1 Project Definition Flashcards

1
Q

What characterizes a project?

A
  • time limit
  • novelty
  • uniqueness
  • size
  • complexity and collaborative characteristic
  • high degree of difficulty and risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Definition of a “project” according to DIN standard 69901

A
A project is essentially characterized by the uniqueness of the conditions in their entirety, such as
• target
• time, financial or other limitations
• differentiation from other projects
• project-specific organization
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Definition of a “project management” according to DIN standard 69901

A
The whole set of related to...
• leadership tasks, 
• organization, 
• techniques, 
• and resources 
...for managing a project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is project management?

A
interdisciplinary coordination of 
• planning, 
• decision-making, 
• implementation, 
• monitoring 
• and control 
for the handling of interdisciplinary tasks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

dimensions of project success

A
  • quality
  • cost
  • time

• overall: stakeholder satisfaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

project management: task areas

A

• project targets

  • organizational structure
  • operational structure
  • project planning
  • leadership
  • project controlling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

phases of a project

A
  • project initiation
  • project planning
  • project execution
  • project monitoring and control
  • project closure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the characteristics of a project compared to routine tasks?

A
Project:
• one-time activities
• individual activities
• "do it right the first time" claim
• rarely reproducible results
• systematic errors difficult to recognize
• immediate correction neccessary
• mostly interdisciplinary handling
• mostly dynamic boundry conditions
routine tasks: 
• routine activities
• standardisable activities
• trainable activities
• reproducible results
• systematic errors easy to recognize
• continuous improvement possible
• mostly department-specific processing 
• mostly static conditions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly