week 10_Cost Management Flashcards

1
Q

What is the importance of project cost management?

A

IT projects have a poor track record for meeting budget goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a cost overrun?

A

The additional percentage or dollar amount by which actual costs exceed estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does project cost management include?

A

The processes required to ensure that the project is completed within an approved budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the four main processes in project cost management?

A
  • Planning cost management
  • Estimating costs
  • Determining the budget
  • Controlling costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define ‘cost’ in the context of project management.

A

A resource sacrificed or foregone to achieve a specific objective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the formula for profit?

A

Profits = Revenues - Expenditures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does life cycle costing consider?

A

The total cost of ownership, including development and support costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Differentiate between tangible and intangible costs.

A
  • Tangible costs: Easily measurable in dollars.
  • Intangible costs: Difficult to measure in monetary terms.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are direct costs?

A

Costs that can be directly related to producing the products and services of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a sunk cost?

A

Money that has been spent in the past and should not be included in future investment decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does the learning curve theory state?

A

The unit cost decreases in a regular pattern as more items are produced repetitively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are reserves in cost management?

A

Dollars included in a cost estimate to mitigate cost risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are contingency reserves?

A

Funds for future situations that may be partially planned for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are management reserves?

A

Funds for unpredictable future situations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the importance of cost estimates in project management?

A

They are essential for completing projects within budget constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the two basic types of cost estimates?

A
  • Analogous estimates
  • Bottom-up estimates
17
Q

What is a cost model?

A

A tool to facilitate changes and document the estimate.

18
Q

What is cost budgeting?

A

Allocating the project cost estimate to individual work items over time.

19
Q

What is a cost baseline?

A

A time-phased budget used to measure and monitor cost performance.

20
Q

What is earned value management (EVM)?

A

A project performance measurement technique that integrates scope, time, and cost data.

21
Q

What does ‘planned value (PV)’ refer to?

A

The portion of the approved total cost estimate planned to be spent on an activity during a given period.

22
Q

What is the actual cost (AC)?

A

The total of direct and indirect costs incurred in accomplishing work on an activity during a given period.

23
Q

What does earned value (EV) estimate?

A

The value of the physical work actually completed.

24
Q

Define the rate of performance (RP).

A

The ratio of actual work completed to the percentage of work planned to have been completed.

25
True or False: A CPI less than 100% indicates the project is under budget.
False.
26
What is the cost performance index (CPI)?
A measure used to calculate the estimate at completion (EAC).
27
Calculate the planned value (PV) for a project with a budget of $100,000 and a timeline of 10 weeks, at week 5.
$50,000.
28
What is the formula for calculating cost variance?
Cost Variance = EV - AC.
29
What does EAC stand for?
Estimate at Completion.
30
Fill in the blank: The _______ is the original total budget for the project.
budget at completion (BAC)