigned to the product on the basis of direct labor hours. The actual data for the year ended November 30 are presented as follows.

Actual production in units: 198,000
Actual direct labor hours: 440,000
Actual variable overhead: $352,000
Actual fixed overhead: $575,000

Franklin’s fixed overhead spending variance for the year is

A. $19,000 favorable.
B. $5,750 favorable.
C. $25,000 favorable.
D. $25,000 unfavorable.

A

C. $25,000 favorable.

Actual fixed overhead was $575,000. Budgeted fixed overhead was $3 per unit at an estimated production of 200,000 units; a total of $600,000. The difference of $25,000 is a favorable variance because the actual amount was less than that budgeted.

22
Q

Last year, a firm budgeted $600,000 of fixed overhead for its plant that manufactures moisturizing cream. The $600,000 was based on a denominator activity level of 40,000 machine hours. There are 0.1 standard machine hours for each bottle of moisturizing cream. 350,000 bottles of moisturizing cream were produced, and 360,000 bottles were sold last year. What was the production volume variance?

A. $75,000 unfavorable.
B. $60,000 favorable.
C. $75,000 favorable.
D. $60,000 unfavorable.

A

Answer (A) is correct.
Each bottle is budgeted to use $1.50 of fixed overhead, at a denominator of 40,000 machine hours or 400,000 bottles. Because only 350,000 bottles were produced, only $525,000 of fixed overhead has been applied. Therefore, there is a $75,000 unfavorable production volume variance ($600,000 – $525,000).

23
Q

A firm uses a standard costing system and allocates variable overhead costs based on direct labor hours. The annual budget projected 1,000 finished units, 10,000 hours of direct labor, and $100,000 of variable overhead costs. At the end of the year, 750 units were completed using 8,000 hours of direct labor and $75,000 in variable overhead. What is the variable overhead spending variance?

A. $5,000 unfavorable.
B. $0
C. $5,000 favorable.
D. $25,000 favorable.

A

C. $5,000 favorable.

The spending variance is the difference between (1) actual variable overhead and (2) the product of the budgeted application rate and the actual amount of the allocation base. The actual variable overhead is stated as $75,000. The firm uses direct labor hours as an allocation base. Thus, the budgeted application rate is equal to $10/DLH ($100,000 budgeted variable overhead ÷ 10,000 budgeted DLHs). The actual amount of direct labor hours was 8,000. Thus, the product of the budgeted application rate ($10) times the actual amount of the allocation base (8,000 DLH) is $80,000. Since the actual overhead of $75,000 is less than the $80,000, the variable overhead spending variance is a favorable $5,000 ($75,000 – $80,000).