Estimating techniques are …
A
Comparative - compare and adjust old project
Parametric - measured quantity (eg area)
Bottom-up - WBS is used
3-point estimates - min (optimistic O), most likely (M), max (pessimistic P)
=(O + 4M + P)/6
2
Q
EVM is
A
Earned Value Management
completed work vs budget assigned
allows you to forecast based on trends
Needs WBS & OBS (and CBS)
Method for measuring
Not easy to do!