Week 4 Flashcards

1
Q

• Unit is in Mode 3.
• ‘B” Diesel Generator has been tagged out for an on-line maintenance.
• The air start system is also tagged out and has been depressurized (both receivers have
been depressurized to < 150 psig).
What LCO condition(s) is the Unit in?

A. LCO 3.8.1 condition B only
B. LCO 3.8.3 condition F only
C. LCO 3.8.1 condition B and 3.8.3 condition E
D. LCO 3.8.1 condition B and 3.8.3 condition F

A

D. LCO 3.8.1 condition B and 3.8.3 condition F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which of the following is NOT a required contingency action if a Diesel Generator will be
inoperable greater than 72 hours?

A. The GTGs must be started and parallelled to the affected Diesel Generator emergency bus.
B. No discretionary maintenance activities will be scheduled on the gas turbine generators (GTGs).
C. The GTGs will not be used for non-safety functions (i.e., power peaking to the grid).
D. The functionality of the GTGs will be verified by ensuring that the monthly start test has been successfully completed within the previous four weeks before entering the extended DG Completion Time.

A

A. The GTGs must be started and parallelled to the affected Diesel Generator emergency bus.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

• The plant is at 100% power.
• The Crew is presently in 3.8.1 condition A due to a loss of an off-site circuit.
• All actions in 3.8.1 condition A. have been completed.
• 4 Hours later the AO reports the associated circuit Emergency Diesel Generator (EDG) lube
oil indicates 0.5 inches in the site-glass.
Based on these conditions, the crew should declare the EDG inoperable…

A. 48 hours after time of discovery.
B. and enter the required actions 3.8.2.
C. and enter the required actions of 3.8.1 condition b and d.
D. and enter the required actions of 3.8.1 condition d and 3.8.2 actions a and b.

A

C. and enter the required actions of 3.8.1 condition b and d.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

• Unit is operating at rated power.
• One Diesel Generator becomes inoperable.
Which one of the following Tech Spec actions must be completed within one hour?

A. Restore DG to operable status.
B. Determine that the opposite train DG is not inoperable due to a common mode failure.
C. Verify correct breaker alignment and indicated power availability for two offsite power sources.
D. Declare required feature(s) supported by DG inoperable when its redundant required feature(s) is inoperable.

A

C. Verify correct breaker alignment and indicated power availability for two offsite power sources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • Unit one is at 100% power
  • DG A Train B starting air receiver fails to 0 psig

What action is required?

A

No action required. Bases says only 1 starting air receiver is required for operability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Technical Specification 3.9.4 (SDC and Coolant Circulation) requires ONE train of Shutdown Cooling to be OPERABLE and in operation. However, this LCO is modified with a note that permits the Operating Crew to deviate from this requirement. Correctly complete the below sentence with the information contained in the note.
Provided no operations are permitted that would cause reduction of the Reactor Coolant System boron concentration, the required SDC loop may be removed from operation…

A. for ≤ 1 hour per 8 hour period.
B. for ≤ 1 hour per 24 hour period.
C. for ≤ 8 hours per 24 hour period.
D. until RCS temperature reaches 180°F.

A

A. for ≤ 1 hour per 8 hour period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Unit 1 is operating at rated power with the following SIT parameters:
PARAMETER:
1A 605 psig 35% 4000 ppm
1B 605 psig 30% 3850 ppm
2A 610 psig 20% 3900 ppm
2B 615 psig 30% 4100 ppm
Per Section 3.5 of the Technical Specifications, which of the following describes the required actions (if any) necessary for these conditions.

A. Immediately enter 3.0.3.
B. Continue unrestricted operations.
C. Declare SIT 2A inoperable (ALL others are operable) and restore it to within limits in 24 hours.
D. Declare SIT 2A inoperable (ALL others are operable) and restore it to within limits in 72 hours.

A

C. Declare SIT 2A inoperable (ALL others are operable) and restore it to within limits in 24 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

• Unit 1 is coming out of a refueling outage.
• RCS bulk temperature is 250 degrees.
• Primary pressure is 650 psia.
• Work control has reported that both HPSI pumps had a complete oil change out with the wrong oil.
What action, if any, is required by Tech Specs?

A. Immediately enter 3.0.3.
B. No action required below 1837 psia.
C. Restore one HPSI pump to operable within 1 hour.
D. Immediately suspend all operations involving reduction of RCS boron concentration and initiate action to restore one train to operable status.

A

C. Restore one HPSI pump to operable within 1 hour.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Unit 1 is operating at rated power with the following SIT parameters:
PARAMETER:
1A 588 psig 35% 4000 ppm
1B 605 psig 30% 3850 ppm
2A 610 psig 20% 3900 ppm
2B 615 psig 30% 4100 ppm
Per Section 3.5 of the Technical Specifications, which of the following describes the required
actions (if any) necessary for these conditions.
A. Restore all but one SIT to Operable status in 1 hour.
B. Enter 3.0.3 immediately.
C. Be in Mode 3 in 6 hours.
D. Restore the inoperable SIT(s) to operable status in 24 hours.

A

A. Restore all but one SIT to OPERABLE status in 1 hour.

NOTE: Old specs answer B. Enter 3.0.3 immediately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

• Unit 1 is at rated power.
• On 9/1/04 at 0600, DG “A” has been declared inoperable to repair leaking fuel racks.
• On 9/5/04 at 1200, the mechanics who are working the job discover a Jacket Water leak on
this DG.
Based on these conditions, DG “A” MUST be restored to an operable condition on….

A. 9/11/04 at 0600
B. 9/11/04 at 1200
C. 9/14/04 at 0600
D. 9/14/04 at 1200

A

A. 9/11/04 at 0600

How well did you know this?