1-200 Flashcards
An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget, D. High-level risks
Acceptance criteria.
Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case
Business case
Which input to the Plan Risk Management process provides information on high-level risks? A. Project charter B. Enterprise environmental factors C. Stakeholder register D. Organizational process assets
Project charter
Which item is an example of personnel assessment? A. Resource calendar B. Tight matrix C. Team-building activity D. Focus group
Focus group
Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
Stakeholder management plan
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? A. Procurement documents B. Communications plan C. Project charter D. Stakeholder register
Project charter
The Identify Stakeholders process is found in which Process Group? A. Initiating B. Monitoring and Controlling C. Planning D. Executing
Initiating
An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast.
Business case.
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? A. Project Risk Management B. Project Human Resource Management C. Project Scope Management D. Project Stakeholder Management
Project Stakeholder Management
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter
Stakeholder register
In which Knowledge Area is the project charter developed? A. Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration Management
Project Integration Management
The ability to influence cost is greatest during which stages of the project? A. Early B. Middle C. Late D. Completion
Early
Which process involves developing an approximation of the monetary resources needed to complete project activities? A. Estimate Costs B. Control Costs C. Determine Budget D. Plan Cost Management
Estimate Costs
Which tool or technique is used in the Develop Project Management Plan process? A. Pareto diagram B. Performance reporting C. SWOT analysis D. Expert judgment
Expert judgment
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk: A. Responses B. Appetite C. Tolerance D. Attitude
Responses
An output of the Manage Stakeholder Engagement process is: A. change requests B. enterprise environmental factors C. the stakeholder management plan D. the change log
change requests
Which process numerically analyzes the effect of identified risks on overall project objectives? A. Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Which Collect Requirements output links the product requirements to the deliverables that satisfy them? A. Requirements documentation B. Requirements traceability matrix C. Project management plan updates D. Project documents updates
Requirements traceability matrix
A temporary endeavor that creates a unique product or service is called a: A. Project B. Plan C. Program D. Portfolio
Project
The process of prioritizing risks for further analysis or action is known as: A. Plan Risk Management. B. Plan Risk Responses. C. Perform Qualitative Risk Analysis. D. Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
Stakeholder satisfaction should be managed as a key project: A. Benefit B. Initiative C. Objective D. Process
Objective
Which cost is associated with nonconformance? A. Liabilities B. Inspections C. Training D. Equipment
Liabilities
Identify Risks is part of which Process Group? A. Planning B. Executing C. Closing D. Initiating
Planning
The business needs, assumptions, and constraints and the understanding of the customers needs
and high-level requirements are documented in the:
A. Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register.
Project charter
Which Process Group and Knowledge Area include the Sequence Activities process?
A. Executing Process Group and Project Time Management
B. Executing Process Group and Project Cost Management
C. Planning Process Group and Project Time Management
D. Planning Process Group and Project Cost Management
Planning Process Group and Project Time Management
In the Plan Stakeholder Management process, expert judgment is used to:
A. Provide information needed to plan appropriate ways to engage project stakeholders.
B. Ensure comprehensive identification and listing of new stakeholders.
C. Analyze the information needed to develop the project scope statement.
D. Decide the level of engagement of the stakeholders at each required stage
Decide the level of engagement of the stakeholders at each required stage
Power, urgency, and legitimacy are attributes of which stakeholder classification model? A. Salience B. Influence/impact C. Power/interest D. Power/influence
Salience
Through whom do project managers accomplish work? A. Consultants and stakeholders B. Stakeholders and functional managers C. Project team members and consultants D. Project team members and stakeholders
Project team members and stakeholders
A stakeholder expresses a need not known to the project manager. The project manager most
likely missed a step in which stakeholder management process?
A. Plan Stakeholder Management
B. Identify Stakeholders
C. Manage Stakeholder Engagement
D. Control Stakeholder Engagement
Plan Stakeholder Management
Skills necessary for project management such as motivating to provide encouragement; listening
actively; persuading a team to perform an action; and summarizing, recapping, and identifying
next steps are known as:
A. organizational skills
B. technical skills
C. communication skills
D. hard skills
communication skills
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an: A. improvement B. program C. result D. portfolio
improvement
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk: A. management B. response C. tolerance D. appetite
appetite
The zero duration of milestones in project planning occurs because milestones:
A. Are unpredictable and challenge the Plan Schedule Management process.
B. Occur at random times in the project plans.
C. Represent a moment in time such as a significant project point or event.
D. Represent both significant and insignificant points in the project and are difficult to anticipate.
Represent a moment in time such as a significant project point or event.
The component of the human resource management plan that includes ways in which team
members can obtain certifications that support their ability to benefit the project is known as:
A. recognition and rewards
B. compliance
C. staff acquisition
D. training needs
training needs
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be: A. Continuous B. Discrete C. Regulated D. Arbitrary
Continuous
In project management, a temporary project can be: A. Completed without planning B. A routine business process C. Long in duration D. Ongoing to produce goods
Long in duration
Which document in the project management plan can be updated in the Plan Procurement Management process? A. Budget estimates B. Risk matrix C. Requirements documentation D. Procurement documents
Requirements documentation
Which type of probability distribution is used to represent uncertain events such as the outcome of
a test or a possible scenario in a decision tree?
A. Uniform
B. Continuous
C. Discrete
D. Linear
Discrete
Which stakeholder approves a project's result? A. Customer B. Sponsor C. Seller D. Functional manager
Customer
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives? A. Collect Requirements B. Plan Scope Management C. Define Scope D. Define Activities
Collect Requirements
Plan Communications Management develops an approach and plan for project communications
based on stakeholders’ needs and requirements and:
A. Available organizational assets
B. Project staff assignments
C. Interpersonal skills
D. Enterprise environmental factors
Available organizational assets
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)? A. 0.03 B. 0.06 C. 0.10 D. 0.50
0.06
A complete set of concepts, terms, and activities that make up an area of specialization is known as: A. a Knowledge Area B. a Process Group C. program management D. portfolio management
a Knowledge Area
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as: A. exploit B. avoid C. mitigate D. share
mitigate
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager? A. Control Quality B. Monitor and Control Project Work C. Control Scope D. Perform Integrated Change Control
Perform Integrated Change Control
Project management processes ensure the:
A. alignment with organizational strategy
B. efficient means to achieve the project objectives
C. performance of the project team
D. effective flow of the project throughout its life cycle
effective flow of the project throughout its life cycle
Which project risk listed in the table below is most likely to occur? A. 1 B. 2 C. 3 D. 4
2
Which is an enterprise environmental factor?
A. Marketplace conditions
B. Policies and procedures
C. Project files from previous projects
D. Lessons learned from previous projects
Marketplace conditions
Project Stakeholder Management focuses on: A. project staff assignments B. project tea m acquisition C. managing conflicting interests D. communication methods
managing conflicting interests
A risk that arises as a direct result of implementing a risk response is called a: A. contingent risk B. residual risk C. potential risk D. secondary risk
secondary risk
The purpose of developing a project scope management plan is to:
A. Manage the timely completion of the project.
B. Ensure that the project includes all of the work required.
C. Make sure the project will satisfy the needs for which it was begun.
D. Reduce the risk of negative events in the project.
Ensure that the project includes all of the work required.
A tool and technique used in the Develop Project Charter process is: A. change control tools B. expert judgment C. meetings D. analytical techniques
expert judgment
A projects purpose or justification, measurable project objectives and related success criteria, a
summary milestone schedule, and a summary budget are all components of which document?
A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan
Project charter
Project managers who lead by example and follow through on the commitments they make
demonstrate the key interpersonal skill of:
A. influencing
B. leadership
C. motivation
D. coaching
influencing
The process of defining how the project scope will be validated and controlled is known as: A. Define Scope. B. Develop Project Management Plan. C. Plan Scope Management. D. Plan Quality Management
Plan Scope Management.
Technical capability, past performance, and intellectual property rights are examples of: A. performance measurement criteria B. source selection criteria C. product acceptance criteria D. phase exit criteria
source selection criteria
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as: A. Earned value management. B. Forecasting. C. Critical chain methodology. D. Critical path methodology.
Earned value management.
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses? A. Identify Risks B. Plan Risk Management C. Perform Qualitative Risk Analysis D. Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
Which element does a project charter contain? A. Management reserves B. Work breakdown structure C. Stakeholder list D. Stakeholder register
Stakeholder list
Every project creates a unique product, service, or result that may be: A. tangible B. targeted C. organized D. variable
tangible
The degree, amount, or volume of risk that an organization or individual will withstand is called risk: A. appetite B. tolerance C. threshold D. management
tolerance
An issue log is an input to which Project Human Resource Management process? A. Manage Project Team B. Acquire Project Team C. Plan Human Resource Management D. Develop Project Team
Manage Project Team
The component of the risk management plan that documents how risk activities will be recorded is called: A. tracking B. scoping C. timing D. defining
tracking
Which Control Stakeholder Engagement tool or technique allows the project manager to
consolidate and facilitate distribution of reports?
A. Information management systems
B. Work performance reports
C. Stakeholder analysis
D. Data gathering and representation
Information management systems
Which basic quality tool explains a change in the dependent variable in relationship to a change
observed in the corresponding independent variable?
A. Cause-and-effect diagram
B. Histogram
C. Control chart
D. Scatter diagram
Scatter diagram
High-level project risks are included in which document? A. Business case B. Risk breakdown structure C. Project charter D. Risk register
Project charter
The scope management plan and scope baseline are contained in: A. organizational process assets B. a requirements traceability matrix C. the project charter D. the project management plan
the project management plan
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a: A. portfolio B. program C. selection D. sub portfolio
program
The stakeholder register is an output of: A. Identify Stakeholders. B. Plan Stakeholder Management. C. Control Stakeholder Engagement. D. Manage Stakeholder Engagement
Identify Stakeholders.
An output of the Develop Project Team process is: A. change requests B. team performance assessments C. project staff assignments D. project documents updates
team performance assessments
The formal and informal interaction with others in an organization industry, or professional environment is known as: A. negotiation B. organizational theory C. meeting D. networking
networking
Which process is included in the Project Integration Management Knowledge Area? A. Manage Project Team B. Collect Requirements C. Sequence Activities D. Direct and Manage Project Work
Direct and Manage Project Work
The project manager notes that stakeholders are aware of the project and potential impacts and
are actively engaged in ensuring that the project is a success. The engagement level of the
stakeholders should be classified as:
A. Supportive
B. Leading
C. Neutral
D. Resistant
Leading
Which of the following is a narrative description of products, services, or results to be delivered by a project? A. Project statement of work B. Business case C. Accepted deliverable D. Work performance information
Project statement of work
A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:
A. Historical information and the lessons-learned database.
B. Historical information and the stakeholder register.
C. Organizational process assets and the lessons-learned database.
D. Project documents and historical information
Historical information and the lessons-learned database.
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)? A. 0.45 B. 0.56 C. 0.70 D. 1.36
0.70
The scope of a project cannot be defined without some basic understanding of how to create the specified: A. objectives B. schedule C. product D. approach
product
The creation of an internet site to engage stakeholders on a project is an example of which type of communication? A. Push B. Pull C. Interactive D. Iterative
Pull
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project? A. Build vs. buy B. Expert judgment C. Alternatives identification D. Product analysis
Alternatives identification
Most experienced project managers know that:
A. every project requires the use of all processes in the PMBOK® Guide.
B. there is no single way to manage a project.
C. project management techniques are risk free.
D. there is only one way to manage projects successfully
there is no single way to manage a project
The product scope description is used to:
A. Gain stakeholders’ support for the project.
B. Progressively elaborate the characteristics of the product, service, or result.
C. Describe the project in great detail.
D. Define the process and criteria for accepting a completed product, service, or result.
Progressively elaborate the characteristics of the product, service, or result
Which of the following is TRUE about most project life cycles?
A. Staffing level is highest at the start.
B. The stakeholders’ influence is highest at the start.
C. The level of uncertainty is lowest at the start.
D. The cost of changes is highest at the start.
The stakeholders’ influence is highest at the start.
An input required in Define Scope is an organizational: A. structure. B. process asset. C. matrix. D. breakdown structure
process asset.
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party? A. Mitigate B. Transfer C. Share D. Avoid
Share
Which activity is an input to the Conduct Procurements process? A. Organizational process assets B. Resource availability C. Perform Integrated Change Control D. Team performance assessment
Organizational process assets
Which of the following investigates the likelihood that each specific risk will occur?
A. Risk register
B. Risk audits
C. Risk urgency assessment
D. Risk probability and impact assessment
Risk probability and impact assessment
What is a hierarchically organized depiction of the identified project risks arranged by risk category? A. Risk register B. Risk breakdown structure (RBS) C. Risk management plan D. Risk category
Risk breakdown structure (RBS)
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process? A. Organizational standard processes B. Marketplace conditions C. Historical information D. Templates
Marketplace conditions
The Define Scope process is in which of the following Process Groups? A. Initiating B. Planning C. Monitoring and Controlling D. Executing
Planning
Organizations perceive risks as:
A. events that will inevitably impact project and organizational objectives.
B. the effect of uncertainty on their project and organizational objectives.
C. events which could have a negative impact on project and organizational objectives.
D. the negative impact of undesired events on their project and organizational objectives.
the effect of uncertainty on their project and organizational objectives.
Who selects the appropriate processes for a project?
A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor
Project manager and project team
The scope management plan is a subsidiary of which project document? A. Schedule management plan B. Project management plan C. Quality management plan D. Resource management plan
Project management plan
The Verify Scope process is primarily concerned with:
A. formalizing acceptance of the completed project deliverables.
B. accuracy of the work deliverables.
C. formalizing approval of the scope statement.
D. accuracy of the work breakdown structure (WBS).
formalizing acceptance of the completed project deliverables.
Which is a tool or technique used in Define Scope? A. Templates, forms, and standards B. Change requests C. Product analysis D. Project assumptions
Product analysis
Which of the following is an output of the Define Activities process? A. Activity list B. Project plan C. Activity duration estimates D. Project schedule
Activity list
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks? A. Identify Risks B. Perform Qualitative Risk Analysis C. Plan Risk Management D. Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
What is one of the objectives of Project Risk Management?
A. Decrease the probability and impact of an event on project objectives.
B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in
place.
C. Increase the probability and impact of positive events.
D. Removal of project risk
Increase the probability and impact of positive events
Which type of managers do composite organizations involve?
A. Functional managers and manager of project managers
B. Functional managers only
C. Project managers only
D. Technical managers and project managers
Functional managers and manager of project managers
Assigned risk ratings are based upon: A. Root cause analysis. B. Risk probability and impact assessment. C. Expert judgment. D. Revised stakeholders' tolerances
Risk probability and impact assessment
Which of the following statements best describes the influence of stakeholders and the cost of
changes as project time advances?
A. The influence of the stakeholders increases, the cost of changes increases.
B. The influence of the stakeholders decreases, the cost of changes increases.
C. The influence of the stakeholders increases, the cost of changes decreases.
D. The influence of the stakeholders decreases, the cost of changes decreases.
The influence of the stakeholders decreases, the cost of changes increases
Which process includes prioritizing risks for subsequent further analysis or action by assessing
and combining their probability of occurrence and impact?
A. Perform Qualitative Risk Analysis
B. Perform Quantitative Risk Analysis
C. Plan Risk Management
D. Plan Risk Responses
Perform Qualitative Risk Analysis
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after
improvements in the industry and electronics technology. With which of the following strategic
considerations is this project mainly concerned?
A. Customer request
B. Market demand
C. Technological advance
D. Strategic
Technological advance
Which of the following processes are part of the Project Integration Management Knowledge
Area?
A. Develop Project Management Plan, Collect Requirements, Create WBS
B. Develop Project Management Plan, Control Scope, Develop Schedule
C. Develop Project Charter, Define Scope, Estimate Costs
D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase
Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria? A. Decomposition B. Benchmarking C. Inspection D. Checklist analysis
Inspection
Which group creativity technique asks a selected group of experts to answer questionnaires and
provide feedback regarding the responses from each round of requirements gathering?
A. The Delphi technique
B. Nominal group technique
C. Affinity diagram
D. Brainstorming
The Delphi technique
At which point of the project is the uncertainty the highest and the risk of failing the greatest? A. Final phase of the project B. Start of the project C. End of the project D. Midpoint of the project
Start of the project
What type of project structure is a hierarchically organized depiction of the resources by type?
A. Organizational breakdown structure (OBS)
B. Resource breakdown structure (RBS)
C. Work breakdown structure (WBS)
D. Project breakdown structure (PBS)
Resource breakdown structure (RBS)
Plan Risk Management is the process of defining how to:
A. Communicate identified risks to the project stakeholders.
B. Conduct risk management activities for a project.
C. Analyze the impact a specific risk may have on the project.
D. Address unexpected risks that may occur during a project
Conduct risk management activities for a project.
What is the definition of Direct and Manage Project Execution?
A. Integrating all planned activities
B. Performing the activities included in the plan
C. Developing and maintaining the plan
D. Execution of deliverables
Performing the activities included in the plan
What name(s) is (are) associated with the Plan-Do-Check-Act cycle? A. Pareto B. Ishikawa C. Shewhart-Deming D. Delphi
Shewhart-Deming
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project
cost. What should be used to calculate the forecast?
A. BAC
B. EAC
C. ETC
D. WBS
EAC
A weighting system is a tool for which area of Conduct Procurements? A. Plan contracting B. Requesting seller responses C. Selecting seller's D. Planning purchase and acquisition
Selecting seller’s
What causes replanning of the project scope? A. Project document updates B. Project scope statement changes C. Variance analysis D. Change requests
Change requests
Which of the following is an output of the Distribute Information process? A. Project calendar B. Communications management plan C. Organizational process assets updates D. Project document updates
Organizational process assets updates
The project scope statement and resource calendars are inputs to which Project Time Management process? A. Sequence Activities B. Estimate Activity Resources C. Develop Schedule D. Control Schedule
Develop Schedule
Which process determines the risks that might affect the project? A. Perform Qualitative Risk Analysis B. Identify Risks C. Plan Risk Management D. Perform Quantitative Risk Analysis
Identify Risks
What risk technique is used to quantify the probability and impact of risks on project objectives? A. Expert judgment B. Risk registry C. Risk response planning D. Interviewing
Interviewing
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work? A. WBS directory B. Activity list C. WBS D. Project schedule
WBS
Which type of analysis is used as a general management technique within the Plan Procurements process? A. Risk assessment analysis B. Make or buy analysis C. Contract value analysis D. Cost impact analysis
Make or buy analysis
Which of the following tools and techniques is used in the Verify Scope process? A. Inspection B. Variance analysis C. Expert judgment D. Decomposition
Inspection
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area? A. Project Time Management B. Project Cost Management C. Project Scope Management D. Project Human Resource Management
Project Time Management
Prioritizing risks for further analysis or action by assessing and combining their probability of
occurrence and impact takes place in which process?
A. Monitor and Control Risks
B. Plan Risk Management
C. Perform Qualitative Risk Analysis
D. Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
In which process is a project manager identified and given the authority to apply resources to project activities? A. Acquire Project Team B. Develop Project Management Plan C. Manage Project Execution D. Develop Project Charter
Develop Project Charter
Which of the following documents allows the project manager to assess risks that may require near term action? A. Probability and impact matrix B. Contingency analysis report C. Risk urgency assessment D. Rolling wave plan
Risk urgency assessment
Which of the following is an information gathering technique in Identify Risks? A. Influence diagrams B. Brainstorming C. Assumption analysis D. SWOT analysis
Brainstorming
Documented identification of a flaw in a project component together with a recommendation is termed a: A. corrective action. B. preventive action. C. non-conformance report, D. defect repair
defect repair.
Which Process Group contains those processes performed to define a new project? A. Initiating B. Planning C. Executing D. Closing
Initiating
The risk management team of a software project has decided that due to the lack of adequate
talent in the company, development of a specific part of the system is under high risk, so the team
has decided to outsource it. This is an example of which risk response?
A. Transfer
B. Share
C. Avoid
D. Accept
Transfer
Which type of agreement is legal, contractual, and between two or more entities to form a
partnership, joint venture, or some other arrangement as defined by the parties?
A. Teaming
B. Collective bargaining
C. Sharing
D. Working
Teaming
Which of the following is a tool and technique used in the Develop Schedule process? A. Three-point estimates B. Resource leveling C. Precedence diagramming method D. Bottom-up estimating
Resource leveling
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the: A. stakeholder management strategy. B. communications management plan C. stakeholder register, D. performance report.
stakeholder management strategy.
Which of the following project documents is an input to the Control Scope process? A. Vendor risk assessment diagram B. Risk register C. Requirements traceability matrix D. Area of responsibility summary
Requirements traceability matrix
In which Project Management Process Group is the project charter developed? A. Monitoring and Controlling B. Executing C. Initiating D. Planning
Initiating
Monte Carlo is which type of risk analysis technique? A. Probability B. Quantitative C. Qualitative D. Sensitivity
Quantitative
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities? A. Authority B. Role C. Competency D. Responsibility
Competency
Which of the following reduces the probability of potential consequences of project risk events? A. Preventive action B. Risk management C. Corrective action D. Defect repair
Preventive action
Which of the following is the primary output of the Identify Risks process? A. Risk management plan B. Risk register C. Change requests D. Risk response plan
Risk register
Which of the following helps to ensure that each requirement adds business value by linking it to
the business and project objectives?
A. Requirements traceability matrix
B. Work breakdown structure (WBS) dictionary
C. Requirements management plan
D. Requirements documentation
Requirements traceability matrix
Which type of risk diagram is useful for showing time ordering of events? A. Ishikawa B. Milestone C. Influence D. Decision tree
Influence
Which standard has interrelationships to other project management disciplines such as program
management and portfolio management?
A. Program Management Body of Knowledge Guide
B. The Standard for Program Management
C. Organizational Project Management Maturity Model (OPM3$)
D. Guide to the Project Management Body of Knowledge (PMBOK®)
Guide to the Project Management Body of Knowledge (PMBOK®)
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives? A. Exploit B. Share C. Enhance D. Transfer
Transfer
Which of the following correctly explains the term “progressive elaboration’?
A. Changing project specifications continuously
B. Elaborate tracking of the project progress
C. Elaborate tracking of the project specifications with a change control system
D. Project specifications becoming more explicit and detailed as the project progresses
Project specifications becoming more explicit and detailed as the project progresses
Which technique is commonly used for the Perform Quantitative Risk Analysis process? A. Brainstorming B. Strategies for opportunities C. Decision tree analysis D. Risk data quality assessment
Decision tree analysis
In which type of organizational structure are staff members grouped by specialty? A. Functional B. Projectized C. Matrix D. Balanced
Functional
Which of the following is an input to the Perform Qualitative Risk Analysis process? A. Risk register B. Risk data quality assessment C. Risk categorization D. Risk urgency
Risk register
Which of the following Process Groups covers all Project Management Knowledge Areas? A. Executing B. Monitoring and Controlling C. Planning D. Initiating
Planning
What is the most accurate rough order of magnitude (ROM)?
A. In the Initiation phase, the estimate is in the range of +/- 50%.
B. In the Planning phase, the estimate is in the range of +/- 50%.
C. In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
D. In the Closing phase, the estimate is in the range of +/- 15%.
In the Initiation phase, the estimate is in the range of +/- 50%.
Project contracts generally fall into which of the following three broad categories?
A. Fixed-price, cost reimbursable, time and materials
B. Make-or-buy, margin analysis, fixed-price
C. Time and materials, fixed-price, margin analysis
D. Make-or-buy, lump-sum, cost-plus-incentive
Fixed-price, cost reimbursable, time and materials
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process? A. Control Scope B. Collect Requirements C. Create WBS D. Define Scope
Collect Requirements
Which of the following is a strategy to deal with positive risks or opportunities? A. Mitigate B. Transfer C. Exploit D. Avoid
Exploit
Which statement is true about the project management body of knowledge?
A. Recognized by every project manager
B. Constantly evolving
C. The sum of all knowledge related to project management
D. A sum of knowledge that should be applied on every project
Constantly evolving
The initial development of a Project Scope Management plan uses which technique? A. Alternatives identification B. Scope decomposition C. Expert judgment D. Product analysis
Expert judgment
Which of the following is a project constraint?
A. Twenty-five percent staff turnover is expected.
B. The technology to be used is cutting-edge.
C. Project leadership may change due to volatile political environment.
D. The product is needed in 250 days.
The product is needed in 250 days
The process of identifying specific actions to be performed to produce project deliverables is: A. Define Activities. B. Create WBS. C. Define Scope. D. Develop Schedule
Define Activities.
What is project management?
