Topic 8: Discounting Flashcards

1
Q

BCAs need various info

A

Conditions or outcomes without project

Project actions

Conditions or outcomes with project i.e cause and effect relationship

Valuation of benefits in $ terms

Likely degree of behaviour change

Risks to project success

Timing of benefits and costs

Costs of various types

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Future value

A

FV(t) = PV x (1+r)^t

FV(t) = future value t years after present

PV= present value

r= interest rate

t= time in years after present

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Discount factor

A

= 1/(1+r)^t

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Net present value (NPV)

A

= PV(B) -PV(C)

PV( )= present value function

B= benefits

C= costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Benefit: Cost ratio (BCR)

A

= PV(B) / PV(C)

Rule for good project: BCR > 1

PV ( ) = present value function

B= benefits

C= costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

PV =

A

Net benefit x discount factor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly