Topic 8: Discounting Flashcards
1
Q
BCAs need various info
A
Conditions or outcomes without project
Project actions
Conditions or outcomes with project i.e cause and effect relationship
Valuation of benefits in $ terms
Likely degree of behaviour change
Risks to project success
Timing of benefits and costs
Costs of various types
2
Q
Future value
A
FV(t) = PV x (1+r)^t
FV(t) = future value t years after present
PV= present value
r= interest rate
t= time in years after present
3
Q
Discount factor
A
= 1/(1+r)^t
4
Q
Net present value (NPV)
A
= PV(B) -PV(C)
PV( )= present value function
B= benefits
C= costs
5
Q
Benefit: Cost ratio (BCR)
A
= PV(B) / PV(C)
Rule for good project: BCR > 1
PV ( ) = present value function
B= benefits
C= costs
6
Q
PV =
A
Net benefit x discount factor