15: Operational strategies: lean production Flashcards

1
Q

Lean production:

A

The adoption of techniques that help to reduce waste.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Just-in-time (JIT):

A

A lean production technique which aims to minimise stock holdings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Kaizen:

A

A lean production technique which aims to improve efficiency by making small but frequent improvements, also known as continual improvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Time-based management:

A

Managing resources effectively to ensure products are fit for market in the shortest time possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Critical path analysis (CPA):

A

A technique for planning complex projects to allow them to be completed in the shortest time possible by identifying activities that can be carried out simultaneously.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical path network:

A

A visual representation of the sequencing and timing of all the activities involved in completing a complex project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Earliest start time (EST):

A

The earliest time an activity can start in a project based upon the completion of a preceding activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Latest finish time (LFT):

A

The latest time an activity must be completed by to avoid any delay in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Critical path:

A

The route which outlines all those activities than cannot be delayed, i.e. have zero float time, if the project is to be completed on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Critical activities:

A

Those activities with zero float time, i.e. if it takes four weeks to complete, there is only four weeks between EST and LFT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Float time:

A

The amount of time by which a non-critical activity could be delayed without having an effect on the whole project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Non-crital activities:

A

Those activities with float time, i.e. if it takes four weeks to complete, there may be six weeks between the EST and LFT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly