Unit 10 Flashcards

1
Q

Identify what does network analysis portray?

A

Network analysis is a planning method that allows a project to be completed in the shortest time possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What factors does a network analysis include?

A
  • Duration of each activity
  • List of all activities
  • Quickest completion time
  • Float and no float to stress which activities must be completed in time.
  • Duration that each activity will take to complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What information is required to construct a network analysis diagram?

A

Tasks/activites, duration of each task, the order in which they should be completed, earliest start time (EST) and latest finish time (LFT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the ‘circle’ symbol within a network analysis diagram present?

A

Node - activity number, EST, LFT (latest start time)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Identify the importance of a critical path

A

Any delay in the competition time of an activity, identified through critical path, impacts the planned completion date of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Identify how the LFT and EST is calculated in a critical path network

A

EST: calculated from left to right, add durations, if a following EST has two nodes before it the larger EST will be chosen.
LFT: calculated from right to left, LFT minus the duration of the previous activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Describe what is meant by the term ‘float’ and identify how it is calculated

A

Float represents the additional time an activity can over run without delaying the overall process.

Float = LFT - duration - EST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Identify how ‘float’ is represented on a critical path

A

’//’ through the line of the activity with a float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Identify potential advantages of constructing a critical path analysis

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly