Integration Mgmt Inputs/Outputs Flashcards
1
Q
(4.1) Develop Project Charter
A
Inputs:
- Project Statement of Work
- Business Case
- Contract
Outputs:
- Project Charter
2
Q
(4.2) Develop Project Management Plan
A
Inputs:
- Project Charter
- Outputs from Planning Processes
Outputs:
- Project Management Plan
3
Q
(4.3) Direct & Manage Project Execution
A
Inputs:
- Project Management Plan
- Approved Change Requests
Outputs:
- Deliverables
- Work Performance Information
- Change Requests
- Project Mgmt Plan Updates
- Project Document Updates
4
Q
(4.4) Monitor & Control Project Work
A
Inputs:
- Project Mgmt Plan
- Performance Reports
- EEF (Work Authorization System)
Outputs:
- Change Requests
- Project Mgmt Plan Updates
5
Q
(4.5) Perform Integrated Change Control
A
Inputs:
- Project Mgmt Plan
- Work Performance Information
- Change Requests
Outputs:
- Change Request Status Updates
- Project Management Plan Updates
6
Q
(4.6) Close Project or Phase
A
Inputs:
- Project Mgmt Plan
- Accepted Deliverables
Outputs:
- Final Product, Service, or Result Trans