Week 2 Flashcards

1
Q

What do we mean about cost behaviour?

A

is an indicator of how a cost will change in total when there is a change in some activity, so cost behaviour can be fixed, variable semi variable etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What do we mean by Cost traceability?

A

Whether the cost can be traced to some level of production or output, so we can have direct and indirect costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Remind me again what is product costs in manufacturing?

A

Direct materials + Direct labour + Manufacturing overheads.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is process costing?

A

When a firm usually have homogenous products, with large numbers, for example oil.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is batch costing?

A

When costs are related to a group of units of products or services rather than to each individual unit of product or service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is job order costing

A

When you assign accumulating manufacturing costs of an individual unit of output. This is used when the various items produced are sufficiently different from each other and each has a significant cost. e.g. aircraft

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When i want to order a slide for example, what do I have to generate from job order costing?

A

You have to generate a job order cost sheet, this is the cost for the job, using having direct materials, direct labour and Manufacturing overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The question is how do we apportion ( distribute) overhead costs, to each unit we produce?

A

The answer is that you will have to use some bases to apportion the costs, which we have to find a predetermined rate to apportion these costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Give example of some bases commonly used?

A

Direct labour hours Direct materials used Floor area occupied

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Lets say you had a heating overhead, what bases would you use to apportion cost?

A

Machine hours for example

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Here is an example of a cost card, the question is how do we decide how much overhead to charge or absorb in each product, as overhead costs can not be traced to a product direcly?

A

We use absorption costing in job order costing ( or full costing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Absorption costing?

A

Absorption costing is a method for accumulating the costs associated with a production process and apportioning them to individual products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Under absorption costing how do we work out total product costs?

A

Direct Materials

+ Direct Labor

+ Variable Overhead

+ Fixed Overhead

= Total Product Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is the product cost in absorption costing different to marginal costing?

A

Product cost = Direct materials, direct labour, variable manfuacturing overhead ( changes with output) but not FOH, under variable costing we treat FOH as period costs( expenses in I/S)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does COGS mean in absorption costing?

A

DM+ DL + VOH + FOH

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Is absroption costing an estimate or not?

A

Its an estimate of how much overhead should be absorbed in each product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

In absroption costing where are the overheads charged to?

A

The overheads are normally charged to the cost centres ( normally departments that use them e.g. lets say you have £1 mil worth of bills, then this is distrubted amongst each of the business departments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When departments receive overheads, what do they do?

A

They charge the overhead to the cost units (products) they work on

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Is it fair that departments like canteen absorb overhead costs?

A

No service departments shouldn’t absorb cost, as they serve main production departments, so we have to reapportion the cost( distrubute cost again)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are 2 ways to reapportion cost from service departments into main production departments?

A

Step down method and Direct method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the step down method?

A

allocates the cost of a service department to other service departments as well as to operating departments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the direct method?

A

You are not reapportioning within the fellow support departments, they simply shove costs into all the production departments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When do we use step down method and when do we use direct method?

A

If the support departments are serving each other as well, than it makes sense to reapportion each other first

If not serving each other mutually direct method makes sense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the different between apportioning and reapportioning?

A

Apportioning - Overheads will be charged to all cost centres/ departments.

Re-apportioning – Service department costs are charged to production departments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the formula for the OAR?

A

OAR = Budgeted Production overhead / Budgeted Activity level

26
Q

If the apportioning bases are floor space(rent), no of orders(ordering costs), value of machinery(machine depreciation) and chef wages and there is department A B and canteen, show a visual diagram of apportionment.

A
27
Q

Show with a visual diagram of reapportionment with canteen, production department 1 and 2.

A

As canteen doesnt work on production it must recharge overheads to the production departments on a reasonable bases

28
Q

We are now looking at a step-down example ( we want to find out how much x and y should absorb of the overheads)

First of all what are the cost bases?

A

Floor space (sq.m)

Value of machinery (£)

No of employees

29
Q

Assign an appopriate bases to each and calculate overhead absroptation rate for each ( use previous page absorption bases)

A

So food and drink allocated to canteen, so we dont have to find a rate

Rent and rates ( floor speace sq.m) 18000/30000 = £0.60/m^2

Heating and light ( floor space sq.m) 12000/30000 = 0.4/m^2

Depreciation ( value of machinery) 30000/300000 = 0.1/ £

Supervision ( no of employees) 24000/80 = 300/ employee

30
Q

Fill in the banks with OAR rate.

A
31
Q

So we have apportionedd 88000 across the 4 departments but canteen and maintence are not the main production departments so what do we have to do and what basis should we apportion with?

A

We need to reapportion these costs, as canteen services all the 3 departments, we reapportion first as they are the least selfish.

We are going to reapportion using bases of number of employees as its the most sensible

32
Q

So now reaapportion canteen with NO of employees as bases?

A
33
Q

step 2. The maintenance department provides 12,000 service hours to Dept. 1 and 10,000 hours to Dept. 2,

this is gping to help us reapportion maintence overhead, so find OAR for the maintence department and reapportion maintence to dept 1 and 2

A

you add 12000 + 10000 = 22000

OAR = Budgeted Production overhead / Budgeted Activity level

11000/22000 = 0.5/hour

Dept 1 = 0.5/hour X 12000 = 6000

Dept 2 = 0.5/hour X 10000= 5000

34
Q

So we have reapportioned canteen first and Maintence, what are the phrases we say to mean the same thing?

A

We have the overhead costs owned up by Dept 1 which add up to 47000 and costs owned up by deptment 2 which add up to 41000.

35
Q

Next step says that 3. Dept. 1 is machine intensive and Dept. 2 is labour intensive 4. Budgeted machine hours for Dept.1 is 6,320 and budgeted labour hours for Dept. 2 is 7,850 so what do we have to do now?

A

We need to work out how many hours of work is going on in each of the 2 departments based on how much is the overhead cost per hour in each of the 2 departments

36
Q

. Dept. 1 is machine intensive and Dept. 2 is labour intensive 4. Budgeted machine hours for Dept.1 is 6,320 and budgeted labour hours for Dept. 2 is 7,850

Calculate OAR on each department based on the information above

A
37
Q

Final step states that Department.1 spends 2 machine hours on a unit of product X and 1.5 hours on a unit of product Y 6. Department.2 spends 3 labour hours on a unit of product X and 4 hours on a unit of product Y ( final step of finding how much OH abosrbed in each product.)

A

APPLYING OH RATE WHICH TELLSYOU HOW MUCH COST OF OVERHEADS IS CAUSED PER HOUR IN EACH OF THE TWO DEPARTMENTS. we can now calculate how much OH is absorbed in product X and Y.

38
Q

What does £30.54 and £32.04 mean?

A

All the overhead costs we have in the factory, for each unit we must own up this much cost.

39
Q

How do you calculate total overhead absorbed?

A

Total overhead absorbed = OAR x Actual activity

40
Q

What does Over absorption and under absorption mean?

A

Over-absorption = Total overheads absorbed > Total actual overhead

Under-absorption = Total overheads absorbed < Total actual overhead

41
Q

1) For example when a firm budgets how much overheads it will use a year it 100000 expenditure and use 10000 hourss on machinethis means OAR = 10/h, at the end of the year you have actually used 9000 hours of machines which means Total overhead absorbed is 90000, what does this mean?
2) What would happen if your bills were £85000 at end of the year and you bugeted £80000

A

This means there is an over absorption of 10000

Underabsorbed 5000, this wil be adjusted and added to COS

42
Q

Now lets look at a direct method example (more simple)

Scenario 1 First we will use Total direct labour hours as the ONLY cost re-apportionment basis for BOTH service departments

As the service departments don’t serve each other, whats the first thing we should do? `

A

Work out OAR of direct departmental costs, using lets say the basis of Direct labour hours

SO that would be

Personnel dept = £400000/4000 = 100/h

Facilities dept = 150000/4000 = 37.5/h

Then apply this to the table

43
Q

Direct method example now lets do another scenario we use an appropriate bases for the service department, what are apporpriate bases for Personnel and Facilities M.?

A

Personnel: Staff headcount 

Facilities Mgmt.: Floor space occupied

44
Q

Direct method As you have allocated an appropriate bases for the service departments, find the OAR rate and apply to the Production departments

A

OAR FOR PERSONNEL = 400000/570 = 701.754386 per staff

OAR FOR FACILITIES = 150000/12720 =11.79245383 per m^2

45
Q

When comparing direct method for the 2 scenarios what can we see?

A

This shows when you have more apporpriate bases such as Headcount for Assembly and floor space for paint shop, assembly should of been absorbed more by about £48,635.

And paintship were being overcharged (48635)

46
Q

What is the most important thing to remember for the stepdown method?

A

The service cost centre that serves most other service cost centres should be reapportioned first

. • Or a service department with highest costs is reapportioned first

47
Q

Lets do another example of the stepdown method?

As you can see we have to reapportion the service department of Personnel as there costs is the highest so find the bases and OAR RATE AND Apply

A

1)Personnel: Headcount [no of staff]

OAR = 400000/520 =769.2307692

then apply

48
Q

Lets do another example of the stepdown method?

Now lets reapportion Facilities M find OAR RATE AND Apply

A

THEY DO NOT SERVE PERSONEL

Bases = floor space (m^2)

We use the new totals here so

£ 238,462/7,200 +4,500 = 20.38136752 / m^2 then apply

49
Q

What are 2Advantages of absorption costing

A

Selling prices can be established to cover full “product” cost

Improved managerial awareness of total costs sustained by cost centre

50
Q

What are 2 disadvantages of absorption costing?

A

Arbitrary re-apportionment of overheads can lead to incorrect decisions being taken

Ignores the distinction between fixed and variable costs

51
Q

Which of the following is not a direct cost for the delivery service of Sainsbury plc to customers?

Select one:

A) Additional travelling expenses of the deliveries

B)The salaries of the company’s marketing managers

C) The wages paid to the delivery staff

D) The costs of the fuel consumption

A

B The cost object is the delivery service of Sainsbury to customers. Unlike the wages paid to the delivery staff, the salaries of marketing managers cannot be specifically and exclusively traced to the costs of delivery services to the customers.

52
Q

Which of the following does not belong to manufacturing overheads?

Select one:

Indirect materials

Direct materials

Factory rent

Depreciation of machinery

A

Direct materials

53
Q

Which one of the following would be classified as indirect labour?

Select one:

Machinists in a factory producing clothes

Assembly workers on a chocolate production line

A fixed wage of £5 for producing 1 unit of product X

Forklift truck drivers in the stores of an engineering company

A

Forklift truck drivers in the stores of an engineering company

54
Q

The Koala Ward of the Great Ormond Street Hospital (GOSH) for Children is responsible for children and young people with craniofacial (head and face) and neurological (brain) problems. The costs of drugs administered by the Koala Ward to patients would be classified as

Select one:

indirect costs of the patients

period costs of GOSH

overhead costs of the Koala Ward

direct costs of the patients

A

Direct costs to patients

55
Q
A

TBA

56
Q

So what are the 3 stages of absorption?

A

Allocation, apportionment and absorption

57
Q

Additional information: • Budgeted hours are 18,960 machine hours for the machining department and 23,550 labour hours for the finishing department.

• The maintenance department provides 6,000 hours of service support to the machining department and 4,500 hours of service support to the finishing department.

Required: (a) Prepare an overhead analysis sheet showing the allocation and apportionment of production overheads to the cost centres.

(b) Calculate the overhead absorption rate for the machining department using machine hours and the finishing department using labour hours

A

b) OAR FOR MACHINING DEPARTMENT = 379200/18960 =£20/MACHINE HOUR

OAR FOR FINISHING DEPARTMENT = 376800/23550 = £16/ LABOUR HOUR

58
Q

(c) Calculate the overhead to be absorbed to a product, which is to be manufactured in the near future given that it takes 4 hours of machine time from the machining department and 2 hours of labour from the finishing department.

A
59
Q

Part A

A

Direct costs can be clearly identified with a specific cost object (e.g. direct materials used in a product). Indirect cost cannot be clearly identified with a particular cost object (e.g. factory rent and electricity).

Example of direct costs ( direct labour)

Example of indirect costs - security, depreciation of machinery

Managers distinguish between direct costs and indirect costs as it helps them to deduce the full cost of a unit of output.

60
Q

Part b

A
61
Q

(c) Prepare full costings for Order No 101 using each of the rates calculated in (2) (that is, two separate costings).

The cost sheet for Order No 101 shows the following:

Raw materials £5,000

Direct labour hours 4,000 hours

Machine hours 1,900 hours.

A

FULL COSTING IS DM + DL + MOH

62
Q

(d) State briefly which of the two bases of overheads you prefer and why. How might you improve on the two possible costs that you derived in (3) by taking a slightly different approach?

A

Since the overheads are dominated by machine-related costs (power, maintenance, depreciation and so on) it could be argued that the machine-hour basis gives more relevant costs.

To improve the business should use departmentments or use activity based costing