Time management Flashcards

1
Q

Plan Schedule Management Input

A

Project Charter

Project Management Plan

  • Scope Management Plan
  • Development Approach

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan Schedule Management Tools and Techniques

A

Expert Judgement

Data Analysis

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan Schedule Management Output

A

Schedule Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define Activities Input

A

Project Management Plan

  • Scope Management Plan
  • Scope Baseline

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define Activities Tools and Techniques

A

Expert Judgement

Decomposition

Rolling Wave Planning

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Activities Output

A

Activity List

Activity Attributes

Milestone List

Change Requests

Project Management Plan updates

  • Schedule Baseline
  • Cost Baseline
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sequence Activities Input

A

Project Management Plan

  • Scope Management Plan
  • Scope Baseline

Project Documents

  • Activity Attributes
  • Activity List
  • Assumption Log
  • Milestone List

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Sequence Activities Tools and Techniques

A

Procedence Diagramming Method (PDM)

Dependency Determination

Leads and Lags

Project Management Information System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Sequence Activities Output

A

Project Schedule Network Diagram

Project Documents Updates

  • Activity Attributes
  • Activity List
  • Assumption Log
  • Milestone List
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate Activity Duration Input

A

Project Management Plan

  • Scope Management Plan
  • Scope Baseline

Project Documents

  • Activity Attributes
  • Activity List
  • Assumption Log
  • Lessons Learned Register
  • Milestone List
  • Project Team Assignment
  • Resource Breakdown Structure
  • Resource Calendars
  • Resource Requirements
  • Risk Register

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Estimate Activity Duration Tools and Techniques

A

Expert Judgement

Analogues Estimating

Parametric Estimating

Three-point Estimating

Bottom-up Estimating

Data Analysis

  • Alternative Analysis
  • Reserve Analysis

Decision Making

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate Activity Duration Output

A

Duration Estimates

Basis of Estimates

Project Documents updates

  • Activity Attributes
  • Assumption Log
  • Lessons Learned Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Develop Schedule Input

A

Project Management Plan

  • Scope Management Plan
  • Scope Baseline

Project Documents

  • Activity Attributes
  • Activity List
  • Assumption Log
  • Basis of estimates
  • Duration estimates
  • Lessons Learned Register
  • Milestone List
  • Project Schedule Network Diagrams
  • Resource Calendars
  • Resource Requirements
  • Risk Register

Agreements

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Develop Schedule Tools and Techniques

A

Schedule Network Analysis

Critical Path Method

Resource Optimization

Data Analysis

  • What-If Scenario Analysis
  • Simulation

Leads and Lags

Schedule compression

Project Management Information System

Agile release planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Develop Schedule Ouput

A

Schedule Baseline

Project Schedule

Schedule Data

Project Calendars

Change Requests

Project Management Plan updates

  • Schedule Management Plan
  • Cost Baseline

Project Documents updates

  • Activity Attributes
  • Assumption Log
  • Duration Estimates
  • Lessons Learned Register
  • Resource Requirement
  • Risk Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Control Schedule Input

A

Project Management Plan

  • Schedule Management Plan
  • Schedule Baseline
  • Performance Measurement Baseline

Project Documents

  • Lessons Learned Register
  • Project Calendars
  • Project Schedule
  • Resource Calendars
  • Schedule Data

Work Performance Data

Organizational Process Assets

17
Q

Control Schedule Tools and Techniques

A

Data Analysis

  • Earned Value Analysis
  • Iteration Burndown Chart
  • Performance Reviews
  • Trend Analysis
  • Variance Analysis
  • What-if Scenario Analysis

Critical Path Method

Project Management Information System

Resource Optimization

Leads and Lags

Schedule Compression

18
Q

Control Schedule Output

A

Data Analysis

  • Earned Value Analysis
  • Iteration Burndown Chart
  • Performance Reviews
  • Trend Analysis
  • Variance Analysis
  • What-if Scenario Analysis

Critical Path Method

Project Management Information System

Resource Optimization

Leads and Lags

Schedule Compression