Vocab and Formulas Flashcards
1
Q
Present Value Formula
A
PV = FV/(1+i)^t
2
Q
Total Float
A
Total Float = Late Finish - Early Finish
3
Q
Free Float
A
= Early start of Successor - EF of activity
4
Q
PERT
A
PERT = (P+4ML+O)/6
5
Q
Schedule Standard Dev
A
STD = (P-O)/6
6
Q
Variance
A
Variance = Standard deviation ^2
7
Q
Cost Variance and Performance Index
A
CV= EV-AC and CPI=EV/AC
8
Q
Schedule Variance and Performance Index
A
SV=EV-PV and SPI=EV/PV
9
Q
Estimate at Completion
A
EAC=BAC/CPI
10
Q
Estimate to Complete
A
ETC=EAC-AC
11
Q
Variance at Completion
A
VAC=BAC-EAC
12
Q
Number of channels
A
Channels = n(n-1)/2
13
Q
Point of Total Assumption
A
PTA=target cost + (ceiling price - target price)/buyer ratio
14
Q
Famous for Critical Chain Method
A
Goldratt
15
Q
Work expands so as to fill the time available for its completion
A
Parkinson’ Theory