Time Mgmt Inputs/Outputs Flashcards
1
Q
(6.1) Define Activities
A
Inputs
- Scope Baseline
- EEF
- OPA
Outputs
- Activity List
- Activity Attributes
- Milestone List
2
Q
(6.2) Sequence Activities
A
Inputs
- Activity List
- Activity Attributes
- Milestone List
- Project Scope Statement
Outputs
- Project Schedule Network Diagrams
3
Q
(6.3) Estimate Activity Resources
A
Inputs
- Activity List
- Activity Attributes
- Resource Calendars
- EEF
- OPA
Outputs
- Activity Resource Requirements
- Resource Breakdown Structure
4
Q
(6.4) Estimate Activity Durations
A
Inputs
- Activity List
- Activity Resource Requirements
- Resource Calendars
- Project Scope Statement
- EEF
- OPA
Outputs
- Activity Duration Estimates
5
Q
(6.5) Develop Schedule
A
Inputs
- Activity List
- Activity Attributes
- Project Schedule Network Diagrams
- Activity Resource Requirements
- Resource Calendars
- Activity Duration Estimates
- Project Scope Statement
Outputs
- Project Schedule
- Schedule Baseline
- Schedule Data
6
Q
(6.6) Control Schedule
A
Inputs
- Project Mgmt Plan
- Project Schedule
- Work Performance Information
Outputs
- Work Performance Measurements
- Change Requests