Time, Cost, Quality, Risk, Novation Flashcards

1
Q

What would you take into consideration when looking at Time?

A
  • How much time is there to prepare a complete design
  • When is the site available
  • When is the work required to be completed
  • What are the phasing or sectional requirements
  • The financial effect of a delayed completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What would you take into consideration when looking at Cost?

A
  • The impact of inflation over a lengthy contract period
  • The time of fixing the price of the works and certainty of out-turn costs
  • What level of risk is acceptable to the client
  • What level of risk is acceptable to the contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What would you take into consideration when looking at Quality / Performance?

A
  • Is retention of design control and important issue
  • Will the nature of the works require stringent supervision
  • Is the building listed or in a conservation area
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Novation?

A

• A new contract that transfers the rights and obligations of one contractual party to a new third party i.e. design rights and obligations of the architect transferred to the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

If the design team is novated, what should the client put in place?

A

A collateral warranty to the design team. Creates a contractual relationship between parties where there would otherwise not have been any.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

On Tolworth you undertook a tender analysis and prepared a tender report, explain the process of the analysis and the contents of the report.

A
  • Record on tender opening sheet (price and programme) at correct time and date
  • Check for errors and conflicts
  • Raise tender queries
  • Equalisation/ Normalisation
  • Agree cost with contractor
  • Recommendation
  • Notify tenderers of result
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How were tender queries dealt with both pre tender return and post?

A

I assembled a query sheet which i sent to each contractor. I then compiled all of the queries and answered them which was sent back to all contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did the scoring matrix you suggested to your client work? Was it just based on cost?

A

The scoring matrix was 65% cost and this was recommended because the works was of such a simple nature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was discussed at the procurement workshop for QL?

A

At the procurement workshop, I discussed with the client what their key drivers:
Time
Cost
Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you explain all the main procurement routes to your client for SWL?

A

By providing a matrix of priority based on:
Time
Cost
Quality
Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What did you advise on the scoring matrix for Tolworth?

A

I advised that due to the nature of the works, which was of a simple nature, and the client wanting to keep a tight budget, a competitive tender with 80% scoring would be best. The companies chosen for an expression of interest were known to the client and consultant team that were capable of producing works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What regulation does OJEU fall under?

A

Public contracts regulations 2015.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the OJEU threshold for works contracts?

A

£5.35m Works Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does a novation agreement look like?

A

Relinquish consultants of contractual relation to the client
Contractor responsibilities for performance prior to novation
CW Placed
Technical Design and beyond S4 Design
Develop in coordination with other disciplines

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Who takes the risk on design that has been undertaken prior to novation?

A

Dependent on what agreement states but my clients novation agreement states the contractor will take this risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly