Topic 2: Process costing (FINAL) Flashcards
What is process costing, and where is it used?
Process costing is a cost system used to allocate production costs to units of product, used in industries such as food and beverage (e.g., Coca-Cola), chemical (e.g., petroleum products), textiles, energy, cement, plastics, and pharmaceuticals commonly use process costing.
What are the key steps in determining costs using process costing?
Step 1: Preparation of Quantity Schedule
Step 2: Calculation of Equivalent Units
Step 3: Cost per Equivalent Unit of Production
Step 4: Cost reconciliation
What documents are essential in a process costing system?
Key documents include:
- Quantity Schedule: Shows the flow of units through the department (beginning work in progress inventory, units started into production and total units)
- Department Production Report: Combines quantity schedule, equivalent units (EU), cost of equivalent units of production and total costs (cost reconciliation).
What is a department production report?
A summary of the number of units moving through a department during a period, and it also provides a computation of unit costs. In addition, it shows what costs were charged to the department and what disposition was made of these costs.
What are the three primary cost components in process costing?
- Direct materials
- Direct labor
- Manufacturing overhead
What components are included in conversion costs?
Direct labor costs and manufacturing overhead.
What is a processing department?
Any location in an organization where work is performed on a product and where materials, labour or overhead costs are added to the product.
1. Activities performed uniformly
2. Output is homogeneous
What is the purpose of tracing costs in a processing department?
To determine total costs for finished goods and ensure accurate cost allocation between departments.
What is sequential processing (related to processing department)?
When units flow in sequence from one department to
another.
What is parallel processing (related to processing department)?
When units flow through different processing departments.
How are materials, labor, and overhead costs tracked in a process costing system?
- Costs are traced to processing departments, simplifying cost accumulation.
- A separate Work in Progress (WIP) account is maintained for each processing department.
- Completed production from one processing department is transferred to the WIP account of the next department for further work.
- Once fully completed, units are transferred from the final department to the Finished Goods account.
(See exhibit 5.4)
What are “transferred-in costs”?
Transferred-in costs are the costs of partially completed goods that are transferred from one processing department to another during production.
How are material costs handled in process costing?
Materials are drawn from the storeroom using a materials requisition form, similar to job-order costing.
Materials can be added at any processing department, but it’s common to add most materials in the first department. Subsequent departments typically add only labor and overhead costs as partially completed units move toward completion.
How are labor costs applied and recorded in a process costing system?
Since costs do not need to be identified with specific jobs, a time clock is generally used to accumulate labor costs and apply them to the appropriate processing department.
How are overhead costs applied to products in a process costing system?
Two scenarios:
1. If production levels are stable and overhead costs are incurred uniformly, actual overhead costs can be charged to products.
2. When production levels fluctuate or overhead costs are not uniform, predetermined overhead rates are used to avoid variations in unit product costs.
Each processing department has its own separate predetermined overhead rate.