Integration management Flashcards

1
Q

Develop Project Charter Input

A

Business Documents

  • Business Cases
  • Benefits Management Plan

Agreement

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Develop Project Charter Tools and Techniques

A

Expert Judgement

Data Gathering

  • Brainstorming
  • Focus Groups
  • Interviews

Interpersonal and team skills

  • Conflict Management
  • Facilitation
  • Meeting Management

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Develop Project Charter Output

A

Project Charter

Assumption Log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Develop Project Management Plan Input

A

Project Charter

Outputs from other processes

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop Project Management Plan Tools and Techniques

A

Expert Judgement

Data Gathering

  • Brainstorming
  • Checklists
  • Focus Groups
  • Interviews

Interpersonal and team skills

  • Conflict Management
  • Facilitation
  • Meeting Management

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Develop Project Management Plan Ouput

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Direct and Manage Project Work Input

A

Project Management Plan
- Any component

Project Documents

  • Change Log
  • Lesson Learned Register
  • Milestones List
  • Project Communications
  • Project Schedule
  • Requirement Traceability Matrix
  • Risk Register
  • Risk Report

Approved Changed Request

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Direct and Manage Project Work Tools and Techniques

A

Expert Judgement

Project Management Information System

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Direct and Manage Project Work Output

A

Deliverables

Work Performance Data

Issue Log

Change Requests

Proejct Management Plan updates
- Any component

Project Documents updates

  • Activity List
  • Assumption Log
  • Lesson Learned Register
  • Requirements Document
  • Risk Register
  • Stakeholder Register

Organizational Proess Assests updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Manage Project Knowledge Input

A

Project Management Plan
- All components

Project Documents

  • Lessons Learned Register
  • Project team assignment
  • Resource Breakdown Structure
  • Source Selection Criteria
  • Stakeholder Register

Deliverables

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Manage Project Knowledge Tools and Techniques

A

Expert Judgeent

Knowledge Management

Information Management

Interpersonal and team skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Manage Project Knowledge Output

A

Lessons learned register

Project Management Plan updates
- Any component

Organization Process Assets updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Monitor and Control Prj Work Input

A

Project Management Plan
- Any component

Project Documents

  • Assumption Log
  • Basis of estimates
  • Cost Forecasts
  • Issue Log
  • Lesson Learned Register
  • Milestone List
  • Quality Reports
  • Risk Register
  • Risk Report
  • Schedule Forecasts

Work Performance Information

Agreements

Enterprise Environmental Factors

Organizational Process Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Monitor and Control Prj Work Tools and Techniques

A

Expert Judgement

Data Analysis

  • Alternatives Analysis
  • Cost-benefit Analysis
  • Earned Value Analysis
  • Root Cause Analysis
  • Trend Analysis
  • Variance Analysis

Decision Making

Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Monitor and Control Prj Work Output

A

Work Performance Reports

Change Request

Project Management Plan updates
- Any component

Project Documents updates

  • Cost Forecasts
  • Issue Log
  • Lesson Learned Register
  • Risk Register
  • Schedule Forecasts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Perform Integrated Change Control Input

A

Project Management Plan

  • Change Management Plan
  • Configuration Management Plan
  • Scope Baseline
  • Schedule Baseline
  • Cost Baseline

Project Documents

  • Basis of estimates
  • Requirement Traceability Matrix
  • Risk Report

Work Performance Reports

Change Request

Enterprise Environmental Factors

Organizational Process Assets

17
Q

Perform Integrated Change Control Tools and Techniques

A

Expert Judgement

Change Control Tools

Data Analysis

  • Alternatives Analysis
  • Cost-benefit Analysis

Decision Making

  • Voting
  • Autocratic Decision Making
  • Multicriteria Decision Analysis

Meetings

18
Q

Perform Integrated Change Control Output

A

Approved Change Request

Project Management Plan updates
- Any component

Project Documents updates
- Change Log

19
Q

Close Prj or Prj Phase Input

A

Project Charter

Project Management Plan
- All components

Project Documents

  • Assumption Log
  • Basis of estimates
  • Change Log
  • Issue Log
  • Lesson Learned Register
  • Milestone List
  • Project Communications
  • Quality Control Measurements
  • Quality Report
  • Requirements Document
  • Risk Register
  • Risk Report

Accepted Deliverables

Business Documents

  • Business Case
  • Benefits Management Plan

Agreement

Procurement

Organizational Process Assets

20
Q

Close Prj or Prj Phase Tools and Techniques

A

Expert Judgement

Data Analysis

  • Document Analysis
  • Regresssion Analysis
  • Trend Analysis
  • Variance Analysis

Meetings

21
Q

Close Prj or Prj Phase Output

A

Project Documents Update
- Lesson Learned Register

Final Product, Service or Result Transition

Final Report

Organizational Process Assets updates