Time Mgmt Inputs/Outputs Flashcards

1
Q

(6.1) Define Activities

A

Inputs

  • Scope Baseline
  • EEF
  • OPA

Outputs

  • Activity List
  • Activity Attributes
  • Milestone List
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

(6.2) Sequence Activities

A

Inputs

  • Activity List
  • Activity Attributes
  • Milestone List
  • Project Scope Statement

Outputs
- Project Schedule Network Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

(6.3) Estimate Activity Resources

A

Inputs

  • Activity List
  • Activity Attributes
  • Resource Calendars
  • EEF
  • OPA

Outputs

  • Activity Resource Requirements
  • Resource Breakdown Structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

(6.4) Estimate Activity Durations

A

Inputs

  • Activity List
  • Activity Resource Requirements
  • Resource Calendars
  • Project Scope Statement
  • EEF
  • OPA

Outputs
- Activity Duration Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

(6.5) Develop Schedule

A

Inputs

  • Activity List
  • Activity Attributes
  • Project Schedule Network Diagrams
  • Activity Resource Requirements
  • Resource Calendars
  • Activity Duration Estimates
  • Project Scope Statement

Outputs

  • Project Schedule
  • Schedule Baseline
  • Schedule Data
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

(6.6) Control Schedule

A

Inputs

  • Project Mgmt Plan
  • Project Schedule
  • Work Performance Information

Outputs

  • Work Performance Measurements
  • Change Requests
How well did you know this?
1
Not at all
2
3
4
5
Perfectly