Theme 3.3.4 Critical Path Analysis Flashcards

1
Q

What is meant by Critical Path Analysis?

A

The process of planning the sequence of activities in a project in order to identify the most efficient way of completing an integrated task or project in the shortest time possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is meant by an Earliest Start Time (EST)?

A

The earliest time that an activity can begin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is meant by the Latest Finish Time (LFT)?

A

This is the latest the activity can finish without making the project longer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is meant by a float time?

A

The float is the duration an activity can be extended or postponed so that the project still finishes within the minimum time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate this?

A

LFT - activity duration - EST + float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is meant by the critical path?

A

Activities with a float of zero cannot be delayed without delaying the entire project - these activities represent the “critical path”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you identify the critical path?

A

On the C.P, activities have an equal EST and LFT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Advantages of using Critical Path Analysis?

A
  • helps businesses meet deadlines - especially for time sensitive projects
  • some projects are expensive and complex, so CPA minimises risk of missing deadlines, and overspending
  • allows businesses to plan resources and build in contingencies - JIT/lean
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Disadvantages of using Critical Path Analysis?

A
  • unforeseen incidents can cause delays despite completing a CPA
  • time-consuming to complete
  • less necessary if the company is experienced in delivering similar projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How can critical path analysis enable a JIT approach to managing a project?

A

By planning when each activity is going to take place, the business can plan when they need the materials/ equipment e.g. if cement mixer is needed by week three, the business can plan ahead and also create a contingency plan if it doesn’t arrive on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly