Video Notes Flashcards

1
Q

high level document that formally authorizes the existence of the project and assigns the project manager and their authority level

A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analyzes who your stakeholders are and how they feel about the project

A

Stakeholder Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Comprehensive document that outlines the basis of all project work and how the the work will be performed

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Scope, Schedule, Cost, Performance Measurement

A

4 Baselines of the Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Process of creating a scope management plan that documents how the project/product will be defined, validated, and controlled

A

Plan Scope Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How the scope will be defined, developed, monitored, controlled, and verified

A

Scope Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How the requirements will be analyzed, documented, and managed

A

Requirement Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Process of determining, documenting, and managing stakeholder needs and requirements to meet objectives

A

Collect Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Developing a detailed description of the project and product.

A

Define Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describes in detail the project deliverables and the work that is required to produce those deliverables

A

Project Scope Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A structured breakdown of the work; also called decomposition of work; subdividing project deliverables and project work into smaller, more manageable components

A

Create Work Breakdown Structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

breaking down each of the project deliverables into smaller components.

A

Decomposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Poject Scope Statement, WBS, and WBS Dictionary are three components of this

A

Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Defines responsibilities of the team

A

Work Breakdown Structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

A

Plan Schedule Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

how the project schedule will be planned, developed, managed, executed, and controlled throughout the phase or project

A

Schedule Management Plan

17
Q

Process of identifying and documenting the specific actions to be performed to produce the project deliverables

A

Define Activities

18
Q

Complete list of all scheduled activities required to be performed on the project

A

Activity List

19
Q

Defines the logical sequence of work to obtain the greatest efficiency given all project constraints

A

Sequence Activities

20
Q

Amount of time a successor activity can be advanced with respect to a predecessor activity

A

Leads

21
Q

Estimating the number of work periods (hours, days, weeks, etc.) needed to complete individual activities with estimated resources

A

Estimate Activity Durations

22
Q

Relies on historical information to predict estimates for current projects. Often used when there is a limited amount of information available.
Costs less in time and money to use, but it provides the least amount of accuracy when it comes to estimating.

A

Analogous Estimating (Top-Down Estimating)

23
Q

A technique that uses a statistical relationship between historical data and other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and duration

A

Parametric Estimating

24
Q

Calculates an expected duration using a weighted average of 3 estimated, Optimistic, Pessimistic, Most Likely

A

Three-Point Estimates / PERT

25
Q

Work needs to be very detailed for this type of estimation to take place
Takes a long time to complete, but highly accurate

A

Bottom-Up Estimating

26
Q

Analyzing activity sequences, durations, resource requirements, and schedule constraints to create a schedule model for project execution and monitoring and controlling

A

Develop Schedule

27
Q

Defining how the project costs will be estimated, budgeted, managed, monitored, and controlled

A

Plan Cost Management

28
Q

Cost Management Plan

A

How costs will be planned, structured, and controlled

29
Q

Developing an approximation of the costs of the resources needed to complete project work

A

Estimate Cost

30
Q

Range of possible cost estimates; includes confidence level of estimates and how the estimates were developed and by whom

A

Basis of Estimates

31
Q

Process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

A

Determine Budget

32
Q

Details on what each schedule activity is scheduled to cost; will roll up to each parent work package to determine total cost and budgetary requirements

A

Cost Aggregation

33
Q

additional money added to project for risk

A

Reserve Analysis

34
Q

PM determines, manages, and controls the contingency reserves, which will address the cost impact of the remaining or known/unknown risks

A

Contingency Reserves

35
Q

Management determines the funds to cover unknown/known risks for the project

A

Management Reserves

36
Q
A