*Utility Relocation Quiz Flashcards
- Master Agreements are normally used on what type of project?
a. Freeway
b. Conventional Highway
c. Expressway
d. Any of the above
d. Any of the above
Answer: 13.04.03.01
- Utility Relocation plans can be designed by
a. utility coordinator
b. project development
c. utility owner
d. both B and C
d. both B and C
Answer: 13.03.04.00
b. project development
c. utility owner
- Utility Coordinator’s responsibilities include all but one of the following:
a. obtain encroachment permits
b. ensure relocation is done by the due date
c. write relocation plans on behalf of the Owner
d. coordinate with Construction for inspection of relocation work
c. write relocation plans on behalf of the Owner
Answer: 13.01.01.01
- When do Utility Agreements have to be amended?
a. only when it is determined necessary by Audits
b. when the Utility Owner notifies the coordinator that their costs are over original estimate.
c. If the final relocation costs exceed 25% of original estimate
d. Never
c. If the final relocation costs exceed 25% of original estimate
Answer: 13.07.05.01
- The primary purpose of the JUA/CCUA is what?
a. perpetuate the State’s rights
b. perpetuate the Owner’s rights
c. determine liability
d. all of the above
b. perpetuate the Owner’s rights
Answer: 13.11.02.00
- A _______ is used when the Owner’s facility will remain on lands used for highway purposes but will be relocated to a position outside, or partly outside, the Owner’s existing right of way where the Owner had prior rights?
a. CCUA(Consent to Common Use Agreement)
b. MOS (Memorandum of Settlement)
c. JUA (Joint Use Agreement)
d. Permit to Enter
c. JUA (Joint Use Agreement)
Answer: 13.11.02.01
- When is the Utility work performed on a project (timing)?
a. Before Construction
b. After Construction
c. During Construction
d. A and C
e. all of the above
e. all of the above
Answer:
- State owned facilities are always considered exempt?
TRUE FALSE
FALSE
Answer:
- State does not pay for _______ of facility, unless such an increase was a project ______ forced on the owner.
a. enlarging
b. improving
c. betterment
d. functional
c. betterment
Answer: 13.04.05.06
- If a Utility Owner has to relocate their facilities with-in _____, the State is liable for these relocation costs.
a. 7 years
b. 15 years
c. 10 years
d. Never
c. 10 years
Answer:
- When does Caltrans allow utility functions to remain longitudinally within the state right of way without the approval of the Chief, Encroachment Exceptions, Division of Design?
a. only on freeways (access restricted)
b. conventional roads
c. on both conventional roads and freeways
b. conventional roads
Answer: 13.03.04.01
- The ______ is utilized by the R/W Agent to order a utility company to remove, adjust, relocate or abandon its facilities with the State’s proposed highway construction area by a specified date to accommodate a project.
a. Utility Agreement
b. Encroachment permit
c. Notice to Owner
d. Right of entry
c. Notice to Owner
Answer: 13.06.01.00
- Master Agreements are an important factor in determining Prior and Superior Rights?
TRUE FALSE
FALSE
Answer: 13.04.01.01
- An Encroachment is a non highway structure or object which is placed in, under or over any portion of the highway.
TRUE FALSE
TRUE
Answer:
- The current Freeway Master Contract totally replace statues in determining cost liability on utility relocation for freeway projects?
TRUE FALSE
TRUE
Answer: Table 13.04-1
- Toxic or flammable gases are considered to be high risk.
TRUE FALSE
TRUE
Answer:
- The Utility Agreement addresses the following credits:
a. salvage, betterments and master agreement
b. depreciation, salvage and betterments
c. pole counts and master agreements
d. appreciation, salvage and betterments
b. depreciation, salvage and betterments
Answer: IV-8