1-200 Flashcards
An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget, D. High-level risks
Acceptance criteria.
Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case
Business case
Which input to the Plan Risk Management process provides information on high-level risks? A. Project charter B. Enterprise environmental factors C. Stakeholder register D. Organizational process assets
Project charter
Which item is an example of personnel assessment? A. Resource calendar B. Tight matrix C. Team-building activity D. Focus group
Focus group
Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
Stakeholder management plan
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? A. Procurement documents B. Communications plan C. Project charter D. Stakeholder register
Project charter
The Identify Stakeholders process is found in which Process Group? A. Initiating B. Monitoring and Controlling C. Planning D. Executing
Initiating
An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast.
Business case.
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? A. Project Risk Management B. Project Human Resource Management C. Project Scope Management D. Project Stakeholder Management
Project Stakeholder Management
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter
Stakeholder register
In which Knowledge Area is the project charter developed? A. Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration Management
Project Integration Management
The ability to influence cost is greatest during which stages of the project? A. Early B. Middle C. Late D. Completion
Early
Which process involves developing an approximation of the monetary resources needed to complete project activities? A. Estimate Costs B. Control Costs C. Determine Budget D. Plan Cost Management
Estimate Costs
Which tool or technique is used in the Develop Project Management Plan process? A. Pareto diagram B. Performance reporting C. SWOT analysis D. Expert judgment
Expert judgment
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk: A. Responses B. Appetite C. Tolerance D. Attitude
Responses
An output of the Manage Stakeholder Engagement process is: A. change requests B. enterprise environmental factors C. the stakeholder management plan D. the change log
change requests
Which process numerically analyzes the effect of identified risks on overall project objectives? A. Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Which Collect Requirements output links the product requirements to the deliverables that satisfy them? A. Requirements documentation B. Requirements traceability matrix C. Project management plan updates D. Project documents updates
Requirements traceability matrix
A temporary endeavor that creates a unique product or service is called a: A. Project B. Plan C. Program D. Portfolio
Project
The process of prioritizing risks for further analysis or action is known as: A. Plan Risk Management. B. Plan Risk Responses. C. Perform Qualitative Risk Analysis. D. Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
Stakeholder satisfaction should be managed as a key project: A. Benefit B. Initiative C. Objective D. Process
Objective
Which cost is associated with nonconformance? A. Liabilities B. Inspections C. Training D. Equipment
Liabilities
Identify Risks is part of which Process Group? A. Planning B. Executing C. Closing D. Initiating
Planning
The business needs, assumptions, and constraints and the understanding of the customers needs
and high-level requirements are documented in the:
A. Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register.
Project charter
Which Process Group and Knowledge Area include the Sequence Activities process?
A. Executing Process Group and Project Time Management
B. Executing Process Group and Project Cost Management
C. Planning Process Group and Project Time Management
D. Planning Process Group and Project Cost Management
Planning Process Group and Project Time Management
In the Plan Stakeholder Management process, expert judgment is used to:
A. Provide information needed to plan appropriate ways to engage project stakeholders.
B. Ensure comprehensive identification and listing of new stakeholders.
C. Analyze the information needed to develop the project scope statement.
D. Decide the level of engagement of the stakeholders at each required stage
Decide the level of engagement of the stakeholders at each required stage
Power, urgency, and legitimacy are attributes of which stakeholder classification model? A. Salience B. Influence/impact C. Power/interest D. Power/influence
Salience
Through whom do project managers accomplish work? A. Consultants and stakeholders B. Stakeholders and functional managers C. Project team members and consultants D. Project team members and stakeholders
Project team members and stakeholders
A stakeholder expresses a need not known to the project manager. The project manager most
likely missed a step in which stakeholder management process?
A. Plan Stakeholder Management
B. Identify Stakeholders
C. Manage Stakeholder Engagement
D. Control Stakeholder Engagement
Plan Stakeholder Management
Skills necessary for project management such as motivating to provide encouragement; listening
actively; persuading a team to perform an action; and summarizing, recapping, and identifying
next steps are known as:
A. organizational skills
B. technical skills
C. communication skills
D. hard skills
communication skills
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an: A. improvement B. program C. result D. portfolio
improvement
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk: A. management B. response C. tolerance D. appetite
appetite
The zero duration of milestones in project planning occurs because milestones:
A. Are unpredictable and challenge the Plan Schedule Management process.
B. Occur at random times in the project plans.
C. Represent a moment in time such as a significant project point or event.
D. Represent both significant and insignificant points in the project and are difficult to anticipate.
Represent a moment in time such as a significant project point or event.
The component of the human resource management plan that includes ways in which team
members can obtain certifications that support their ability to benefit the project is known as:
A. recognition and rewards
B. compliance
C. staff acquisition
D. training needs
training needs
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be: A. Continuous B. Discrete C. Regulated D. Arbitrary
Continuous
In project management, a temporary project can be: A. Completed without planning B. A routine business process C. Long in duration D. Ongoing to produce goods
Long in duration
Which document in the project management plan can be updated in the Plan Procurement Management process? A. Budget estimates B. Risk matrix C. Requirements documentation D. Procurement documents
Requirements documentation
Which type of probability distribution is used to represent uncertain events such as the outcome of
a test or a possible scenario in a decision tree?
