P&T Document Questions Flashcards

1
Q

Why did you advise to opt for Design and Build on QL?

A
Time 
Cost 
Quality
Risk
Complexity
Certainty
Value
Appetite
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What was the process of your tender analysis?

A
Error check
PTQs
Normalisation 
Scoring
Recommendation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What did the matrix look like in your procurement report?

A

ANSWER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you carry out normalisation on Tolworth?

A

Raised any exclusions or missing items within tenders on PTQs to normalise as a first instance

If nothing returned:
Normalised on the average or highest allowance included in other tender returns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you deal with Provisional Sums during your tender analysis?

A

Tried to fix PS as much as possible to alleviate the risk and lack of cost certainty for my client, however, some prov sums could not be fixed.

All PS’ were defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What associated risks did you have when looking at your tenders?

A

Ground risk upto 2m was excluded, however, this was agreed with the contractor
S278 works
Levelling the site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Was your recommendation based purely on cost?

A

No, however, I assessed the commercial aspect with regards to cost and cost certainty and other disciplines looked at other criteria

How well did you know this?
1
Not at all
2
3
4
5
Perfectly