Week 1 Lecture 1- Network Analysis/Project Scheduling Flashcards

1
Q

What are the three aims of ‘Project Scheduling’?

A

1) Shortest duration
2) Minimum cost
3) Maximum quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does ‘CPA’ stand for? And what does it mean?

A

Critical path analysis

The path projects take where the Total float is equal to 0 (ZERO).
These are the activities that, if delayed, will result in the project finish date being delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What three things can be done or considered before a project started to help analyse it?

A

Feasibility study
Scenario experimentation
Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a ‘Feasibility analysis’?

A

Lets us know how long a project should take and helps to stop unrealistic deadlines being set

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is ‘Scenario experimentation’?

A

If projects have activities that could vary in time, scenario experimentation allows for comparisons between the best and worst case scenario

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the ‘approach’ for project scheduling? What are the 6 steps?

A

1) identify activities
2) identify relationship between activities
3) Draw network diagram
4) Calculate timings and project duration
5) Identify critical path and floats
6) Adjust schedule according to objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is meant by the term ‘Work Breakdown Structure’?

A

A hierarchy of activities that need to be completed in order for the project to be finished.

Each activity is given a different level of importance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What two things must be included in a network representation?

A

Dummy start event

Dummy finish event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is meant by the term ‘Total Float’ of an activity? And what is the equation for calculating ‘Total Float’?

A

The amount of flexibility an activity can be delayed or extended without affecting the project duration.

Total Float = LFT (of predecessor) - EFT (of successor)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the ‘Critical Path’?

A

The path of activities with a total float of 0.

Delaying one critical activity will delay the whole project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly