USBR ch 7 Flashcards

1
Q

What are the conditions that must occur before a rockfill dam can prove to the economical?

a) earthfill materials are difficult to obtain or regulate extensive processing before use
b) short construction seasons prevail
c) the dam is tp be raised at later date
d) all above

A

d) all above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Does uplift pressures and erosion caused by seepage through a rockfill dam generally cause probelms?

a) no, due to saturation and evaporation
b) no, rockfill materials do not generally constitute significant design problems
c) yes, because of sedimentation
d) none above

A

b) no, rockfill materials do not generally constitute significant design problems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Name materials that are used as impervious material in a rockfill dam

a) steel
b) tile
c) wood
d) concrete
e) fiberglass
f) earth material

A

a) steel

c) wood
d) concrete

f) earth material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Two advantages of using an internal membrane in a rockfill dam are shorter grout curtain lengths and less total area exposed to water

T or F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bedrock foundations that are soft and erosion resistant are the most desirable for a rockfill dam

T or F

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Limited settlement is critical in the construction of rockfill dams because excessive settlement may rupture the upstream membrane or cause joint separation with subsequent water loss.

T or F

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Name some advantages of asphaltic concrete

a) flexibility
b) can tolerate larger settlement than reinforced concrete
c) economical alternative to concrete
d) dependable when correctly constructed
e) all above

A

e) all above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly