1
Q

How far must candles or open flames be from a Christmas tree

A

Within a distance equal to the height of the tree

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is required to place a Christmas tree in a public building

A

Permit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What should the tag on a Christmas tree say

A

Date of placement in the public building
type of flame retardant treatment used
name of the person who applied the flame retardant
name of the person of fixing the tag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How should the tree trunk of a Christmas tree be prepared

A

A butt cut at a diagonal at least 1 inch above the original cut

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How high should the water level be in a Christmas tree

A

2 inches above the butt cut

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What type of fire extinguisher should be available at a public buildings Christmas tree

A

2A:10BC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the flame test of a fire retardant treated Christmas tree

A

No spread of flame from the area in contact with the test flame and after flaming shall not exceed 10 seconds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the test for fire retardant treated fabrics

A

Fabric shall not continue to flame for more than one second after the ignition source is removed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When must licenses for the sale of fireworks be obtained

A

Prior to June 15from the state fire marshal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When do you have to get your permit to sell fireworks from the city

A

10 days before sales open from the governing body of the city

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the sales period for fireworks

A

12 noon on June 28 through 12 noon on July 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Age ranges for fireworks sales

A

At least one supervisor 21 years of age or older on duty at all times no one under 18 inside the stand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Staffing and guarding firework stands

A

Stands shall be guarded at all times but no person shall sleep or remain inside the stand when it is not open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Location in distances for fireworks stands

A
At least 25 feet from all buildings 
15 feet from curb lines 
10 feet clear in every direction 
25 feet from vehicles used for sleeping
100 feet from storage or use of flammable liquids 
dry grass and weeds clear for 25 feet
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Dimensions for the construction of fireworks stands

A

Built of wood or metal
no more than 400 ft.²
no more than 12 feet deep
counter 3 feet high with panel of unbreakable glass or wire mesh 18 inches in height minimum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Doors for fireworks stands

A

At least 36 inches wide at both ends opening outward

no exit shall be less than 12 feet away from anywhere in the stand

17
Q

Fireworks stand signage

A

Minimum 3 inch letters stating fireworks shall not be sold two persons under 16 years of age

18
Q

Extinguishers for a fireworks stand

A

Minimum of two 2 1/2 gallon water extinguishers serviced within the last 12 months

19
Q

When must firework stands be removed

A

Premises must be cleared of structures and debris within 72 hours after midnight on July 4

20
Q

What must all new swimming pools are spas in very high fire hazard severity zones (VHFHSZ) have

A

New pools or spas with 5000 gallons or more will have a minimum 4 inch diameter drain and discharge line connected to a draft hydrant

21
Q

What are the exceptions for the VHFHSZ pools draft hydrants

A

Pool bottoms of 15 feet or more below a draft hydrant connection
properties with adequate access road and fire hydrant that flow 1250 GPM for two hours
properties built prior to August 13 95 that would suffer undue hardship

22
Q

How large is the area adjacent to high transmission line easement

A

100 foot wide area adjacent to in parallel with the dip line of the most outward high-voltage transmission line

23
Q

What voltage do high-voltage transmission lines operate

A

66 kV

24
Q

Can new permanent structures be constructed with in the utility easement under high-voltage lines

A

No new permanent structures unless they are restrooms or an occupied telecom structures less than 15 feet in height

25
Q

What is the limits of combustible storage under high voltage utility easements

A

Piles not exceeding 5000 ft.² or 50,000 ft.³ in volume

26
Q

Outdoor storage of combustible materials under high-voltage lines must have how much clear space

A

A clear space of at least 20 feet or half the height of the pile which ever is greater between pile under high-voltage powerlines

27
Q

What are the requirements for vehicle storage underneath high-voltage transmission lines

A

20 foot wide FD vehicle access
20 foot break every 150 feet
3 feet between cars and
not exceed four cars deep

28
Q

Requirements for storing cargo containers and truck trailers underneath high-voltage powerlines

A

Must be less than 15 feet in height

29
Q

What is the required on site hydrants for secondary use under high-voltage powerlines

A

On site hydrant spaced it 600 foot intervals

30
Q

What is the required fire floor underneath high-voltage powerlines in VHFHSZ

A

1000 GPM

31
Q

Are the requirements for a marine vessels or boats under high voltage power lines

A

They are not permitted to be parked or stored within the easement under power lines

32
Q

What is a façade

A

Outdoor structure designed to represent the front of the building for motion picture television and commercial production not intended for human occupancy

33
Q

What are the classifications of façades

A

Enclosed facade and exterior façade

34
Q

What is an enclosed permanent façade

A

A façade that is in closed on three or more sides and contains a roof and or floor system

35
Q

What is an exterior permanent outdoor façade

A

A façade that has a maximum of three sides and does not contain a roof or floor system

36
Q

What is the definition of permanent when dealing with outdoor façades

A

Anything erected for a period of more than 180 days must be approved by DPW building and safety division

37
Q

What is the maximum height requirement for a permanent outdoor façade

A

Highest roof surface shall Not exceed four stories or 50 feet

38
Q

What are the requirements for a hot work permit’s on permanent outdoor façades

A

Firewatch extended to one hour must have a charged three-quarter inch hard rubber hose line long enough to reach all areas permit she’ll be approved by the jurisdiction of fire prevention inspector