topic 6 Geo Flashcards

1
Q

Describe the two main differences between a contiguous bored pile and a normal bored pile.

A
  1. CBP requires more steel reinforcements than bored pile
  2. CBP is subjected to lateral load and bored pile is subjected to vertical load.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List the three main advantages of contiguous bored pile.

A
  1. Improved water tightness
  2. Adaptable to any irregular layout of the excavation site
  3. Can be adapted to form part of the permanent structure
  4. Less noise compared to driven pile
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Determine four factors affecting the choice of materials for filling and backfilling.

A

1.The material is not too wet, full of voids and liable to excessive shrinkage

  1. The material contains appropriate texture or consistency such that it can be
    properly compacted.

3.The material is readily available.

4.The material is as hard as possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

State the effects of wet conditions to excavation work.

A
  1. Difficult to trim the formation level accurately
  2. Difficult to erect formwork / Earth Retaining Structure (ERS)
  3. Increase in concrete’s water/cement ratio
  4. Increase in lateral pressure on ERS
  5. Bottom heaving of excavation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly