Value Stream Mapping Flashcards
1
Q
Plant Operating Details
A
- 3 Shifts, 5 days per week, 8 hours/shift, 30min break/shift, 48 weeks, customer demand 800,000 units/annum
- Cell layout consists of 3 machines (operating sequence M1 - M2 - M3). 3 operators (1 OP per machine)
2
Q
M1
A
value add machine element time - 12.5sec
non value add machine element time - 3 sec
3
Q
M2
A
Value add machine element time - 10 sec
non value add machine element time - 1 sec
4
Q
M3
A
Value add machine element time - 4sec
non value add machine element time - 4.5sec
5
Q
Installed Capacity
A
Installed Capacity = Available Time/ Bottleneck Cycle Time