1.13 Contractor Safety Flashcards

0
Q

What are the responsibilities of the Client during a notifiable project?

A

Appoint a competent CDM Co-ordinator and competent contractor as Principal contractor.

Be satisfied that CDM Co-ordinator, designer and contractor are competent

Pass on pre construction information

Ensure project is managed SFAIRP to avoid risks.

Ensure welfare facilities are available during construction and sit is safe.

Ensure work does not start before construction phase plan is in place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

What is the criteria for a project to become a notifiable project under CDM?

A

Projects last over 30 days or with 500+ people involved.

Projects require formal plans and files, the appointment of a CDM Co-ordinator, Designer and Principal Contractor.

Demolition work must always have a method statement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the responsibilities of the Designer?

A

Ensure client is aware of duties before preparing design

Ensure SFAIRP design avoids foreseeable risks to construction/cleaning workers

Ensure SFAIRP design includes info about structure/materials that may be affect H&S

Co-operate with CDM Co-ordinator

Ensue building complies with workplace regs (H&S welfare).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the responsibilities of the CDM Co-ordinator?

A

Ensure SFAIRP that the design includes considerations &info required via the duties on designers.

Co-ordinate early design work

Ensure co-operation between designers

Advise client and contractor on competency and provision of adequate resources in appointments

Ensure H&S files is delivered to client on completion of the project

Notify HSE on form 10 unless it a domestic client in which case it’s the Principal contractors responsibility

Manage early H&S communication

Liaise with principal contractor re: ongoing construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the responsibilities of the Principal Contractor?

A

Planning, managing and monitoring all construction work

Preparing construction phase plan for notifiable projects

Ensure contractors comply with rules in construction H&S plan

Liaise with contractors in developing plan and provide with relevant parts of plan

Arranging site inductions and any further training/info required

Consulting with workers

Liaising with CDM coordinator re: ongoing construction

Ensuring site is secure at all times

Ensuring the safety of all on site (Inc. visitors)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is pre tendering information?

A

A collections of information which contractor would need to be able to put in to realistic tender to complete the construction project. It’s complied by the CDM coordinator I.e. Site access, exiting hazards, details of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the construction phase safety plan?

A

Developed by the principal contractor

Must include:

Risk assessments

Welfare arrangements

Emergency procedures

Site ruled

Sire security measures

Document should show how the principals contractor is going two manage the project and highlight key risks.

Plan has 3 distinct parts

Project description

Safety management

Dealing with site specific hazards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the health and safety file?

A

Document completed at end of job and provided to client allowing them to mange, maintain, repair and demolish the structure in the future.

It contains:

Maintenance information

How it was built

As built drawings

Any services in place

Materials used

Manufacturers manuals for all fittings and fixtures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly