A can do a work in x days
A + b can do a work in Y days
B can do a work in
Xy/y- x days
A can do a work in x days
b can do a work in Y days
A + b can do a work in
Xy/ X + y days
A can do a work in x days B in y days C in z days together they can do work in
Xyz/xy + y z + ZX
Certain number of men can do work in D days
X-Men Less could be finished in e days
Number of men originally
x(d+e)/e
Certain number of men can do work in D days
X-Men more could be finished in e days
Number of men originally
x(d-e)/e
A is n times as fast / slow as B
Therefore is able to finish a work in 30 days more or less
Time taken to complete the work together
(Dn/ n^2-1) days
X men and y women can reap a field in D days
S men and P women can take
D(xy)/xp+ys
There is sufficient food left for M men for D days
If after s days X men will leave the place rest of the food will last for
(D-s/ M-X)M
There is sufficient food left for M men for D days
If after s days X men will join the place rest of the food will last for
(D-s/ M+X)M
if a can do a work in 6 days B can do a work in 18 days if contract for work is rupees X and both of them work together then the share of a and b is given by
(X/x+y )*y. For a
(X/x+y )*x. For B
A person can do work in X days with the help of another person b, can do the same work in y days
If they get rupees z for that work then the share of a and b is given by
Share of A
Zy/x
Share of B
Z(x-y)/x
A can do a work in x days B can do work in y days they began to work together but a left sometimes later be finish remaining work in Z number of days after which a left is given by
(Xy/X + y) (y-z/y)
A group of man decided to do a work in x days
But n of them became absent
If the rest of the group did the work in y days
Then the original number of men is given by
(Ny/y-x)men
A can do a work in x days
B can do it in y days
If they work together for D days
A goes away the number of days in which we finish the work is
Y- [1+y/x]d days
If a working alone takes X days more then A and B working takes y days more than a and b
Number of days taken by both A and B working together
√xy