Week 2 - Tutorial Questions Network Anlaysis Flashcards
How do you calculate the Probability of a project taking less than ‘X’ weeks/days?
1) Calculate the mean of the project (using network diagram).
2) Calculate the variance of each activity in the critical path. ((Tp-To)/S)2)
3) Sum the variance of the critical path and square root the answer to find the standard deviation.
4) Find the Z-score to look up (Z=(x-m)/s)
5) Look up Z-score on table and convert into a percentage probability.
How do you calculate the probability that a project finished between ‘X” and ‘X1’?
1) Calculate the standard deviation of the project (By calculating the variance of each activity in the critical path and square rooting the answer).
2) (X-M)/S for both of the range values.
3) Find the closest number to the values found in step 2 on the z-table and take note of what they correspond to.
4) We now know the probability of the project being outside of X and X1.
4) Calculate 1 Less the probability of the project being outside of the range. (This leaves the Probability that the project will be within this range)
There is a 90% chance the project will take X weeks to complete, what is the value of X in weeks.
How is this sort of question calculated?
1) Find the missing value from part 1 of the question, in this case it is 10% 0r 0.10.
2) Look up 0.10 on the Z-table and find the closest value and its corresponding Z-score.
3) Use the formula: Mean + Z-score x Standard deviation
What does the dotted line on a gantt chart represent?
The total float of the activity
What does the solid line on a gantt chart represent?
Represent the length of the activity
If we want to reduce the chance of the project taking longer than 20 weeks to 1%, How much do we need to reduce average time?
1) What value is missing? 1% or 0.01
2) What is the closest value to this in the z-table? (0.00990)
3) What does 0.00990 correspond to in Z-table? (2.33)
4) Mean + Z-score x Standard deviation = 16.16 days
What is one limitation of PERT analysis?
The variation of activities outside of the critical path are ignored.
Some may have high variance and therefore a chance of impacting upon the project.