Unit 4- Network analysis Flashcards

1
Q

Estimated task time formula

A

𝑇𝑒 = (𝐴+4𝑀+𝑃)/ 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Estimated task time

A

the sum of optimistic time estimate+ 4 times most probable time estimate + pessimistic time, all divided by 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Network diagram path lengths

A

you add all the times from each point from a path on the network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Critical path

A

is the longest path in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

crash

A

saves time not money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Predecessor

A

is a task that must be completed before the next task can be started. these help determine the sequence in which tasks must be completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

succesor

A

task that must follow another task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

tabular format information

A
  • identifier
  • description
  • predecessors
  • duration
  • assigned resources.
  • cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

steps in creating a network diagram

A
  1. define the project and all of the project tasks
    2.determine the task relationship and which activities must precede or succeed others.
    3draw the diagram connecting the activities.
    4.assign time estimates or durations to each activity.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

cost slope formula

A

crash cost- normal cost / normal distribution-crash duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly