Value Stream Mapping Flashcards

1
Q

Plant Operating Details

A
  • 3 Shifts, 5 days per week, 8 hours/shift, 30min break/shift, 48 weeks, customer demand 800,000 units/annum
  • Cell layout consists of 3 machines (operating sequence M1 - M2 - M3). 3 operators (1 OP per machine)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

M1

A

value add machine element time - 12.5sec

non value add machine element time - 3 sec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

M2

A

Value add machine element time - 10 sec

non value add machine element time - 1 sec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

M3

A

Value add machine element time - 4sec

non value add machine element time - 4.5sec

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Installed Capacity

A

Installed Capacity = Available Time/ Bottleneck Cycle Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly