topic 4 Flashcards

1
Q

Capacity Factor

A

Utilization rate of an asset - the percentage of time that an asset produces at its maximum rate. Multiplying the CF by 8760 (# of hours in a year) results in Expected Annual Production. The CF can decrease over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Heat Rate

A

Units of input fuel adjusted to units of output electricity. This is very specific to the type of fuel being used by the specific generator designed. Denominated as a rate in which energy fuel is converted to kWh (ex: MJ/kWh)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Rate Case

A

Process by which PUCs set prices (approval of cost of service recovery). Usually a regulatory commission oversees the proceeding.

case made by utilities about how much they should be allowed to charge customers, based on their investments and costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Stranded Costs

A

Existing investments in infrastructure for incumbent utilities that may become redundant in a competitive environment.

A large, incumbent monopoly electric power utility will have made substantial investments over the years and will carry debt. The market cost of electricity includes payments on this debt.

For example, a power plant may have been built when prices were regulated and the utility was able to accurately predict the amount of money it would earn. However, if the market is deregulated shortly after a plant is built, and competition comes into the market, the rates that the company can charge will fall. As a result, future revenues won’t be enough to pay for the plant thereby stranding the costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Emissions

A

The cost can be calculated using economic valuation of the damage caused or using the cost of alternatives to reduce emissions. Estimations from damage is controversial because different electricity sources pose different impacts. Monetary quantification is difficult because of the complexity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CHP

A

Combined heat & power produce heat for alternative purposes. CHP can be compared with energy sources that provide both power generation and another service. CHP is an opportunity for savings in costs and energy because it recovers heat; in some case efficiency has been improved from 30% to 80%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Capacity Markets

A

Set payment mechanisms with visibility far enough out to induce necessary investments in additional assets. Typically buy forward capacity, 3 or more years out and owners of generators get contracts to sell capacity at future dates. The contracts provide revenue certainty which attracts financial capital. Wide variation in how sellers are compensated.; in spot market you buy kWh, in future markets you buy capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Organized Market

A

Markets for buying capacity, primarily in the US, whose aim is to meet demand at the lowest possible cost. 3 most common types are forward markets, day-ahead markets, and real-time markets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Wholesale Market

A

Market of buyers and sellers of electricity. Includes generators and utilities (consumers do not usually participate in wholesale market unless they are very large industrials)

A way for buyers and sellers to transact at reasonable prices. Market considerations include unpredictable loads, purchasing reliability and quality, location pricing, purchasing low-cost energy supply. These considerations help set the rules of the markets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Discount Rate

A

Calculates the costs incurred in one period that need to be spread over many periods. Usually measured in WACC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Supply Stack

A

Collection and aggregation of bids. Electricity generators bid into the wholesale market the amount of electricity they produce at their marginal cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Merit Order

A

Prioritization by lowest cost. Ensures the lowest cost producers are the first ones called on, followed by the next lowest until load is met

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Market Clearing Price

A

Equilibrium price where all profit opportunities for sellers and all benefit opportunities for buyers have been exhausted. Electricity markets use a Dutch auction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Marginal Cost

A

Cost to produce one more or one less unit of something. Generators are willing to sell into the market as long as the price received is more than costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

LCOE

A

Levelized Cost of Electricity: sums all cost elements on a consistent basis involved in the creation, operation, and fueling of an asset and divides that total cost evenly over the output of the asset. Often denominated as cents/kWh. Key errors are the assumptions about performance of an asset and false comparisons to other generators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Busbar

A

A substation connection device where electricity is priced and delivered into the grid

17
Q

Busbar Costs

A

Also referred to as the LCOE. Once electricity reaches the grid, it is difficult to further directly attribute additional costs of transformation to the output of that single generator

18
Q

Overnight Cost

A

The cost of completing the generation asset and putting it into service as if it were to happen overnight. Denominated in units of power ($/W) and incurred once. Known at the time of construction.

19
Q

Fixed O&M Cost

A

The operating and maintenance costs required to keep the asset at full operating capacity before it is used to produce the first unit of output. Includes site maintenance, staffing, cleaning, etc. Denominated as a cost per unit of capacity that must be incurred each year ($/W per year)

20
Q

Variable O&M Cost

A

Maintaining the plant becomes costlier as it is used. Maintenance will be determined on a marginal basis. Typically determined on a cent/kWh basis

21
Q

Prime Mover

A

A machine, such as a water wheel or steam engine, that receives and modifies energy as supplied by some natural source or fuel and transforms it into mechanical work.

22
Q

Bid Stack

A

Bids arranged by merit order form bid stacks. The spot price is set by finding the highest bid stack needed to match demand

The “stack” of bids to supply capacity made by generators. Bids are stacked in order of the bid price- lowest at the bottom of the stack. Utilities purchase in the auction starting with lowest price.

23
Q

Load Duration Curve

A

Illustrates the relationship between generating capacity requirements and capacity utilization. It puts in declining order the load for all 8760 hours of the year.

24
Q

Induced Seismicity

A

Earthquake activity resulting from human activity (often tied to fracking)

25
Q

Run-of-river

A

Applied to hydro plants: a low-head plant using the flow of a stream as it occurs and having little or no reservoir capacity for storage

26
Q

Flood control

A

All methods used to reduce or prevent detrimental effects of flood waters

27
Q

LCOE - Subsidized/Un-subsidized

A

Government subsidies range from 0% (coal) to 100% (solar). Newer technologies tend to need subsidies to compete (as does nuclear)

28
Q

Reprocessing

A

Nuclear reprocessing technology was developed to chemically separate and recover fissionable plutonium from irradiated nuclear fuel

29
Q

Fungibility

A

Property of a commodity whose individual units are capable of mutual substitution. WHAT, WHERE, WHEN, HOW CERTAIN

30
Q

Power Take-Off

A

A device that transfers mechanical power from an engine to another piece of equipment

31
Q

Credit Rating

A

An estimate of the ability of an organization to fulfill their financial commitment based on previous dealings

32
Q

WACC

A

Weighted Avg Cost of Capital: Combines costs of debt financing and equity financing on projects. Approximates overall risk. Factors into calculating the Discount Rate