A. Uniform
B. Continuous
C. Discrete
D. Linear
Discrete
Which stakeholder approves a project's result? A. Customer B. Sponsor C. Seller D. Functional manager
Customer
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives? A. Collect Requirements B. Plan Scope Management C. Define Scope D. Define Activities
Collect Requirements
Plan Communications Management develops an approach and plan for project communications
based on stakeholders’ needs and requirements and:
A. Available organizational assets
B. Project staff assignments
C. Interpersonal skills
D. Enterprise environmental factors
Available organizational assets
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)? A. 0.03 B. 0.06 C. 0.10 D. 0.50
0.06
A complete set of concepts, terms, and activities that make up an area of specialization is known as: A. a Knowledge Area B. a Process Group C. program management D. portfolio management
a Knowledge Area
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as: A. exploit B. avoid C. mitigate D. share
mitigate
Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager? A. Control Quality B. Monitor and Control Project Work C. Control Scope D. Perform Integrated Change Control
Perform Integrated Change Control
Project management processes ensure the:
A. alignment with organizational strategy
B. efficient means to achieve the project objectives
C. performance of the project team
D. effective flow of the project throughout its life cycle
effective flow of the project throughout its life cycle
Which project risk listed in the table below is most likely to occur? A. 1 B. 2 C. 3 D. 4
2
Which is an enterprise environmental factor?
A. Marketplace conditions
B. Policies and procedures
C. Project files from previous projects
D. Lessons learned from previous projects
Marketplace conditions
Project Stakeholder Management focuses on: A. project staff assignments B. project tea m acquisition C. managing conflicting interests D. communication methods
managing conflicting interests
A risk that arises as a direct result of implementing a risk response is called a: A. contingent risk B. residual risk C. potential risk D. secondary risk
secondary risk
The purpose of developing a project scope management plan is to:
A. Manage the timely completion of the project.
B. Ensure that the project includes all of the work required.
C. Make sure the project will satisfy the needs for which it was begun.
D. Reduce the risk of negative events in the project.
Ensure that the project includes all of the work required.
A tool and technique used in the Develop Project Charter process is: A. change control tools B. expert judgment C. meetings D. analytical techniques
expert judgment
A projects purpose or justification, measurable project objectives and related success criteria, a
summary milestone schedule, and a summary budget are all components of which document?
A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan
Project charter
Project managers who lead by example and follow through on the commitments they make
demonstrate the key interpersonal skill of:
A. influencing
B. leadership
C. motivation
D. coaching
influencing
The process of defining how the project scope will be validated and controlled is known as: A. Define Scope. B. Develop Project Management Plan. C. Plan Scope Management. D. Plan Quality Management
Plan Scope Management.
Technical capability, past performance, and intellectual property rights are examples of: A. performance measurement criteria B. source selection criteria C. product acceptance criteria D. phase exit criteria
source selection criteria
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as: A. Earned value management. B. Forecasting. C. Critical chain methodology. D. Critical path methodology.
Earned value management.
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses? A. Identify Risks B. Plan Risk Management C. Perform Qualitative Risk Analysis D. Perform Quantitative Risk Analysis
Perform Qualitative Risk Analysis
Which element does a project charter contain? A. Management reserves B. Work breakdown structure C. Stakeholder list D. Stakeholder register
Stakeholder list
Every project creates a unique product, service, or result that may be: A. tangible B. targeted C. organized D. variable
tangible
The degree, amount, or volume of risk that an organization or individual will withstand is called risk: A. appetite B. tolerance C. threshold D. management
tolerance
An issue log is an input to which Project Human Resource Management process? A. Manage Project Team B. Acquire Project Team C. Plan Human Resource Management D. Develop Project Team
Manage Project Team
The component of the risk management plan that documents how risk activities will be recorded is called: A. tracking B. scoping C. timing D. defining
tracking
Which Control Stakeholder Engagement tool or technique allows the project manager to
consolidate and facilitate distribution of reports?
A. Information management systems
B. Work performance reports
C. Stakeholder analysis
D. Data gathering and representation
Information management systems
Which basic quality tool explains a change in the dependent variable in relationship to a change
observed in the corresponding independent variable?
A. Cause-and-effect diagram
B. Histogram
C. Control chart
D. Scatter diagram
Scatter diagram
High-level project risks are included in which document? A. Business case B. Risk breakdown structure C. Project charter D. Risk register
Project charter
The scope management plan and scope baseline are contained in: A. organizational process assets B. a requirements traceability matrix C. the project charter D. the project management plan
the project management plan
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a: A. portfolio B. program C. selection D. sub portfolio
program
The stakeholder register is an output of: A. Identify Stakeholders. B. Plan Stakeholder Management. C. Control Stakeholder Engagement. D. Manage Stakeholder Engagement
Identify Stakeholders.
An output of the Develop Project Team process is: A. change requests B. team performance assessments C. project staff assignments D. project documents updates
team performance assessments
The formal and informal interaction with others in an organization industry, or professional environment is known as: A. negotiation B. organizational theory C. meeting D. networking
networking
Which process is included in the Project Integration Management Knowledge Area? A. Manage Project Team B. Collect Requirements C. Sequence Activities D. Direct and Manage Project Work
Direct and Manage Project Work
The project manager notes that stakeholders are aware of the project and potential impacts and
are actively engaged in ensuring that the project is a success. The engagement level of the
stakeholders should be classified as:
A. Supportive
B. Leading
C. Neutral
D. Resistant
Leading
Which of the following is a narrative description of products, services, or results to be delivered by a project? A. Project statement of work B. Business case C. Accepted deliverable D. Work performance information
Project statement of work
A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:
A. Historical information and the lessons-learned database.
B. Historical information and the stakeholder register.
C. Organizational process assets and the lessons-learned database.
D. Project documents and historical information
Historical information and the lessons-learned database.
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)? A. 0.45 B. 0.56 C. 0.70 D. 1.36
0.70
The scope of a project cannot be defined without some basic understanding of how to create the specified: A. objectives B. schedule C. product D. approach
product
The creation of an internet site to engage stakeholders on a project is an example of which type of communication? A. Push B. Pull C. Interactive D. Iterative
Pull
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project? A. Build vs. buy B. Expert judgment C. Alternatives identification D. Product analysis
Alternatives identification