Q
  1. Overall responsibility for complying with API 570?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Responsible for developing and implementing a Quality Assurance inspection/repair management system?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. Perform audit of owner/users to assure compliance with 570?
A

Competent Team

The competent audit team is typically from:
- Another owner/user plant site
-Company Central office
- Third party organization experienced and competent in refining and/or petrochemical process plant inspection programs or a combination of third party and other owner/user sites.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Responsible for implementing an effective MOC process?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Responsible to develop program for Integrity Operating Windows?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Responsible for Quality Control during repairs or alterations?
A

Repair Organization

-The repair organization shall be responsible to the owner/user and shall provide the materials, equipment, quality control, and workmanship necessary to maintain and repair the piping systems in accordance with the requirements of API570

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Assure owner - Quality Assurance, testing, inspection & examinations meet Code?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. Extend scope of inspection when justified by findings?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Timely notify owner of Non-conformances?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. Evaluate and accept NDE examination results?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. Set requirements for NDE Techs competency and certification?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. Maintain certification records of NDE examiners?
A

Tech Employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. Has access to NDE certification records?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. Develop an inspection plan for a piping system?
A

Inspector AND/OR Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. Also involved in making inspection plans for pipe that operates >750F?
A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. Choose to conduct RBI assessments?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. Review RBI assessments?
A

Inspector AND Qualified other

*The RBI assessment shall be reviewed and approved by the appropriate qualified personnel per API 580 and inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. Get familiar with prior piping history before an inspection?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. Understand operating conditions & damage mechanisms affecting pipe?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. Approve revisions to the Inspection Plan?
A

Inspector AND/OR Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

21.Perform On-Stream inspections?

A

Inspector or Examiner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  1. Approve On-Stream Inspection work performed by Examiners?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
  1. Take thickness measurements?
A

Inspector or Examiner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
  1. Ensure individuals taking thickness measurements are trained and qualified?
A

Owner/User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q
  1. Determine cause if short-term corrosion rate varies significantly (from the previous identified rate)?
A

Inspector AND Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q
  1. Perform External Inspection?
A

Inspector OR qualified other

*Qualified examiners, operating or maintenance personnel may also conduct external inspections, when acceptable to the inspector. In such cases, the persons conducting external piping inspections in accordance with API 570 shall be qualified through an appropriate amount of training.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q
  1. Involved if the # of CML’s will be significantly reduced or eliminated?
A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q
  1. Select or adjust the # of CMLs?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
  1. Select CMLs for pipe systems subject to localized corrosion or cracking?
A

Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q
  1. Should be aware of causes of thickness measurements errors?
A

Inspector

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q
  1. To understand damage mechanism, select type & extent of NDE, Inspector consults with…?
A

Engineer OR Corrosion Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q
  1. Determine surface preparation for NDE exam. Inspector may need to consult with:
A

NDE Specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q
  1. Perform UT flaw detection for finding ID surface braking flaws?
A

QUTE ( i.e. industry qualified UT Angle Beam Examiner)

** API QUTE: API Qualification of Ultrasonic Testing Examiners certification program (Thickness Measurement)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q
  1. Determine pressure for leak test (non-code tests)?
A

Owner/User
* Service tests and/or lower pressure tests, which are used only for tightness of piping systems, may be conducted at pressures designated by the owner/user

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q
  1. Consulted when a component pressure test is conducted?
A

Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q
  1. Prior to hydrotest determine if structure will support weight?
A

Engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q
  1. Determine risk of brittle fracture prior to performing a pressure test?
A

Engineer

38
Q
  1. Approve substituting NDE for a pressure test after an alteration?
A

Inspector AND engineer

39
Q
  1. Perform UT as a substitute for a pressure test?
A

QUTE ( i.e. industry qualified UT Angle Beam Examiner)

** API QUTE: API Qualification of Ultrasonic Testing Examiners certification program (Thickness Measurement)

40
Q
  1. Determine if PMI program is needed for existing alloy facilities?
A

Owner/User

41
Q
  1. Determine schedule for replacing incorrect components found during PMI exam?
A

Inspector AND corrosion specialist AND Owner/User

42
Q
  1. Periodically inspect components found during PMI survey that are wrong materials?
A

Inspector

43
Q
  1. Verify that new alloy material during repairs and alteration meet specifications?
A

Inspector

44
Q
  1. When verifying new materials, determine the sampling percentage to PMI?
A

Owner/User

45
Q
  1. PMI new materials during repairs & alterations?
A

Inspector OR examiner

46
Q
  1. Incorrect material found in existing pipe, determine amount of further verification?
A

Inspector

47
Q
  1. Determine if crack-like weld flaws are the result of original weld fabrication?
A

Inspector

48
Q
  1. Assess crack-like flaws and environmental cracking?
A

Engineer AND/OR Corrosion Specialist

49
Q
  1. Assess preferential weld corrosion
A

Inspector

50
Q
  1. Determine inspection intervals for Thickness Measurements & Externals
A

Inspector OR Owner/User (Code Conflict)

51
Q
  1. Determine inspection intervals for Thickness Measurements & Externals
A

Inspector OR engineer (Code Conflict)

52
Q
  1. Establish the rules for maximum inspection intervals for Class 4 piping?
A

Owner/User

53
Q
  1. Maintain a record of the piping classification for each process fluid?
A

Owner/User

54
Q
  1. Determine # of CML’s to examine during Thickness Inspection, Inspector consults with…?
A

Engineer AND/OR Corrosion Specialist

55
Q
  1. Determine the amount of inspection to perform on secondary Class 3&4 Small Bore Piping (SBP)
A

Owner/User

56
Q
  1. Consult about placement of CMLs on deadlegs?
A

Corrosion Specialist

57
Q
  1. PRD’s tested and repaired?
A

Repair Organization experienced in PRD maintenance

58
Q
  1. Determine the inspection interval for Pressure Relief Devices?
A

Inspector OR engineer OR qualified other

59
Q
  1. Determines how Corrosion Rates are established: Point-to-Point or Statistics?
A

Owner/User

60
Q
  1. Select corrosion rate (ST or LT) that best reflects conditions
A

Inspector AND Corrosion Specialist

61
Q
  1. Maintain piping records?
A

Owner/User

62
Q
  1. Review and approval an interval deferral?
A

Inspector AND Owner/User

63
Q
  1. Perform deferral that does NOT extend interval more than 6 months, etc.?
A

Inspector

64
Q
  1. Revise an existing interval that has unusual degradation issues. Inspector and:
A

Engineer OR Corrosion Specialist

65
Q
  1. Perform piping repairs and alterations?
A

Repair Organization

66
Q
  1. Authorize all repairs?
A

Inspector

67
Q
  1. Authorize all alterations?
A

Inspector AND engineer

68
Q
  1. Designate hold points for repairs and alterations?
A

Inspector

69
Q
  1. Provide general authorization for limited or routine repairs?
A

Inspector

70
Q
  1. At Repairs & Alterations, approve all methods of design, materials, WPSs, NDE & testing?
A

Inspector OR Engineer

71
Q
  1. Approve use of on-stream welding?
A

Owner/User

72
Q
  1. Approve repair welding of cracks?
A

Engineer

73
Q
  1. Approve all repair and alteration work at hold points?
A

Inspector

74
Q
  1. Approve all repair and alteration work at completion of work?
A

Inspector

75
Q
  1. Design temporary repairs?
A

Engineer

76
Q
  1. Determine longitudinal cracks won’t grow beyond a Fillet-Welded patch?
A

Engineer

77
Q
  1. Approve using lap patches with a material different than the pipe?
A

Engineer

78
Q
  1. Determine that wall thickness is adequate prior to on-stream welding?
A

Inspector

79
Q
  1. Assure on-stream temporary welded repairs can be safely done on higher risk systems?
A

Engineer

80
Q
  1. Allow temporary welded repairs to remain in place past “next opportunity”?
A

Engineer

81
Q
  1. Determine which non-welded repair methods are acceptable?
A

Inspector AND/OR Engineer

82
Q
  1. Allow temporary leak sealing devices to remain in place past “next opportunity”?
A

Engineer

83
Q
  1. Review leak sealing procedures?
A

Inspector OR Engineer

84
Q
  1. Maintain record of qualified WPS’s and WPQ’s?
A

Repair Organization

85
Q
  1. Allow exceptions to required preheat temperature for temporary repairs?
A

Engineer

86
Q
  1. Exceptions to PWHT on temporary repairs?
A

Engineer

87
Q
  1. Review the use of local PWHT in lieu of a full encirclement PWHT?
A

Engineer

88
Q
  1. Review the use of Preheat or Controlled-Deposition Welding (CDW) in lieu of PWHT?
A

Engineer

89
Q
  1. Determine whether a pressure test is needed after repairs?
A

Inspector

90
Q
  1. Approve substituting NDE in lieu of a pressure test?
A

Inspector AND engineer

91
Q
  1. Perform rerating calculations?
A

Inspector OR Engineer

92
Q

Keep any piping CP records?

A

Owner/User