Total Float (Quick Revision) Flashcards

1
Q

Define: Total Float

A

The total float is the amount of time an activity can overrun without delaying the project as a whole.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

State three advantages of critical path analysis.

A
  • Can reduce stock levels
  • Can order items just when needed
  • Can complete a project more quickly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earliest Start Time: day 4

Latest Finish Time: day 12

Total Float: 3 days

What is the duration of the activity?

A

12 - 4 - duration = 3 days

So the duration must be 5 days for answer to be 3 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the significance of identifying the critical path?

A

Can focus on these activities to make sure project is completed on time; can prioritise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How might a firm speed up the time taken to complete a project?

A

Invest more money in resources (e.g. more people, more technology)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Examiner’s note for Total Float?

A

Critical path analysis can help a firm to order supplies only when they are needed and so can lead to better working capital control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Evaluation point for Total Float?

A

Critical path analysis is a planning tool. It’s value relies on how well it is used. For example;

  • Are there clear guidelines about who has to achieve what?
  • Are targets chased to make sure people achieve them?
  • Are the resources provided to make sure the targets are viable?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly