Q
Scope Baseline
A
The approved version of a scope statement, WBS, and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.
2
Q
stakeholder engagement plan
A
A component of project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project or program decision making and execution.
3
Q
Communications Management Plan
A
A component of project, program or portfolio management plan that describes how, when and by whom information about the project will be administered and disseminated.