A. A logical grouping of project management inputs, outputs, tools, and techniques
B. Applying knowledge, skills, tools, and techniques to project activities to meet the project
requirements
C. Launching a process that can result in the authorization of a new project
D. A formal, approved document that defines how the project is executed, monitored, and
controlled
Applying knowledge, skills, tools, and techniques to project activities to meet the project
requirements
An input to the Collect Requirements process is the: A. stakeholder register. B. project management plan. C. project scope statement. D. requirements management plan
stakeholder register
Projects are separated into phases or subprojects; these phases include:
A. feasibility study, concept development, design, and prototype.
B. initiate, plan, execute, and monitor.
C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report
Performance.
D. Identify Stakeholders, develop concept, build, and test.
feasibility study, concept development, design, and prototype.
In which type of contract are the performance targets established at the onset and the final
contract price determined after completion of all work based on the sellers performance?
A. Firm-Fixed-Price (FFP)
B. Fixed Price with Economic Price Adjustments (FP-EPA)
C. Fixed-Price-Incentive-Fee (FPIF)
D. Cost Plus Fixed Fee (CPFF)
Fixed-Price-Incentive-Fee (FPIF)
Which of the following is an input to the Develop Project Charter process? A. Work performance information B. Project management plan C. Business case D. Change requests
Business case
The diagram below is an example of a: A. Risk breakdown structure (RBS). B. Project team. C. SWOT Analysis. D. Work breakdown structure (WBS).
Risk breakdown structure (RBS).
Who is responsible for initiating a project? A. Project sponsor B. Project manager C. Program manager D. Project management office (PMO)
Project sponsor
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives? A. Affinity B. Scatter C. Fishbone D. Matrix
Matrix
Risk exists the moment that a project is: A. planned. B. conceived. C. chartered. D. executed.
conceived.
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
A. Cost Plus Award Fee Contract (CPAF)
B. Firm-Fixed -Price Contract (FFP)
C. Time and Material Contract (T&M)
D. Cost Plus Incentive Fee Contract (CPIF)
Time and Material Contract (T&M)
Which characteristics do effective project managers possess?
A. Project management knowledge, performance skills, and personal effectiveness
B. Preparedness, project management knowledge, and personality characteristics
C. General management, preparedness, and project management knowledge
D. Assertiveness, collaboration, and performance skills
Project management knowledge, performance skills, and personal effectiveness
Which is an output of the Collect Requirements process? A. Requirements traceability matrix B. Project scope statement C. WBS dictionary D. Work performance measurements
Requirements traceability matrix
A project lifecycle is defined as:
A. a collection of generally sequential and sometimes overlapping project phases.
B. a process required to ensure that the project includes all the work required, and only the work
required, to complete the project successfully.
C. a recognized standard for the project management profession.
D. the application of knowledge, skills, tools, and techniques to project activities to meet the
project requirements.
a collection of generally sequential and sometimes overlapping project phases.
Which of the following are an enterprise environmental factor that can influence the Identify Risks process? A. Work performance reports B. Assumptions logs C. Network diagrams D. Academic studies
Academic studies
Which Control Scope input is compared to actual results to determine if corrective action is required for the project? A. Scope baseline B. Scope management plan C. Change management plan D. Cost baseline
Scope baseline
The risk shared between the buyer and seller is determined by the: A. assumption log. B. quality checklist. C. risk register. D. contract type.
contract type.
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they: A. operate separately. B. move together in batches, C. overlap and interact. D. move in a sequence.
overlap and interact
A tool and technique used during the Define Scope process is: A. facilitated workshops. B. observations. C. questionnaires and surveys. D. group creativity techniques.
facilitated workshops.
Which of the following response strategies are appropriate for negative risks or threats? A. Share, Accept, Transfer, or Mitigate B. Exploit, Enhance, Share, or Accept C. Mitigate, Share, Avoid, or Accept D. Avoid, Mitigate, Transfer, or Accept
Avoid, Mitigate, Transfer, or Accept
Identify Stakeholders is the process of identifying all of the people or organizations impacted by
the project and documenting relevant information regarding their interests in, involvement in, and
impact on the project:
A. manager.
B. success.
C. deadline.
D. scope.
success.
Which of the following is a tool or technique used in the Acquire Project Team process? A. Networking B. Training C. Negotiation D. Issue log
Negotiation
Risk responses reflect an organization's perceived balance between: A. risk taking and risk avoidance. B. known risk and unknown risk. C. identified risk and analyzed risk. D. varying degrees of risk
risk taking and risk avoidance
The application of knowledge, skills, tools, and techniques to project activities to meet project
requirements describes management of which of the following?
A. Project
B. Scope
C. Contract
D. Program
Project
Prototype development may be used as a tool for which of the following risk response strategies? A. Avoid B. Accept C. Mitigate D. Exploit
Mitigate
A tool and technique used during the Collect Requirements process is: A. prototypes. B. expert judgment. C. alternatives identification. D. product analysis.
prototypes.
One of the objectives of a quality audit is to:
A. highlight the need for root cause analysis.
B. share the process documentation among stakeholders.
C. offer assistance with non-value-added activities.
D. identify all of the gaps or shortcomings.
identify all of the gaps or shortcomings
Which statement correctly describes the value of a business case?
A. It provides the necessary information to determine if a project is worth the required investment.
B. It provides for alternative dispute resolution procedures in event of contract default.
C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
D. It is used to help a project manager understand the scope of commercial advantages
It provides the necessary information to determine if a project is worth the required investment.
Which of the following includes how requirements activities will be planned, tracked, and reported? A. Configuration management plan B. Scope baseline C. Requirements management plan D. Schedule baseline
Requirements management plan
Which type of dependency is contractually required or inherent in the nature of the work? A. External B. Lead C. Discretionary D. Mandatory
Mandatory
The probability and impact matrix is primarily used to:
A. Quantify risk issues for trends during a quality audit.
B. Develop a risk register for risk planning.
C. Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.
D. Define risk and compare impacts during Perform Quantitative Risk Analysis.
Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis
Scope verification is PRIMARILY concerned with which of the following?
A. Acceptance of the work deliverables.
B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure
Acceptance of the work deliverables
Who is responsible for determining which processes from the Process Groups will be employed
and who will be performing them?
A. Project sponsor and project manager
B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager
Project manager and project team
Which activity is an input to the select sellers process? A. Organizational process assets B. Resource availability C. Change control process D. Team performance assessment
Organizational process assets
Which of the following methods is a project selection technique? A. Flowcharting B. Earned value C. Cost-benefit analysis D. Pareto analysis
Cost-benefit analysis
Soft logic is also known as what type of dependency? A. External B. Discretionary C. Mandatory D. Internal
Discretionary
Who MUST know when a risk event occurs so that a response can be implemented? A. Customers B. Project sponsors C. Project management team D. Insurance claims department
Project management team
What are the components of the “triple constraint”? A. Scope, time, requirements B. Resources, time, cost C. Scope, management, cost D. Scope, time, cost
Scope, time, cost
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks? A. Risk identification B. Qualitative risk analysis C. Risk management planning D. Quantitative risk analysis
Qualitative risk analysis
An input required to develop a preliminary project scope statement is: A. Organizational Structure B. Organizational Process Assets C. Organizational Matrix D. Organizational Breakdown Structures
Organizational Process Assets
Which of the following is an example of a risk symptom?
A. Failure to meet intermediate milestones
B. Force of nature, such as a flood
C. Risk threshold target
D. Crashing, front loading, or fast tracking
Failure to meet intermediate milestones
Which is a tool or technique used in scope definition? A. Templates, forms, and standards B. Change requests C. Stakeholder analysis D. Project assumptions
Stakeholder analysis
Which of the following processes includes prioritizing risks for subsequent further analysis or
action by assessing and combining their probability of occurrence and impact?
A. Qualitative risk analysis
B. Quantitative risk analysis
C. Risk management planning
D. Risk response planning
Qualitative risk analysis
Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process? A. Schedule Control B. Activity Definition C. Schedule Development D. Activity Resource Estimating
Activity Resource Estimating
A Project Management Office (PMO) manages a number of aspects, including what?
A. Project scope, schedule, cost, and quality of the products of the work packages
B. Central coordinator of communication management across projects, and for the delivery of
specific project objectives, organization opportunity assessment
C. Assigns project resources to best meet project objectives
D. Overall risk, overall opportunity and interdependencies among projects
Overall risk, overall opportunity and interdependencies among projects
Where are product requirements and characteristics documented? A. Product scope description B. Project charter C. Preliminary project scope statement D. Communications management plan
Product scope description