Urban Issues and Challenges - The Olympic Plan Flashcards
1
Q
Features of site before work began:
A
- Open space
- Contaminated overgrown land
- 250 businesses employing 5000
- Community with 500 homes
2
Q
Obstacles:
A
- Land had to be brought under ODA
- People forced to leave
- Electricity pylons removed
- Cables buried underground
3
Q
Reasons for successful bid:
A
- Large area of available land
- Good transport connections e.g. SIS
- Legacy would help to regenerate East London
- Diverse population of London
4
Q
Key Features of QE Olympic Park Project (100 hectares):
A
- Here East (5000 jobs)
- East Village (2800 homes with affordable rent)
- Sports venues
- Westfield employs 10,000
- International Quarter will employ 25,000
5
Q
Money spent by London on the games:
A
£9.3 billion
6
Q
Plan by 2030 for new residentials:
A
5 new communities, providing 8000 homes
7
Q
Facts about East Village:
A
- 2800 homes, half for priv rent half for affordable rent
- Range of homes (apartments - townhouses)
- New school for 1,800 (Chobham Academy)
- Close to bus routes, new local station, and SIS
- 27 Ha are, with 10 Ha of park and public open space - social + environmental benefit
- 35 small independent businesses including a supermarket and gym