Unit 3.1- Remedies Flashcards
What is the main remedy of breach of contract?
Damages
What does ARMM stand for?
Aim- to compensate the claimant
Remoteness- within the contemplation of parties (Hadley Baxendale)
Measure- reliance (Anglica TV v Reed) or expectation loss (Robinson v Harman)
Mitigation- has the claimant taken reasonable steps to mitigate their loss?
What should be considered in relation to expectation loss?
Difference in value of goods Cost of Cure Loss of amenity Lost opportunity (Chaplin v Hicks) Lost pleasure (Addis v Gramaphone, Jarvis v Swan's Tours, Farley v Skinner)
What is expectation loss?
Putting the claimant back in the position they would have been in had the contract been properly performed (Robinson v Harman)
What is reliance loss?
Putting claimants in position they would have been in had the contract never been entered into in the first place (Anglia TV v Reed)
What has to be considered when measuring damages?
Remoteness
Mitigation
The time being assessed
Specific damages/ penalty clause
How do you decide specific damages/ penalty clauses?
Dunlop Pneumatic Tyre Co- question of construction
Sum stated extravagant/ unconscionable compared to greatest loss that could be proved to have followed- PC
Breach consists of not paying- PC
Single sum due on happening of one or more events that can cause a range of damage, presumed PC
Saying PC/ SD not conclusive
Define Specific damages
A genuine attempt to pre-estimate loss, can be enforced
Define penalty clause
An attempt to put pressure on a party to perform their part of the contract
Available remedies?
Damages
Restitution
Action for Agreed Sum
Equitable remedies- specific performance/ injunction
What is the remoteness rule?
Hadley v Baxendale- was the damage caused due to an ordinary course of dealings and if not were the special course of dealings known to the parties at the time the contract was entered into?
Case law re remoteness?
Victoria Laundry- profits that are highly lucrative/ special are too remote
Parsons (Livestock) v Uttley Ingham- if the type of loss is foreseen then the extent of that loss is also foreseen
Brown v KMR- distinguish between special profits and high profits
Balfour Beatty- HoL said Scottish Power not liable for full loss suffered by claimant as a result of an interruption in the electricity supply
What does British Westinghouse say?
Claimant must take reasonable steps to mitigate loss and he can claim expenses incurred in trying to do so even if attempt is unsuccessful
What is the rule re time assessment for damages?
Damages are assessed by reference to time of breach (e.g. cost of goods at time of breach)
However, aim of damages is to put claimant in position he should have been in had contract been performed
Latter prevails (The Golden Victory) so if time assessment rule doesn’t allow this, don’t use it
Action for agreed sum
Not a damages claim so remoteness and mitigation rules do not apply