15: Operational strategies: lean production Flashcards
Lean production:
The adoption of techniques that help to reduce waste.
Just-in-time (JIT):
A lean production technique which aims to minimise stock holdings.
Kaizen:
A lean production technique which aims to improve efficiency by making small but frequent improvements, also known as continual improvement.
Time-based management:
Managing resources effectively to ensure products are fit for market in the shortest time possible.
Critical path analysis (CPA):
A technique for planning complex projects to allow them to be completed in the shortest time possible by identifying activities that can be carried out simultaneously.
Critical path network:
A visual representation of the sequencing and timing of all the activities involved in completing a complex project.
Earliest start time (EST):
The earliest time an activity can start in a project based upon the completion of a preceding activity.
Latest finish time (LFT):
The latest time an activity must be completed by to avoid any delay in the project.
Critical path:
The route which outlines all those activities than cannot be delayed, i.e. have zero float time, if the project is to be completed on time.
Critical activities:
Those activities with zero float time, i.e. if it takes four weeks to complete, there is only four weeks between EST and LFT.
Float time:
The amount of time by which a non-critical activity could be delayed without having an effect on the whole project.
Non-crital activities:
Those activities with float time, i.e. if it takes four weeks to complete, there may be six weeks between the EST and LFT.