Week 3 - Audit Risk Calculation Flashcards
1
Q
If inherent and control risk are high, what do we need to do to detection risk?
A
Try and make it lower
2
Q
How do you decrease detection risk?
A
Increase the amount of sampling you do - more audit work needed
3
Q
If inherent risk and control risk are low, what can we do to detection risk?
A
We can afford to have it a little bit higher - less audit work needed because overall audit risk will be manageable